Title: Section 2: Basic Energy Economics Analysis
1Section 2 Basic Energy Economics Analysis
Dr. Congxiao Shang Room No. 01 37P Email
c.shang_at_uea.ac.uk
ENV-2D02 (2006)Energy Conservation
22.1 Introduction
- Decisions to an energy project should largely be
made on the basis of economic analysis. - Imperfect analysis of energy issues can be
flawed, and give misleading answers on decisions
made.
?
A project costs 100 To implement
Viable
32.1 Introduction
- An energy project should consider
- - whether to promote energy conservation, i.e.
energy saving, - - or to develop new energy resources, such as
wind, tidal energy, solar, hydrogen and biofuels
etc
Main objective To assess whether an energy
project is economically feasible.
42.1 Introduction
- Decisions to an energy project should largely be
made on the basis of economic analysis. - Imperfect analysis of energy issues can be
flawed, and give misleading answers on decisions
made.
?
A project costs 100 To implement
Viable
52.1 Introduction
- Before answering the question correctly
Lets revise some concepts for simple cost
benefit analyses. Those who have done
Environmental Economics will know some
simplifications in what is described below.
62.2 Discount Rate
The concept of discount rate is introduced
because of the following facts
- On the one hand, money borrowed to implement a
project will incur interest charges which are
compounded each year. - On the other, the value of money or saving
declines with time, due to inflation. - To simplify the analysis, we use the present
time as a reference for analysis (hence, interest
charge is not an issue), the concept of a
Discount Rate to account for inflation, and the
Net Present Value (NPV) to evaluate the present
value of future savings.
72.2 Discount Rates
- The term, discount rate , is used to determine
the present value of future cash flows arising
from a project, i.e. the discounted value of
future cashflows, due to inflation. - The actual value of the discount rate is
equivalent to the basic interest rate that a
high-street bank is charged to borrow funds
directly from the Central Bank.
82.2 Discount Rates
- We can analyse the economics of a project using
the discount rate - in two ways
- Individual discount approach
- Cumulative discount approach
92.2 Discount Rates
- The discount factor of the year n can be computed
from the formula
The NPV( Net Present Value) (value of saving
in the year n) ? (the discount factor of the
year) reflects the value of the fuel saving
would have if it were accounted at the present
time rather than some years into the future. It
accounts for the effect of inflation.
102.2 Discount Rates
- The discount factor of the year n can be computed
from the formula
- To sum up, the accumulated NPV fuel saving over
the first five years is 86.59, which is still
13.41 short of repaying the initial capital of
100, i.e. a loss of 13.41, the project would
not be viable - However, if the projects life span is 6 years
with no further cost, the total NPV becomes 100
1.51 - For 7 years life span, the NPV 100 15.72,
certainly viable!
112.2 Discount Rates
- Cumulative discount approach
It gives the cumulative factor of discount up to
and including the year n. it is usually quicker
to use such values rather then some the
individual discount values as shown in the
previous table
122.2 Discount Rates
- How to calculate Cumulative discount factors?
The Cumulative Discount Factor in year n is the
sum of all the discount factors from year 1 to
year n
The Cumulative NPV to year n is the sum of all
the NPVs of individual savings from year 1 to
year n or Annual saving x the Cumulative
Discount Factor
132.3 Project life and Choice of Discount Rate
- Project Life depends on a number of factors
- A single initial cost
- Compensation factors, e.g. fuel price rises
- Offsetting factors, e.g. maintenance charges
- Competing schemes, e.g. a new process that gives
more profit than the saving from the project, for
the same initial investment
142.3 Project life and Choice of Discount Rate
152.3 Project Life and Choice of Discount Rate
- Discount rates vary from time to time depending
on the economic climate - Different organizations will set different target
discount rates - 1) A higher discount rate 10 favours coal and
fossil fired power generation. - 2) Moderate discount rates 5 tend to favour
gas and nuclear options. - 3) Low discount rates, even zero, favour
conservation and renewable energy. -
162.4 Fuel Price Rises
- 2.5 Negative Discount Rates
172.6 Internal Rate of Return (IRR)
At one discount rate, the NPV over the life of
the project is 0, this corresponds to the
Internal Rate of Return.
- The figure shows the results of analyzing the
example in 2.2 with differing discount rates for
a project life of 7 years. - The NPV becomes zero for a discount rate of 9.2
- the Internal Rate of return. - The graphical approach is much quicker to
determine the IRR than a numeric method.
