Title: Earned Value Management
1Earned Value Management
Instructor Manfred Huber
- Partially adapted from Mike ODell. Some slides
in this presentation were originally developed by
Mr. Tom Rethard.
2Earned Value - What is it?
- Simply, it is a project monitoring and
measurement system that - establishes a clear relationship between planned
accomplishments and actual accomplishments - reinforces and rewards good planning practices
3Earned Value - What is it?
- Basic concepts of Earned Value Management (EVM)
- Each task in a project earns value as planned
work is completed - For example (perhaps), if you were paid on this
basis, you would earn at key milestones based
on the value of what you have completed (earned
value) - Earned value can be compared to actual cost and
budgeted cost to determine variance and predict
future performance
4Earned Value - What is it?
- The budgeted cost (e.g., dollars, person-hours,
person-days, etc.) in terms of your baseline
plan/budget of the work performed up to a
specified point in time - Also known as Budgeted Cost of Work Performed
(BCWP) - Each task in the Work Breakdown Structure (WBS)
is assigned a BCWP based on its individual cost. - Project BCWP is total of BCWP for all tasks
required to complete the project
5Earned Value Components
- Planned Value (a.k.a. BCWS)
- How much work (person-hours) you planned to have
accomplished at a given point in time (this is
from the WBS in your plan) - Actual Cost (a.k.a. ACWP)
- How much work (person-hours) you have actually
spent at a given point in time - Earned Value (a.k.a. BCWP)
- The value (person-hours) in terms of your base
budget of what you have accomplished at a given
point in time (or, complete X Planned Value)
6Earned Value Example
Today
18
8
14
- On Day X
- PLANNED VALUE (Budgeted cost of the work
scheduled, BCWS) - 18 10 16 6 50
- EARNED VALUE (Budgeted cost of the work
performed, BCWP) - 18 8 14 0 40
- ACTUAL COST (of the work performed , ACWP)
- 55 (from your project tracking - not evident in
above chart)
7Earned Value Example
Actual Cost what you have actually spent to
this point in time.
Today
Budgeted (Planned) Spending
Planned Value what your plan called for sending
on the tasks planned to be completed by this date.
Cost (Person-Hours)
Earned Value
Actual Spending
Earned Value value (cost) of what you have
accomplished to date, per the base plan.
Time (Date)
8Earned Value Example
Today
Budgeted (Planned) Spending
Cost (Person-Hours)
Earned Value
Actual Spending
Time (Date)
9Variance
- Any schedule or cost deviation from a specific
plan. - Used within an organization to verify the budget
and schedule for a project - Frequently used as a key component of plan
reviews and performance measurement
10Variance
- Must compare scheduling and budget variance at
the same time - Schedule variance deviations from work planned
not a measure of changes in cost - Cost variance deviations from the budget not
a measure of work scheduled vs. work completed - Example applying more /people to a task may
maintain the schedule, but it adds to cost
schedule on track over budget on expenses (cost)
11Performance Indices
- Cost Performance Index
- CPI BCWP/ACWP
- Schedule Performance Index
- SPI BCWP/BCWS
- Analysis
- CPI gt 1.0 ? exceptional performance
- CPI lt 1.0 ? poor performance
- Similar for SPI
12Quiz
- The EV measurement of work you planned to have
accomplished at a given point in time - BCWP
- ACSP
- BCWS
- ACWS
- True or False At any point in time, the SPI
tells you exactly how far ahead or behind
schedule you are on your project. - TRUE
- FALSE
13Quiz
- If BCWP is 20 pm and ACWP is 15 pm, CPI
- .75
- 1.33
- 1.0
- 0
- If BCWP is 27 pm BCWS is 25 pm, you are probably
- On schedule
- Ahead of schedule
- Behind schedule
- None of the above
14Earned Value Variance Example
- On Day X
- PLANNED VALUE (BCWS) 18 10 16 6 50
- EARNED VALUE (BCWP) 18 8 14 0 40
- ACTUAL COST (ACWP) 55 (from your project
tracking) - Therefore
- Schedule Variance BCWP BCWS 40 - 50 -10
(behind schedule) - Schedule Performance Index 40 / 50 0.8, or
80 of plan (a B-, at best) - Cost Variance BCWP - ACWP 40 - 55 -15
- Cost Performance Index 40/55 .73, or youre
getting an 73 return on every 1.00 (or,
person-hour) spent on this project
15Primary Measurement Methods
- Measurable efforts
- Discrete increments of work with definable
schedule and tangible results (i.e., real tasks
with a deliverable) - Level of effort
- Work that is not discernable in discrete,
measurable tasks (e.g., project management,
training)
16Determining Complete When?
- Allocate based on time spent but what if you
spend more time than allocated? - Allocate 50 at start of task, 50 at end
- But only for small, discrete tasks
- Allocate 100 at start of task
- Allocate 100 at end of task
- Best solution if you keep tasks very small
- Allocate value at Critical Milestones
- Good solution when using with contract work
- Others?
Our approach
17Another Example Project
- Plans to spend 100K in each of first 4 weeks
(baseline budget, per documented plan) - Actuals, at end of week 4 show 325K spent
- BCWS 400K (100K x 4)
- ACWP 325K
- What conclusions can you draw?
- Under budget?
- Is project on schedule?
18Another Example Project
- Suppose BCWP is 300K
- How is this determined?
- What conclusions now?
- SV BCWP BCWS
- SV 300k - 400K -100K
- Behind schedule, but what does the 100K in
variance really mean? - CV BCWP ACWP 300K - 325K
- Over budget by 25K
19Earned Value Management
- How can you use this information?
- Careful analysis of variance and trends
- Resetting schedule or budget, when appropriate
- Variance Analysis Questions
- What is the problem causing the variance?
- What is the impact on time, cost and performance?
- What is the impact on other efforts, if any?
- What corrective action is planned or under way?
- What are the expected results of the corrective
action?
20Earned Value Management
- Extraordinary variance or alarming trends may be
cause for reset or cancellation of a project, but
where do you draw the line? - How much variance to allow depends on a number of
factors - Life-cycle phase
- Length of life-cycle phase
- Length of project
- Type of estimate
- Accuracy of estimate
21Variance Projection
22Performance Index Trends
23Ideal Performance Index
24Closing Thoughts Management Reserve
- The padding always added to a project for
unexpected costs that are within project scope - Not an allowance for changes to scope
- Not part of the cost estimate
- Added by upper management, not the project
manager.
25Closing Thoughts Government Requirements
- U.S. government contract cost tracking often must
include - BCWS
- BCWP
- ACWP
- Estimated cost at completion
- Budgeted cost at completion
- Cost and schedule variances with explanations
- Traceability
26Summary
- Cost, in the form of Earned Value or BCWP, can be
used to analyze progress of a project - Using Earned Value data to make critical project
decisions must be based on careful analysis of
data, variances and trends