Title: Project Review
1Project Review
Architectural Panel Edward Jones
Headquarters Mark Greiner High Concrete Group LLC
2Project Details
- Building Type
- Office
- Location
- St. Louis, MO
- Stories
- 6
- Square Feet of Space
- 40,000
- CarbonCast Product
- Architectural Wall Panels
- Owner
- Edward Jones
- Architect
- Arcturis, St. Louis
- General Contractor
- McCarthy, St. Louis
- Engineer
- Alper Audi, St. Louis
- Erector
- Big Boy Steel, St. Louis
3Edward Jones Headquarters
Rendering courtesy of Arcturis
4Edward Jones Headquarters
Rendering courtesy of Arcturis
5Edward Jones Headquarters
Rendering courtesy of Arcturis
6Edward Jones Headquarters
Rendering courtesy of Arcturis
7Edward Jones Headquarters
Rendering courtesy of Arcturis
8Edward Jones Headquarters
Rendering courtesy of Arcturis
9Situation Analysis
- Owner Needs/Requirements
- Structure designed for limestone, high costs
mandated substitute - Project could not be delayed for redesign
- Steel frame design with weight limit of 50
lbs./sq. ft. - Why precast was preferable
- Could give the look of limestone at a lower cost
- Long term durability
- However, conventional precast was too heavy for
the design - What special needs CarbonCast products fulfilled
- Lighter weight worked within constraints of
existing structural design - Non-corrosive maintain longer-term aesthetics
10How the Product Use Table Applies to this Sale
11Sales Process
- How we became aware of the project
- Relationship with the architect (Arcturis) they
called when they found out they had a problem - The early meetings
- A CarbonCast design solution was proposed for
weight and aesthetics - Architect was encouraging, so I involved
engineering - Limestone was preferred, but problems with the
design were indicated by architect - How decisions were made
- Engineering attended sales meetings with
architect to see if CarbonCast could meet design
criteria - Proved we could do 50 lbs./sq. ft.
- Engineering analysis of building elevations and
sections for sizing and connections - Architects indicated CarbonCast was their
preference to address weight issue
12Sales Process Continued
- How decisions were influenced
- Relationship with the architect
- Challenges encountered
- Needed to limit some eyebrow and parapet panels
to 4 thickness (conventional precast) - How challenges were dealt with
- Engineering checked to determine if we could meet
weight criteria - Supplied typical panel design diagram showing 8
panel with ribbing - Used conventional precast for panels with returns
or not flat
13Technical Challenges
- Challenges
- Design required 50 psf or less panels
- Look of dimensional limestone
- Solutions
- Engineering supported technical sales proposal of
lightweight CarbonCast
14Lessons Learned
- What could have been done to make the process
more effective - Design the project for CarbonCast from the
beginning - Obtain CM buy-in
- How the process could be improved
- Introduce CarbonCast as part of the initial
design - Involve CM in early design meetings so they can
understand the solution
15Panel Section
EPS Foam
16Questions?