Bellingham - PowerPoint PPT Presentation

About This Presentation
Title:

Bellingham

Description:

Leslee Shumway Olympic Pipeline Control Center Events Computer Operations The system administrator in the computer room had no formal SCADA ... – PowerPoint PPT presentation

Number of Views:81
Avg rating:3.0/5.0
Slides: 13
Provided by: nts59
Learn more at: https://www.ntsb.gov
Category:

less

Transcript and Presenter's Notes

Title: Bellingham


1
Leslee Shumway
Olympic Pipeline Control Center Events
2
Timeline of Control Center Events 10 June 1999
3
Timeline of Control Center Events,continued
4
Timeline of Control Center Events,continued
5
(No Transcript)
6
Bayview Pressure Trend Data
7
Timeline of Control Center Events, Continued
8
Computer Operations
  • The system administrator in the computer room had
    no formal SCADA training.

9
  • The system administrator should have notified his
    supervisor and the controllers when computer
    error messages first appeared.
  • He should not have left the computer room until
    his supervisor became available.

10
Computer Database Revisions
  • New records added to the primary on-line SCADA
    computer caused both computers to fail.
  • These SCADA database revisions were performed
    without prior testing.

11
  • SCADA computer changes should be implemented and
    thoroughly tested on an off-line system.

12
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com