OPTIMAL%20CONTRIBUTION%20OF%20DISTRIBUTED%20GENERATION - PowerPoint PPT Presentation

About This Presentation
Title:

OPTIMAL%20CONTRIBUTION%20OF%20DISTRIBUTED%20GENERATION

Description:

optimal contribution of distributed generation in medium voltage grids ... dg more power lost over ... contribution of distributed generation in ... – PowerPoint PPT presentation

Number of Views:206
Avg rating:3.0/5.0
Slides: 19
Provided by: Aim92
Category:

less

Transcript and Presenter's Notes

Title: OPTIMAL%20CONTRIBUTION%20OF%20DISTRIBUTED%20GENERATION


1
OPTIMAL CONTRIBUTION OF DISTRIBUTED GENERATION
  • IN MEDIUM VOLTAGE GRIDS
  • DURING A FAULT,
  • NOW AND IN THE FUTURE

Alliander S. van Loon, F. Volberda, F.
Provoost Enexis J. Morren Session 3 0092
2
Introduction
  • Distribution System Operators (DSO) within The
    Netherlands

Session 3 0092
3
Introduction
  • Increasing DG in MV-grids
  • Connected by step-up transformer
  • Direct connection

MV
LV
Gen
Gen
Session 3 0092
4
Introduction
  • Conflicts
  • Selective tripping ? time grading (gt300ms)
  • Voltage dips ? unwanted disconnection of DG
  • No support grid codes (MV and lt 5 MVA)
  • E.ON grid code FRTHV-grids, lt150 ms

Session 3 0092
5
Introduction
  • Is there a need for smarter protection schemes in
    MV-grids?

Session 3 0092
6
Present protection scheme
  • A voltage dip / frequency change ? disconnect DG
  • More DG ? more power lost
  • Over-/under- voltage ? damage to equipment

Session 3 0092
7
Present protection scheme
150/10 kV substation
  • Example
  • 2 phase fault
  • DG protection
  • DSO protection

21
27
27
27
G1
G2
G3
Undervoltage
27
Distance relay
21
Session 3 0092
8
Present protection scheme
DG disconnect
Fault
  • Example
  • Duration fault 1060 ms

Network protection
Session 3 0092
9
Present protection scheme
  • Example
  • Power swing HV/MV transformer

12 MW
-6 MW
Session 3 0092
10
Expectations DSO
  • Stability
  • Reliability
  • Fully selective protection scheme
  • Safety of personnel
  • Security of supply
  • Prevent damage to equipment
  • Worst case
  • Under- and/or over-voltage

Session 3 0092
11
Smarter grids
  • A smart grid needs a smart protection

Change grid Influence grid Cost
Scenario 1 Low Low Low
Scenario 2 High Medium High
Scenario 3 Medium Medium Medium
Session 3 0092
12
Conclusions
  • Increasing DG ? new protection scheme
  • Fast disconnection of faults
  • Shorter voltage dips
  • Prepare the MV-grid now for future grids
  • Change protection of dedicated feeders
  • Allow contribution of large DG

Session 3 0092
13
A smart grid needs a smart protection!
E M C2
Energy Measurement Control Communication
Session 3 0092
14
Scenario 1
DG must stay connected
DG must disconnect
Session 3 0092
15
Scenario 1
HV/MV substation
Undervoltage
27
27
27
27
G1
G2
G3
Non-dedicated feeders
Dedicated feeders
Session 3 0092
16
Scenario 2
DG must stay connected
DG must disconnect
Session 3 0092
17
Scenario 2
HV/MV substation
87
Undervoltage
27
27
27
27
Differential
87
G1
G2
G3
LOM
LOM
LOM
Loss of mains
LOM
Bi-directional
Non-dedicated feeders
Dedicated feeders
Session 3 0092
18
Scenario 3
HV/MV substation
87
Undervoltage
27
27
27
27
Differential
87
G1
G2
G3
LOM
LOM
Loss of mains
LOM
Bi-directional
Non-dedicated feeders
Dedicated feeders
Session 3 0092
Write a Comment
User Comments (0)
About PowerShow.com