Title: Loran Recap Project
1Status of the Loran Recapitilization Project
FAA Team Meeting July 2002 CDR G. K. Weeks
Jr., U. S. Coast Guard, Commanding Officer USCG
Loran Support Unit
2TTX (11 US) SSX (13 US) NSX (1 Pending) LSU
(SSX, TTX, NSX) Control Site (2 US) PCMS Site
(24 US)
3Transmitting Sites
- Completed- Cesium Installs (24 US, 2 Canadian)
- TTM Installs (Master Stations)
- ABS Installed (29 station, 24 US online)
4Loran Station Timing and Control Equip.
- LORSTA Equipment.
- Timing and Frequency Equip
- First Article Testing Ongoing at LSU
- First Production Units Oct 2002
- First Install, George, WA Nov 2002
5Loran Station Operations Room UPS
- OPS Room UPS
- ? All SSX Installs completed.
- LorSta George completed.
- Installation at rest of the TTX sites will
start after X.25 to Frame Relay transition
is completed (Spring 03).
6Loran Station Transmitter UPS
- Transmitter UPS
- LSU Baseline completed ? Jupiter Inlet,
partially completed, transformer install
pending - Malone and Raymondville completed.
- George completed
- Grangeville, 23 Aug 02
- Carolina Beach, 20 Sep 02
7Loran Station Transmitter (circa 2003-2004)
Replacement Transmitters
- New SSX Transmitter
- Factory Acceptance testing at Megapulse 12
Aug 2002 - LSU install Sep 2002
- George install to be completed
Thanksgiving, 2002 - Kodiak back on the schedule for Summer
2003.
8Loran SSX Switch Gear
- New SSX Switchgear
- ? Installed at LSU and LorSta Grangeville
- Lorsta Jupiter and Carolina Beach scheduled
for Sep 2002
9Loran Station Remote Automated Integrated Loran
(RAIL)
RAIL ?5 LorStas participating in Limited
Installation testing. ? OScope Cards contract
awarded Deliveries started arriving ?
Routers finally onboard LSU? Final Form Rail in
FAT
10Network Transition X.25 to Frame Relay
- LORSTA Equipment.
- Routers
- Sprint terminating X.25 services by Jun 2003
(Dec 2002) - MCI Worldcom selected to provide Frame
Relay for Loran - Installations at the two control sites
(NAVCEN NAVCEN Det) and the 24 US PCMS
sites slated to begin August 2002.
11Loran Station Casualty Control Receiver
- LORSTA Equipment.
- Casualty Control Receiver
- ? Locus LRS IIID
- Installed at 5 stations George, Seneca,
Jupiter, Carolina Beach and Grangeville - Resolving Master station auto-naming
problem found at Seneca - Remaining receivers to be installed with
final form RAIL installations
12Loran Towers
LORSTA Towers ? Tower Study Completed ?
Critical Port Clarence (1350) PP
estimates earliest possible move to Nome
as 2004-2005
13Monitor Sites (PCMS/SAM)
Completed- 29 PCMS Sites (24 US, 5 Canadian)
Locus LRS-IIID All-in-View Receivers
14Status of the Loran Recapitilization Project
Points of Contact CDR G. K. Weeks Jr., USCG
Loran Support Unit, gweeks_at_lsu.uscg.mil Mike
Campbell, USCG Loran Support Unit,
mcampbell_at_lsu.uscg.mil LCDR J. Boyer, USCG Loran
Support Unit, jboyer_at_lsu.uscg.mil
15Loran Station HP-5071A Oscillators
LORSTA Equipment. Cesium Clocks ? Installed at
all US 2 Canadian stations
DONE
16Primary Chain Monitor Set (circa 2000)
PCMS Equipment ? 29 Locations (24 U.S. 5
Canadian) Installed and operational.