Linear Programming - PowerPoint PPT Presentation

1 / 53
About This Presentation
Title:

Linear Programming

Description:

Title: PowerPoint Presentation Author: Salman Azhar Last modified by: vaio Created Date: 2/8/2001 7:27:30 PM Document presentation format: On-screen Show (4:3) – PowerPoint PPT presentation

Number of Views:71
Avg rating:3.0/5.0
Slides: 54
Provided by: Salm66
Category:

less

Transcript and Presenter's Notes

Title: Linear Programming


1
Chapter 2 Linear Programming
Dr. Alaa Sagheer 2010-2011
2
Chapter Outline
Part I
  • Introduction
  • The Linear Programming Model
  • Examples of Linear Programming Problems
  • Developing Linear Programming Models
  • Graphical Solution to LP Problems

3
Introduction
  • Mathematical programming is used to find the best
    or optimal solution to a problem that requires a
    decision or set of decisions about how best to
    use a set of limited resources to achieve a state
    goal of objectives.
  • Steps involved in mathematical programming
  • Conversion of stated problem into a mathematical
    model that abstracts all the essential elements
    of the problem.
  • Exploration of different solutions of the
    problem.
  • Finding out the most suitable or optimum
    solution.
  • Linear programming requires that all the
    mathematical functions in the model be linear
    functions.

4
Introduction
Example The Burroughs garment company
manufactures men's shirts and womens blouses for
Walmark Discount stores. Walmark will accept all
the production supplied by Burroughs. The
production process includes cutting, sewing and
packaging. Burroughs employs 25 workers in the
cutting department, 35 in the sewing department
and 5 in the packaging department. The factory
works one 8-hour shift, 5 days a week. The
following table gives the time requirements and
the profits per unit for the two garments
5
Introduction
Minutes per unit
Garment Cutting Sewing Packaging Unit profit()
Shirts 20 70 12 8.00
Blouses 60 60 4 12.00
Determine the optimal weekly production schedule
for Burroughs.
6
Introduction
Solution Assume that Burroughs produces x1
shirts and x2 blouses per week
8 x1 12 x2
Profit got
Time spent on cutting
20 x1 60 x2 mts
Time spent on sewing
70 x1 60 x2 mts
Time spent on packaging
12 x1 4 x2 mts
7
Introduction
The objective is to find x1, x2 so as to maximize
the profit z 8 x1 12 x2 satisfying the
constraints
20 x1 60 x2 25 ? 40 ? 60 70 x1 60 x2
35 ? 40 ? 60 12 x1 4 x2 5 ? 40 ? 60
x1, x2 0, integers
8
Introduction
This is a typical optimization problem
Any values of x1, x2 that satisfy all the
constraints of the model is called a feasible
solution. We are interested in finding the
optimum feasible solution that gives the maximum
profit while satisfying all the constraints.
9
The Linear Programming Model
  • Let x1, x2, x3, , xn are decision
    variables and
  • Z Objective function or linear
    function
  • Requirement Maximization of the linear function
    Z
  • Z c1x1 c2x2 c3x3 cnxn
  • subject to the following constraints

where aij, bi, and cj are given constants.
10
The Linear Programming Model
  • The linear programming model can be written in
    more efficient notation as

The decision variables, xI, x2, ..., xn,
represent levels of n competing activities
11
The Linear Programming Model
An LPP satisfies the three basic properties
1. Proportionality It means, the contributions
of each decision variable in the objective
function and its requirements in the constraints
are directly proportional to the value of the
variable
2. Additivity This property requires the
contribution of all the variables in the
objective function and its constraints to be the
direct sum of individual contributions of each
variables.
3. Certainty All the objective and constraint
coefficient of the LP model are deterministic.
This mean that they are known constants- a rare
occurrence in real life.
12
Examples of LP Problems
1. A Product Mix Problem
  • A manufacturer has fixed amounts of different
    resources such as raw material, labor, and
    equipment.
  • These resources can be combined to produce any
    one of several different products.
  • The quantity of the ith resource required to
    produce one unit of the jth product is known.
  • The decision maker wishes to produce the
    combination of products that will maximize total
    income.

