Section 2: Basic Energy Economics Analysis - PowerPoint PPT Presentation

About This Presentation
Title:

Section 2: Basic Energy Economics Analysis

Description:

Title: Slide 1 Author: x Guo Last modified by: x Guo Created Date: 12/13/2005 3:35:23 PM Document presentation format: On-screen Show Company: QM Other titles – PowerPoint PPT presentation

Number of Views:140
Avg rating:3.0/5.0
Slides: 32
Provided by: xGu5
Category:

less

Transcript and Presenter's Notes

Title: Section 2: Basic Energy Economics Analysis


1
Section 2 Basic Energy Economics Analysis
Dr. Congxiao Shang Room No. 01 37P Email
c.shang_at_uea.ac.uk
ENV-2D02 (2006)Energy Conservation
2
2.1 Introduction
  • Decisions to an energy project should largely be
    made on the basis of economic analysis.
  • Imperfect analysis of energy issues can be
    flawed, and give misleading answers on decisions
    made.

?
A project costs 100 To implement
Viable
3
2.1 Introduction
  • An energy project should consider
  • - whether to promote energy conservation, i.e.
    energy saving,
  • - or to develop new energy resources, such as
    wind, tidal energy, solar, hydrogen and biofuels
    etc

Main objective To assess whether an energy
project is economically feasible.
4
2.1 Introduction
  • Decisions to an energy project should largely be
    made on the basis of economic analysis.
  • Imperfect analysis of energy issues can be
    flawed, and give misleading answers on decisions
    made.

?
A project costs 100 To implement
Viable
5
2.1 Introduction
  • Before answering the question correctly

Lets revise some concepts for simple cost
benefit analyses. Those who have done
Environmental Economics will know some
simplifications in what is described below.
6
2.2 Discount Rate
The concept of discount rate is introduced
because of the following facts
  • On the one hand, money borrowed to implement a
    project will incur interest charges which are
    compounded each year.
  • On the other, the value of money or saving
    declines with time, due to inflation.
  • To simplify the analysis, we use the present
    time as a reference for analysis (hence, interest
    charge is not an issue), the concept of a
    Discount Rate to account for inflation, and the
    Net Present Value (NPV) to evaluate the present
    value of future savings.

7
2.2 Discount Rates
  • The term, discount rate , is used to determine
    the present value of future cash flows arising
    from a project, i.e. the discounted value of
    future cashflows, due to inflation.
  • The actual value of the discount rate is
    equivalent to the basic interest rate that a
    high-street bank is charged to borrow funds
    directly from the Central Bank.

8
2.2 Discount Rates
  • We can analyse the economics of a project using
    the discount rate
  • in two ways
  • Individual discount approach
  • Cumulative discount approach

9
2.2 Discount Rates
  • The discount factor of the year n can be computed
    from the formula

The NPV( Net Present Value) (value of saving
in the year n) ? (the discount factor of the
year) reflects the value of the fuel saving
would have if it were accounted at the present
time rather than some years into the future. It
accounts for the effect of inflation.
10
2.2 Discount Rates
  • The discount factor of the year n can be computed
    from the formula
  • To sum up, the accumulated NPV fuel saving over
    the first five years is 86.59, which is still
    13.41 short of repaying the initial capital of
    100, i.e. a loss of 13.41, the project would
    not be viable
  • However, if the projects life span is 6 years
    with no further cost, the total NPV becomes 100
    1.51
  • For 7 years life span, the NPV 100 15.72,
    certainly viable!

11
2.2 Discount Rates
  • Cumulative discount approach

It gives the cumulative factor of discount up to
and including the year n. it is usually quicker
to use such values rather then some the
individual discount values as shown in the
previous table
12
2.2 Discount Rates
  • How to calculate Cumulative discount factors?

The Cumulative Discount Factor in year n is the
sum of all the discount factors from year 1 to
year n
The Cumulative NPV to year n is the sum of all
the NPVs of individual savings from year 1 to
year n or Annual saving x the Cumulative
Discount Factor
13
2.3 Project life and Choice of Discount Rate
  • Project Life depends on a number of factors
  • A single initial cost
  • Compensation factors, e.g. fuel price rises
  • Offsetting factors, e.g. maintenance charges
  • Competing schemes, e.g. a new process that gives
    more profit than the saving from the project, for
    the same initial investment

14
2.3 Project life and Choice of Discount Rate

15
2.3 Project Life and Choice of Discount Rate
  • Discount rates vary from time to time depending
    on the economic climate
  • Different organizations will set different target
    discount rates
  • 1) A higher discount rate 10 favours coal and
    fossil fired power generation.
  • 2) Moderate discount rates 5 tend to favour
    gas and nuclear options.
  • 3) Low discount rates, even zero, favour
    conservation and renewable energy.

16
2.4 Fuel Price Rises
  • 2.5 Negative Discount Rates

17
2.6 Internal Rate of Return (IRR)
At one discount rate, the NPV over the life of
the project is 0, this corresponds to the
Internal Rate of Return.
  • The figure shows the results of analyzing the
    example in 2.2 with differing discount rates for
    a project life of 7 years.
  • The NPV becomes zero for a discount rate of 9.2
    - the Internal Rate of return.
  • The graphical approach is much quicker to
    determine the IRR than a numeric method.

