Title: Loran Recap Project


1
Status of the Loran Recapitilization Project
FAA Team Meeting July 2002 CDR G. K. Weeks
Jr., U. S. Coast Guard, Commanding Officer USCG
Loran Support Unit
2
TTX (11 US) SSX (13 US) NSX (1 Pending) LSU
(SSX, TTX, NSX) Control Site (2 US) PCMS Site
(24 US)
3
Transmitting Sites
  • Completed- Cesium Installs (24 US, 2 Canadian)
  • TTM Installs (Master Stations)
  • ABS Installed (29 station, 24 US online)

4
Loran Station Timing and Control Equip.
  • LORSTA Equipment.
  • Timing and Frequency Equip
  • First Article Testing Ongoing at LSU
  • First Production Units Oct 2002
  • First Install, George, WA Nov 2002

5
Loran Station Operations Room UPS
  • OPS Room UPS
  • ? All SSX Installs completed.
  • LorSta George completed.
  • Installation at rest of the TTX sites will
    start after X.25 to Frame Relay transition
    is completed (Spring 03).

6
Loran Station Transmitter UPS
  • Transmitter UPS
  • LSU Baseline completed ? Jupiter Inlet,
    partially completed, transformer install
    pending
  • Malone and Raymondville completed.
  • George completed
  • Grangeville, 23 Aug 02
  • Carolina Beach, 20 Sep 02

7
Loran Station Transmitter (circa 2003-2004)
Replacement Transmitters
  • New SSX Transmitter
  • Factory Acceptance testing at Megapulse 12
    Aug 2002
  • LSU install Sep 2002
  • George install to be completed
    Thanksgiving, 2002
  • Kodiak back on the schedule for Summer
    2003.

8
Loran SSX Switch Gear
  • New SSX Switchgear
  • ? Installed at LSU and LorSta Grangeville
  • Lorsta Jupiter and Carolina Beach scheduled
    for Sep 2002

9
Loran Station Remote Automated Integrated Loran
(RAIL)
RAIL ?5 LorStas participating in Limited
Installation testing. ? OScope Cards contract
awarded Deliveries started arriving ?
Routers finally onboard LSU? Final Form Rail in
FAT
10
Network Transition X.25 to Frame Relay
  • LORSTA Equipment.
  • Routers
  • Sprint terminating X.25 services by Jun 2003
    (Dec 2002)
  • MCI Worldcom selected to provide Frame
    Relay for Loran
  • Installations at the two control sites
    (NAVCEN NAVCEN Det) and the 24 US PCMS
    sites slated to begin August 2002.

11
Loran Station Casualty Control Receiver
  • LORSTA Equipment.
  • Casualty Control Receiver
  • ? Locus LRS IIID
  • Installed at 5 stations George, Seneca,
    Jupiter, Carolina Beach and Grangeville
  • Resolving Master station auto-naming
    problem found at Seneca
  • Remaining receivers to be installed with
    final form RAIL installations

12
Loran Towers
LORSTA Towers ? Tower Study Completed ?
Critical Port Clarence (1350) PP
estimates earliest possible move to Nome
as 2004-2005
13
Monitor Sites (PCMS/SAM)
Completed- 29 PCMS Sites (24 US, 5 Canadian)
Locus LRS-IIID All-in-View Receivers
14
Status of the Loran Recapitilization Project
Points of Contact CDR G. K. Weeks Jr., USCG
Loran Support Unit, gweeks_at_lsu.uscg.mil Mike
Campbell, USCG Loran Support Unit,
mcampbell_at_lsu.uscg.mil LCDR J. Boyer, USCG Loran
Support Unit, jboyer_at_lsu.uscg.mil
15
Loran Station HP-5071A Oscillators
LORSTA Equipment. Cesium Clocks ? Installed at
all US 2 Canadian stations
DONE
16
Primary Chain Monitor Set (circa 2000)
PCMS Equipment ? 29 Locations (24 U.S. 5
Canadian) Installed and operational.