13
Examples of LP Problems
2. A Blending Problem
  • Blending problems refer to situations in which a
    number of components (or commodities) are mixed
    together to yield one or more products.
  • Typically, different commodities are to be
    purchased. Each commodity has known
    characteristics and costs.
  • The problem is to determine how much of each
    commodity should be purchased and blended with
    the rest so that the characteristics of the
    mixture lie within specified bounds and the total
    cost is minimized.

14
Examples of LP Problems
3. A Production Scheduling Problem
  • A manufacturer knows that he must supply a given
    number of items of a certain product each month
    for the next n months.
  • They can be produced either in regular time,
    subject to a maximum each month, or in overtime.
    The cost of producing an item during overtime is
    greater than during regular time. A storage cost
    is associated with each item not sold at the end
    of the month.
  • The problem is to determine the production
    schedule that minimizes the sum of production and
    storage costs.

15
Examples of LP Problems
4. A Transportation Problem
  • A product is to be shipped in the amounts al, a2,
    ..., am from m shipping origins and received in
    amounts bl, b2, ..., bn at each of n shipping
    destinations.
  • The cost of shipping a unit from the ith origin
    to the jth destination is known for all
    combinations of origins and destinations.
  • The problem is to determine the amount to be
    shipped from each origin to each destination such
    that the total cost of transportation is a
    minimum.

16
Examples of LP Problems
5. A Flow Capacity Problem
  • One or more commodities (e.g., traffic, water,
    information, cash, etc.) are flowing from one
    point to another through a network whose branches
    have various constraints and flow capacities.
  • The direction of flow in each branch and the
    capacity of each branch are known.
  • The problem is to determine the maximum flow, or
    capacity of the network.

17
Developing LP Model
  • The variety of situations to which linear
    programming has been applied ranges from
    agriculture to zinc melting.
  • Steps Involved
  • Determine the objective of the problem and
    describe it by a criterion function in terms of
    the decision variables.
  • Find out the constraints.
  • Do the analysis which should lead to the
    selection of values for the decision variables
    that optimize the criterion function while
    satisfying all the constraints imposed on the
    problem.

18
Developing LP Model
Graphical Solution
Example Product Mix Problem
The N. Dustrious Company produces two products I
and II. The raw material requirements, space
needed for storage, production rates, and selling
prices for these products are given in Table I.
The total amount of raw material available per
day for both products is 15751b. The total
storage space for all products is 1500 ft2, and a
maximum of 7 hours per day can be used for
production.
19
Developing LP Model
Example Product Mix Problem
All products manufactured are shipped out of the
storage area at the end of the day. Therefore,
the two products must share the total raw
material, storage space, and production time. The
company wants to determine how many units of each
product to produce per day to maximize its total
income
Solution
  • The company has decided that it wants to maximize
    its sale income, which depends on the number of
    units of product I and II that it produces.
  • Therefore, the decision variables, x1 and x2 can
    be the number of units of products I and II,
    respectively, produced per day.

20
Developing LP Model
  • The object is to maximize the equation
  • Z 13x1 11x2
  • subject to the constraints on storage space, raw
    materials, and production time.
  • Each unit of product I requires 4 ft2 of storage
    space and each unit of product II requires 5 ft2.
    Thus a total of 4x1 5x2 ft2 of storage space is
    needed each day. This space must be less than or
    equal to the available storage space, which is
    1500 ft2. Therefore,
  • 4X1 5X2 ? 1500
  • Similarly, each unit of product I and II produced
    requires 5 and 3 1bs, respectively, of raw
    material. Hence a total of 5xl 3x2 Ib of raw
    material is used.

21
Developing LP Model
  • This must be less than or equal to the total
    amount of raw material available, which is 1575
    Ib. Therefore,
  • 5x1 3x2 ? 1575
  • Prouct I can be produced at the rate of 60 units
    per hour. Therefore, it must take I minute or
    1/60 of an hour to produce I unit. Similarly, it
    requires 1/30 of an hour to produce 1 unit of
    product II. Hence a total of x1/60 x2/30 hours
    is required for the daily production. This
    quantity must be less than or equal to the total
    production time available each day. Therefore,
  • x1 / 60 x2 / 30 ? 7
  • or x1 2x2 ? 420
  • Finally, the company cannot produce a negative
    quantity of any product, therefore x1 and x2 must
    each be greater than or equal to zero.