18
2.6 Internal Rate of Return (IRR)
  • The IRR is the discount rate that makes net
    present value of all cash flow equal zero or the
    project will break even.
  • If you apply a discount rate to future cashflows
    that is higher than the IRR, the project will
    make a loss in real terms. If you apply a
    discount that is lower than the IRR, the project
    will be profitable

Profitable
Non-profitable
19
2.7 The Changing Price Structure for Electricity
Gas
  • Electricity
  • Charges will be in three parts
  • 1.Charge to the Regional Electricity Company
    (REC) for transmission which will be the same for
    all suppliers
  • 2.Charges for the actual units used
  • 3.A charge for meter reading
  • Gas
  • Duel fuel

20
2.8 Trends in Energy Tariffs
  • In the case of electricity, the corresponding
    tariffs are (from WEB Site, 19th December 2005)

EDF Tariff
PowerGen Tariff
Scottish Power Tariff
21
2.8 Trends in Energy Tariffs
Comparison of three electricity tariffs
22
2.8 Trends in Energy Tariffs
In the case of gas, the corresponding tariff for
PowerGen (19th December 2005)
Unlike the electricity, the gas tariffs were more
uniform across the country. However, there are
variations recently due to competition introduced
to the distribution of gas as well
23
2.9 Some Examples on loft insulation
  • Example 1 Area of average house 49m2

Assume house with no loft insulation
Situation after insulation measures
Energy costs based on tariffs from Dec. 2003.
The differences indicate the rise in prices over
last two years.
24
2.9 Some Examples on loft insulation
Example 2 Area of average house 49m2 some
house with 50mm insulation already
  • Gas heated (condensing boiler) case again
  • Initial consumption will be 6.48 GJ (c.f. 30.6
    GJ) for pre-war house.
  • Initial annual consumption for post war house
    5.63 GJ (c.f. 17.8GJ)
  • NOTE you will be shown how
  • to calculate the values of 6.48
  • and 5.63 later in the course.

Calculation
25
2.11 Criteria for Investing in a Project
  • The project must have a net positive present
    value over its life span
  • The project has the most favourable rate of
    return when compared to other projects, or to
    direct investment (i.e. use IRR as an indicator
    here).
  • If money has to be borrowed to undertake the
    project, then the rate of return must be greater
    than the borrowing rate.
  • The rate of return must be significantly above
    the direct investment rate as capital is tied up
    and cannot be used for other things.

26
(No Transcript)
27
2.2 Discount Rates
  • Example of a compounded interest rate
  • A project is cost 100, borrowed at 5 interest
    rate

After one year
The total amount repaid 1001.05105
After two years
The total amount repaid 1051.05110.25
By the end of fifth year
The total amount repaid 100 1.055
127.63 not 100 5 100 5 125 in the
simple interest case
28
2.2 Discount Rates
Optional Information In fact a discount rate is
slightly different from the interest rate,
mathematically The discount rate is based on the
future cash flow in lieu of the present value of
the cash flow. E.g. we have 80, and we buy a
government bond that pays us 100 in a year's
time. The discount rate represents the discount
on the future cash flow (100-80)/100 20 The
interest rate on the cash flow is calculated
using 80 as its base (100-80)/80 25 Hence, for
every interest rate, there is a corresponding
discount rate, given by d i/(1i) Again when
referring to a cash flow being discounted, it
will likely refer to the interest rate and not
the proper mathematical discount rate. However,
the two are separate concepts in financial
mathematics.
29
2.10 Some Comments on these examples.
  • The examples show exactly how cost effective loft
    insulation can be particularly if there is no
    insulation to start with.
  • It pays to install thicker insulation at outset
    as it will be cost effective (even if there is no
    grant).
  • It becomes progressively uneconomic to upgrade
    insulation standards, and that if 100m already
    exists, it is not cost effective to upgrade, even
    though it is cost effective to put in 150mm from
    scratch
  • The present grant system is a disincentive to
    those who have spent money in the passed.
  • Grants of up to 90 are available for pensioners
  • It is argued that the poor cannot afford the
    capital outlay. The poor will not have
    condensing boilers, and are more than likely to
    have electric heating, and pay back is within a
    few weeks. With an extended 90 grant, the
    capital cost is no more than 10, so this can
    hardly be construed as a deterrent

Or see the lecture notes
30
Structure of Electricity Supply in early 1990s
?????????
??????? ??????????????? ? ?????? 1990
?.?.
Scotland ?????????
  • Scotland ?????????
  • Vertical Integration ???????????? ??????????
  • two companies ???
    ????????

England and Wales ?????? ? ????? 12
Regional Supply Companies 12 ????????????
???????? also Distributed Network Operators
? ?????
?????????????? ??????? ?????????
31
Distributed Network Ownership in 2004
Distributed Network Ownership in 2005
???????? ????????????????? ????? ?
2005
Regional Supply Ownership ???????? ????????????
???????????
PowerGen
Central Networks
Distributed Network Ownership ????????
????????????????? ????
Write a Comment
User Comments (0)
About PowerShow.com