182.6 Internal Rate of Return (IRR)
- The IRR is the discount rate that makes net
present value of all cash flow equal zero or the
project will break even. - If you apply a discount rate to future cashflows
that is higher than the IRR, the project will
make a loss in real terms. If you apply a
discount that is lower than the IRR, the project
will be profitable
Profitable
Non-profitable
192.7 The Changing Price Structure for Electricity
Gas
- Electricity
- Charges will be in three parts
- 1.Charge to the Regional Electricity Company
(REC) for transmission which will be the same for
all suppliers - 2.Charges for the actual units used
- 3.A charge for meter reading
- Gas
- Duel fuel
-
202.8 Trends in Energy Tariffs
- In the case of electricity, the corresponding
tariffs are (from WEB Site, 19th December 2005)
EDF Tariff
PowerGen Tariff
Scottish Power Tariff
212.8 Trends in Energy Tariffs
Comparison of three electricity tariffs
222.8 Trends in Energy Tariffs
In the case of gas, the corresponding tariff for
PowerGen (19th December 2005)
Unlike the electricity, the gas tariffs were more
uniform across the country. However, there are
variations recently due to competition introduced
to the distribution of gas as well
232.9 Some Examples on loft insulation
- Example 1 Area of average house 49m2
Assume house with no loft insulation
Situation after insulation measures
Energy costs based on tariffs from Dec. 2003.
The differences indicate the rise in prices over
last two years.
242.9 Some Examples on loft insulation
Example 2 Area of average house 49m2 some
house with 50mm insulation already
- Gas heated (condensing boiler) case again
- Initial consumption will be 6.48 GJ (c.f. 30.6
GJ) for pre-war house. - Initial annual consumption for post war house
5.63 GJ (c.f. 17.8GJ) -
- NOTE you will be shown how
- to calculate the values of 6.48
- and 5.63 later in the course.
Calculation
252.11 Criteria for Investing in a Project
- The project must have a net positive present
value over its life span - The project has the most favourable rate of
return when compared to other projects, or to
direct investment (i.e. use IRR as an indicator
here). - If money has to be borrowed to undertake the
project, then the rate of return must be greater
than the borrowing rate. - The rate of return must be significantly above
the direct investment rate as capital is tied up
and cannot be used for other things.
26(No Transcript)
272.2 Discount Rates
- Example of a compounded interest rate
- A project is cost 100, borrowed at 5 interest
rate
After one year
The total amount repaid 1001.05105
After two years
The total amount repaid 1051.05110.25
By the end of fifth year
The total amount repaid 100 1.055
127.63 not 100 5 100 5 125 in the
simple interest case
282.2 Discount Rates
Optional Information In fact a discount rate is
slightly different from the interest rate,
mathematically The discount rate is based on the
future cash flow in lieu of the present value of
the cash flow. E.g. we have 80, and we buy a
government bond that pays us 100 in a year's
time. The discount rate represents the discount
on the future cash flow (100-80)/100 20 The
interest rate on the cash flow is calculated
using 80 as its base (100-80)/80 25 Hence, for
every interest rate, there is a corresponding
discount rate, given by d i/(1i) Again when
referring to a cash flow being discounted, it
will likely refer to the interest rate and not
the proper mathematical discount rate. However,
the two are separate concepts in financial
mathematics.
292.10 Some Comments on these examples.
- The examples show exactly how cost effective loft
insulation can be particularly if there is no
insulation to start with. - It pays to install thicker insulation at outset
as it will be cost effective (even if there is no
grant). - It becomes progressively uneconomic to upgrade
insulation standards, and that if 100m already
exists, it is not cost effective to upgrade, even
though it is cost effective to put in 150mm from
scratch - The present grant system is a disincentive to
those who have spent money in the passed. - Grants of up to 90 are available for pensioners
- It is argued that the poor cannot afford the
capital outlay. The poor will not have
condensing boilers, and are more than likely to
have electric heating, and pay back is within a
few weeks. With an extended 90 grant, the
capital cost is no more than 10, so this can
hardly be construed as a deterrent
Or see the lecture notes
30Structure of Electricity Supply in early 1990s
?????????
??????? ??????????????? ? ?????? 1990
?.?.
Scotland ?????????
- Scotland ?????????
- Vertical Integration ???????????? ??????????
- two companies ???
????????
England and Wales ?????? ? ????? 12
Regional Supply Companies 12 ????????????
???????? also Distributed Network Operators
? ?????
?????????????? ??????? ?????????
31Distributed Network Ownership in 2004
Distributed Network Ownership in 2005
???????? ????????????????? ????? ?
2005
Regional Supply Ownership ???????? ????????????
???????????
PowerGen
Central Networks
Distributed Network Ownership ????????
????????????????? ????