22
Developing LP Model
Graphical Solution
  • The linear programming model for this example can
    be summarized as

23
Developing LP Model
Graphical Solution
Example (2) Reddy Mikks produce both interior
and exterior paints from two raw materials, M1
and M2. The following table provides the basic
data of the problem
24
Developing LP Model
Example Problem
A market survey indicates that the daily demand
for the interior paint cannot exceed that for
extirior paint by more than one ton. Also, the
maximam daily demand for the interior paint is 2
tons. Reddy Mikks wants to determine the
optimum(best) product mix of the interior and
exterior paints that maximizes the total daily
profit.
Solution
  • Reddy Mikks has decided that it wants to maximize
    its total daily profit, which depends on the
    product mix of the interior and exterior paints.
  • Therefore, the decision variables, x1 and x2 can
    be the ton of exterior and interior paints,
    respectively, produced per day.

25
Developing LP Model
  • The object is to maximize the equation
  • Z 5x1 4x2
  • The daily raw material M1 is 6tons per ton of
    exterior paint and 4 tons per ton of interior
    paint must be equal the daily avaliability of raw
    material M1 (24 ton) , Therefore,
  • 6x1 4x2 ? 24
  • Similary, The daily usage of raw material M2 is
    1ton per ton of exterior paint and 2 tons per ton
    of interior paint must be equal the daily
    aviliability or raw material M2 (6 tons),
    Therefore,
  • x1 2x2 ? 6

26
Developing LP Model
  • The first demand restriction stipulates that the
    excess the daily production of interior over
    exterior paint should not exceed 1 ton, Therefore
    ,
  • x2 - x1 ? 1
  • The second demand restrection stipulates that the
    maximum daily demand of interior paint is limited
    to 2 tons. Therefore,
  • x2 ? 2

27
Developing LP Model
Graphical Solution
  • The linear programming model for this example can
    be summarized as

28
Developing LP Model
Example (3)
Wild West produces two types of cowboy hats. Type
I hat requires twice as much labor as a Type II.
If all the available labor time is dedicated to
Type II alone, the company can produce a total of
400 Type II hats a day. The respective market
limits for the two types of hats are 150 and 200
hats per day. The profit is 8 per Type I hat and
5 per Type II hat. Formulate the problem as an
LPP so as to maximize the profit.
29
Developing LP Model
Solution Assume that Wild West produces x1
Type I hats and x2 Type II hats per day.
8 x1 5 x2
Per day Profit got
Assume the time spent in producing one type II
hat is c minutes.
Labour Time spent is
(2 x1 x2) c minutes
30
Developing LP Model
The objective is to find x1, x2 so as to
maximize the profit z 8 x1 5 x2
satisfying the constraints
(2 x1 x2 ) c 400 c x1
150 x2 200 x1, x2
0, integers
31
Developing LP Model
Example (4)
BITS wants to host a Seminar for five days. For
the delegates there is an arrangement of dinner
every day. The requirement of napkins during the
5 days is as follows
Day 1 2 3 4 5
Napkins Needed 80 50 100 80 150
32
Developing LP Model
Institute does not have any napkins in the
beginning. After 5 days, the Institute has no
more use of napkins. A new napkin costs Rs.
2.00. The washing charges for a used one are Rs.
0.50. A napkin given for washing after dinner is
returned the third day before dinner. The
Institute decides to accumulate the used napkins
and send them for washing just in time to be used
when they return. How shall the Institute meet
the requirements so that the total cost is
minimized ? Formulate as a LPP.
33
Developing LP Model
Solution Let xj be the number of napkins
purchased on day j, j1,2,..,5 Let yj be the
number of napkins given for washing after dinner
on day j, j1,2,3 Thus we must have
x1 80, x2 50, x3 y1 100, x4 y2 80 x5
y3 150
Also we have y1 80, y2 (80 y1) 50
y3 (80 y1) (50 y2) 100
34
Developing LP Model
Thus we have to Minimize z 2(x1x2x3x4x5)0.
5(y1y2y3) Subject to x1 80, x2 50, x3
y1 100, x4 y2 80, x5
y3 150, y1 80,
y1y2 130, y1y2y3 230,
all variables 0, integers
35
Developing LP Model
Example (5)
A Post Office requires different number of
full-time employees on different days of the
week. The number of employees required on each
day is given in the table below. Union rules say
that each full-time employee must receive two
days off after working for five consecutive days.
The Post Office wants to meet its requirements
using only full-time employees. Formulate the
above problem as a LPP so as to minimize the
number of full-time employees hired.
36
Developing LP Model
Requirements of full-time employees day-wise
Day No. of full-time employees required
1 - Monday 10
2 - Tuesday 6
3 - Wednesday 8
4 - Thursday 12
5 - Friday 7
6 - Saturday 9
7 - Sunday 4
37
Developing LP Model
Solution Let xi be the number of full-time
employees employed at the beginning of day i (i
1, 2, , 7). Thus our problem is to find xi so
as to
Minimize
Subject to
38
The Graphical Solution
  1. The determination of the solution space that
    defines the feasible solutions that satisfy all
    the constrains of the model.
  2. The determination of the optimum solution from
    among all the points in the feasible solution
    space.

