Title: PACIFIC TEAM SPRING QUARTER PRESENTATION
1 PACIFIC TEAM SPRING QUARTER PRESENTATION
2 TEAM MEMBERS
TONIE GARZA ARCHITECT
PETER DEMIAN STRUCTURAL ENGINEER
JOHN ENGSTROM CONSTRUCTION MANAGER
Owners
ASAKO AKAZAWA APPRENTICE
Robert Alvarado Industry Owner
Mr. Kozakai Japan
3Outline of Presentation
Project Introduction Winter Quarter
Alternatives A-E-C Iterations and
Resolutions Architectural Review Structural
Review Construction Review Collaboration and
Group Dynamics
4A E C
Team Dynamics
- Lessons from Winter Quarter
- Be more honest in our interactions
- Meet more frequently
- Increase the teams interaction with the owner
5Team Dynamics
- Spring Quarter Improvements?
- Interaction was more active
- The group met more frequently (at least twice per
week) - Interactions with the owner were not increased
significantly - The group developed a better understanding of the
disciplines - Our individual project decisions were more
disciplined based
6Project Information
The Engineering School of Pacific
University Location Oregon Coast Year
2010 Square Footage 30,000 sf. Budget
5,500,000
7A E C
Site Layout
8A E C
Design Alternatives
9A E C
Design Alternatives
- Good forms.
- Slightly predictable.
- No clear architectural intent.
A
DESIGN ALTERNATIVES
- Simple Frame.
- Potential problems with columns.
E
C
10A E C
Design Alternatives
Large beam span in auditorium may pose some
significant challenges. Standard grid allows for
little variation in building skin.
A
C
Concurrent construction 4.8M
E
Simple layout due to grid format
11DESIGN ALTERNATIES
A E C
Design Alternatives
A
- Initial reaction to conceptual beginning.
Challenging and intriguing structural system.
Exceeds structural budget. 5.9M
E
C
12A E C
Design Alternatives
Remains close to conceptual ideas while at the
same time addressing programmatic requirements
A
Best combination of structural and architectural
requirements.
Presents challenges to all disciplines while
staying within the budget. 5.5M
E
C
13A E C
Proposal Recommendation
PROPOSAL 4 - The Crystal Palace
14The Design
151st Floor Plan Layout
162nd Floor Plan Layout
173rd Floor Plan Layout
18Programmatic Changes
Iteration 1
Iteration 2
19 Circulation vs. Used Space
circulation
used
Iteration 1
Iteration 2
20Area Designated by Use
21Level 3
Level 2
Level 1
22Atrium Lighting
Evening light study
Morning light study
233D Renderings
Building main entry -Evening and afternoon light
243D Renderings
Northeast façade Overhangs
25Future Design Proposal
26A E C
- Concrete - to reflect architectural bunker
concept - Post-tensioned flat slab with drop panels
- Shear walls - seismic Zone 3, lateral strength
for earthquake loads - large spans span/depth38
- gravity loads dead 100 psf
- live 50 psf (office)
- 100 psf (computer lab)
- earthquake load UBC 94 Zone 3 Design Spectrum
27- Put picture of structure here
28(No Transcript)
29Columns / Foundations
A E C
PROPOSAL 3 - The Bunker
- Interior columns
- circular, 20 diameter, 3 reinforcement, carries
axial load, very small moments - drop panels 3 diameter by 8 deep
- Exterior columns (corners and sides)
- 24 square, 6-8 reinforcement
- drop panels 4 square by 8 deep
30Slab
A E C
- 12 in thick PT slab
- PT details here
- shear moment
31Column to Slab Connection
A E C
32Shear Walls
A E C
- 4 exterior walls 20 thick by 12 long
- thick than necessary to compliment architectural
concept - shear wall combined with adjacent column.
Column acts as a column for out-of-plane
bending, and as a shear wall boundary element for
in-plane bending. - Connection subtleties
33Shear Wall to Slab Connection
A E C
34Old Atrium
A E C
Moment resisting Frames
Complex joint between two different slab systems
Roof/ slab interaction
Struts for lateral support
35Atrium New
A E C
36Seismic Analysis
A E C
Floor Displacements and Drifts
- UBC 94 Design Spectra not site-specific
- Period of structure 0.3 seconds
37Slab Deflections, Vibrations - Potential Problem?
A E C
- Large spans - large deflections
- UBC limit l/480 ? 1in
- Max displacement from approximate computer model
2 in - Vibrations more difficult to analyze. Further
investigation required.
38Construction Summary
A E C
Construction
- Concrete CIP Structure
- Rock Excavation
- Slab Overhangs and Pre-cast
- Atrium Glass Curtain Wall
39A E C
Site Layout
40A E C
Estimate
Cost 4.9M (161/sf)
41A E C
Excavation Costs
- Discovery of Rock on Site significantly increased
the unit cost of excavation. - This was mitigated by
- Reducing floor-to-floor heights and eliminating a
submerged 1st level. - This reduced the amount of excavation by over
half (still need auditorium and large classrooms - Ancillary effect was to reduce the size of
footings
42A E C
Slab Costs /sf
43A E C
Schedule
Completion September 12, 2012
44A E C
Milestones
Exterior Closure May 24, 2012
Superstructure April 12, 2012 (5.5 Months)
45A E C
MEP Systems
- Mild Climate
- Exposed system important for architecture
- Standard Design
- Air Handler, Chiller, Boiler configuration
46A E C
HVAC Distribution
A-C Iteration MEP Rooms centrally located
E-C Iteration Holes in the Slab Next to Elevator
Shaft
47(No Transcript)
48AEC Interaction
A
E/ C
Atrium
AEC Interaction
E/ C
A
Overhangs
A
E
Shear Walls
49AEC Interaction
A
E/ C
Atrium
AEC Interaction
50AEC Interaction
A
E/ C
Overhangs
AEC Interaction
51A
E
Shear Walls
52Value of Course
- Architect
- Cross-Disciplinary
- Construction Manager focus on work efficiency
- Engineer assumption about architectural
understanding of structure - Take Home Lesson
- The more sketching I do, the more questions E
CM will want answered.
53Value of Course
- Engineer
- Cross-Disciplinary
- Understanding the importance of structural
concept - Appreciate the scheduling/financial aspects of CM
- Take Home Lesson
- Every structural decision will effect other
disciplines
54Value of Course
- Construction Manager
- Cross-Disciplinary
- Conceptual architecture is difficult to grasp.
- 3D Model is essential to facilitate communication
- Take Home Lesson
- Design is never complete, it is simply abandoned.
- Pay attention to the gap between conceptual phase
and detail phase
55The End