Title: Project Manager


1
Project Hydro Gemini
  • Project Manager Wade Schlueter

2
Project Gantt Chart
  • This chart shows the summary tasks completed
  • Survey Entire Site, Clear/Prep Road, Clear rest
    of the site, Construction of the Admin Block and
    Power House

3
(No Transcript)
4
Project Gantt Chart
  • Summary and Subtasks in Red Change Requests
  • Summary and Subtasks in Blue Org. Baseline

5
Baseline Cost Report
6
Earned Value
7
Funding Requirements
  • Funds Project Tasks Timeline, (Total
    Time) Approx. Cost Funds to Disbursement
  • Disbursement 1 (32 days) 334,452
  • Survey the Entire Site Area - 5 days - 10,500
  • Clear and prep 2 km road - 12 days - 62,313
  • Clear the rest of the site - 15 days - 91,145
  • Disbursement 2 (29 days) 334,452
  • Construction -29 days - 475,807
  • Disbursement 3 (31 days) 334,452
  • Change Requests, part 1 -up to 31 of the 93 -
    284,963

8
Funding Requirements (Cont.)
  • Funds Project Tasks Timeline, (Total
    Time) Approx. Cost Funds to Disbursement
  • Disbursement 4 (30 days) 334,452
  • Change Requests, part 2 -32 to 62 of 93 days -
    284,963
  • Disbursement 5 (30 days) 334,452
  • Change Requests, part 3 -63 through 93 days -
    284,963
  • Disbursement 6 (35 days) 334,452
  • Residential Const., part 1 -up to 35 of 70
    days - 352,193
  • Disbursement 7 (35 days) 334,452
  • Residential Const., part 2 -36 through 70 days -
    352,193
  • Total Funds to be disbursed 2,341,164