39
Graphical LP Solution Model
Example
Electra produces two types of electric motors,
each on a separate assembly line. The respective
daily capacities of the two lines are 150 and 200
motors. Type I motor uses 2 units of a certain
electronic component, and type II motor uses
only 1 unit. The supplier of the component can
provide 400 pieces a day.The profits per motor of
types I and II are 8 and 5 respectively.
Formulate the problem as a LPP and find the
optimal daily production.
40
Graphical LP Solution Model
Let the company produce x1 type I motors and x2
type II motors per day.
The objective is to find x1 and x2 so as to
Maximize the profit
Subject to the constraints
41
Graphical LP Solution Model
Step 1 Determination of the Feasible solution
space
The non-negativity restrictions tell that the
solution space is in the first quadrant. Then we
replace each inequality constraint by an equality
and then graph the resulting line (noting that
two points will determine a line uniquely).
Step 2 Determination of the optimal solution
The determination of the optimal solution
requires the direction in which the objective
function will increase (decrease) in the case of
a maximization (minimization) problem. We find
this by assigning two increasing (decreasing)
values for z and then drawing the graphs of the
objective function for these two values. The
optimum solution occurs at a point beyond which
any further increase (decrease) of z will make us
leave the feasible space.
42
Graphical solution
x2
Maximize z8x15x2
Subject to the constraints
Optimum 1800 at
2x1x2 ? 400 x1 ? 150 x2 ? 200
x1,x2? 0
(100,200)
(0,200)
z1200
(150,100)
z1800
z1000
x1
z1700
z400
(150,0)
43
Graphical LP Solution Model
Realted to Reddy Mikks problem
Problem
44
Graphical Solution to LP Problems
Related to Product Mix Problem
Problem
45
Graphical LP Solution Model
Feed Mix Problem Minimize z 2x1 3x2 Subject
to x1 3 x2 ? 15 2 x1 2 x2
? 20 3 x1 2 x2 ? 24
x1, x2 ? 0
46
Graphical Solution of Feed Mix Problem
(0,12)
z 26
z 30
z 36
z 39
(4,6)
z 42
z 22.5
(7.5,2.5)
(15,0)
Minimum at
47
Graphical LP Solution Model (5)
Maximize z 2x1 x2 Subject to x1 x2
40 4 x1 x2 100
x1, x2 0
Optimum 60 at (20, 20)
48
(No Transcript)
49
The Graphical Solution
Graphical Solution
Ozark farms uses at least 800 Ib of special feed
is a mixture of corn and soybean meal with the
following compositions
The dietary requirement of the special feed are
at least 30 protein and at most 5 fiber. Ozark
Farms wishes to determine the daily minimm- cost
feed mix.
50
The Graphical Solution
Graphical Solution
Solution
We can consider that,
And the objective function seeks to minimize the
total daily cost (in dollars) of the feed mix and
is thus expressed as
Subject to constrains
51
The Graphical Solution
  • Unlike previous examples, the second and the
    third constraints pass through the origin. To
    plot associated straight lines, we need one
    additional point, which can be obtained by
    assigning value to one of the variables and then
    solving for other variables. For example, in the
    second constraint, x1200, then x2140

52
The Graphical Solution
Problem
53
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com