Title: Pete 552
1PETE 450 Introduction to Geothermal Reservoir
Engineering Electricity Generation Dr. Mahmut
Parlaktuna
2- Most power plants need steam to generate
electricity - The steam rotates a turbine that activates a
generator, which produces electricity - Geothermal power plants use steam produced from
geothermal reservoirs
3- There are three types of geothermal power plants
- Dry steam
- Flash steam
- Binary cycle
4Dry Steam Power Plant
- Dry steam power plants draw from underground
resources of steam. The steam is piped directly
from underground wells to the power plant, where
it is directed into a turbine/generator unit.
5Dry Steam Power Plant
- The dry steam power plant is suitable where the
geothermal steam is not mixed with water.
Production wells are drilled down to the aquifer
and the superheated, pressurised steam (180 -
350 C) is brought to the surface at high
speeds, and passed through a steam turbine to
generate electricity.
Schematic of a Dry Steam Power Plant
6Dry Steam Power Plant
- The first geothermal power generation plant from
dry steam was constructed in 1904 in Larderello,
Italy. This had a capacity of 250kW.
7Larderello
The first modern geothermal power plants were
also built in Larderello, Italy. They were
destroyed in World War II and rebuilt. Today
after 100 years, the Larderello field is still
producing.
8Larderello
Larderello Landscape
9Larderello
Cooling Towers
10Larderello
Steam vent
11The Geysers
Geysers Power Plant
12The Geysers
- Full-scale commercial development began by 1955,
and the 11-megawatt (MW) Geysers Unit 1 power
plant was commissioned in 1960. By 1989,
installed generating capacity at The Geysers was
1,967 MW. Since 1987, The Geysers has experienced
a decline in steam pressure and electricity
production that has coincided with older power
plants in the area reaching the end of their
useful lives. Initial pressure in most Geysers
production wells was above 500 psi, but by the
mid-1990s many fell below 200 psi. And because
pressure determines production rate, it is no
longer practical in most areas of The Geysers to
drill new wells to supplement steam supply.
13The Geysers
- The Lake County-Southeast Geysers Effluent
Pipeline Project begins operations in 1997. The
pipeline project is the first wastewater-to-electr
icity project in the world. The 29-mile
underground pipeline delivers eight million
gallons of treated reclaimed water to The Geysers
everyday to be recycled into the geothermal
resource.
14The Geysers
- The Santa Rosa Geysers Recharge Project is
selected to transport 11 million gallons of
treated reclaimed water per day to The Geysers
through a 41-mile underground pipeline, 1998.
Water is recycled back into the ground, heated,
and used at steam to power the plants.
15The Geysers
16The Geysers
17The Geysers
The first geothermal power plants at The Geysers
dry steam field were built in 1962. It is still
the largest producing geothermal field in the
world.
18The Geysers
20 plants are still operating at The Geysers.
Wastewater from nearby cities is injected into
the field, providing environmentally safe
disposal and increased steam to power plants.
19Flash Steam Power Plant
- They use geothermal reservoirs of water with
temperatures greater than 360F (182C). This
very hot water flows up through wells in the
ground under its own pressure. As it flows
upward, the pressure decreases and some of the
hot water boils into steam. The steam is then
separated from the water and used to power a
turbine/generator. Any leftover water and
condensed steam are injected back into the
reservoir, making this a sustainable resource.
20Flash Steam Power Plant
- Single flash steam technology is used where the
hydrothermal resource is in a liquid form. The
fluid is sprayed into a flash tank, which is held
at a much lower pressure than the fluid, causing
it to vaporise (or flash) rapidly to steam. The
steam is then passed through a turbine coupled to
a generator as for dry steam plants.
Single Flash Steam Power Plant
21Flash Steam Power Plant
Hydrothermal plant in New Zealand
22Wairakei, New Zealand
- The first geothermal power station from flash
steam was built in the 1950s at Wairakei, New
Zealand.
23Kizildere Power Plant
- 20.4 MWe installed capacity
- Uses steam at 4.5 bar (147 ?C)
- Due to water disposal problems (B), it can
produce 12-13 MWe
24Kizildere Power Plant
25Kizildere Power Plant
26Kizildere Power Plant
27Binary Cycle Power Plant
- Binary cycle power plants operate on water at
lower temperatures of about 225360F
(107182C). These plants use the heat from the
hot water to boil a working fluid, usually an
organic compound with a low boiling point. The
working fluid is vaporized in a heat exchanger
and used to turn a turbine. The water is then
injected back into the ground to be reheated. The
water and the working fluid are kept separated
during the whole process, so there are little or
no air emissions.
28Binary Cycle Power Plant
- Binary cycle power plants (Figure 9) are used
where the geothermal resource is insufficiently
hot to efficiently produce steam, or where the
resource contains too many chemical impurities to
allow flashing.
Binary Cycle Power Plant
29Electricity Generation
30Electricity Generation
- There is 8900 MW of installed geothermal
electricity generation capacity worldwide. The
United States is the largest producer of
geothermal electricity (2544 MW), followed by the
Philippines (1931 MW) (Bertani, 2005).
31Electricity Generation
32High Temperature Geothermal Sources
- Kizildere-Denizli (242 C)
- Germencik-Aydin (232 C)
- Tuzla-Çanakkale (174 C)
- Salavatli-Aydin (171 C)
- Simav-Kütahya (162 C)
- Seferihisar-Izmir (153 C)
- Caferbey-Manisa (150 C)
- Yilmazköy-Aydin (142 C)
- Dikili-Izmir (130 C)
33Example-1
Husavik, Iceland Enery Development
34Example-2
Nesjavellir, Iceland Enery Development
35Example-3
Svartsengi, Iceland Enery Development