Title: MUMBAI URBAN TRANSPORT PROJECT
1 MUMBAI URBAN TRANSPORT PROJECT CONSOLIDATED
ENVIRONMENTAL ASSESSMENT PRESENTATION for
PUBLIC CONSULTATION November 2001 Mumbai
Metropolitan Region Development Authority, Bandra
- Kurla Complex, Bandra (East) Mumbai
2MUTP - Background
- Mumbai that was a group of seven islands in the
17th century has now grown to be a financial and
commercial capital of India. The original seven
islands have merged into Island City. Greater
Mumbai including the Island City, Western Suburbs
and the Eastern Suburbs supports a population of
11 .8 million - The urban growth has spread much beyond the
boundaries of Greater Mumbai along the rail
corridors.
3POPULATION GROWTH DENSITY
Sub region Area sq.km Population 1991 million Population 2001 million Density Per sq.km
Gr.Mumbai 467 9.9 11.8 25267
Island 72 3.2 3.3 45833
Western Suburbs 226 3.9 5.0 22123
Eastern suburbs 168 2.8 3.5 20833
Mira-Vasai-Virar 250 0.5 0.9 3600
Thane Kalyan 328 2.1 3.2 9756
Navi Mumbai 388 0.5 1.2 3092
Total 1433 13 17.1 11933
4TRANSPORT PRESSING PROBLEM
- Such phenomenal growth has given rise to
problems commonly faced by most metropolitan
cities in the developing world. - Acute shortage of affordable shelter
- Lack of adequate water and sanitation facilities
- Environmental degradation
- But in Mumbai acute shortage of transport
infrastructure is the most pressing problem. -
5EXISTING MODAL SPLIT
Number of Passengers per day
Passenger Kms per day
2
5
8
7
17
46
42
73
Rail
Bus
Private Vehicles
Taxis
6TRANSPORT SCENARIO IN MUMBAI
- In 1993 total peak hour passenger trips generated
by population of about 15 million was 21,54,860 .
- 88 were performed by public transport
- In 1981-91 the population growth was 3 p.a
whereas vehicular growth was 8.8 .p.a. - Private vehicle registration in MMR in 2011 is
expected to more than double the 1991 level
(13,56,498 vehicles) - Number of vehicles per 1000 persons is expected
to increase from 44 in 1991 to 61.1 in 2011.
7OVERCROWDING
8ENVIRONMENTAL CONCERNS
- The road transport is a major contributor to air
and noise pollution. - As per the URBAIR Study of 1992, vehicular
traffic contributes to 54of N0x emissions and
24 of PM10 emissions in Greater Mumbai. Levels
of Both N0x and PM10 exceed AAQ standards at
many residential areas and traffic intersections. - Noise levels along the roads have been found to
be in the range of 65dB(A) and 85 dB(A). - Given the trend of higher vehicle ownership,
vehicular pollution and noise in Mumbai has
become a cause of concern
9COMPREHENSIVE TRANSPORTATION STRATEGY
- MMRDA has prepared a long-term multi-modal
Comprehensive Transport Strategy (1994) for the
MMR. - The objective
- To deal with the increasing travel demand in an
effective and financially and environmentally
sustainable manner.
10COMPREHENSIVE TRANSPORTATION STRATEGY (CTS)
- CTS identified four strategic options,
- Do Minimum(DM) ,
- Public Transport (PT),
- Public Transport Demand Management (PTDM), and
- Road Investment (RI)
-
- CTS, based largely on economic and efficiency
considerations, recommended the strategy
comprising - Priority for investment in public transport
- Strengthening road networks in suburbs especially
east - west links - Introduction of demand management measures for
controlling traffic congestion
11ENVIRONMENTAL ASSESSMENT
THE CTS STRATEGY AND THE RESULTANT INVESTMENT
PROGRAM REQUIRED EA TO IDENTIFY ENVIRONMENTAL
IMPACTS AND TO PROPOSE ENVIRONMENTAL MANAGEMENT
PLANS TO MITIGATE ADVERSE IMPACTS.
- THIS PRESENTAION OF EA OF MUTP IS DIVIDED INTO
FOLLOWING SECTIONS - ENVIRONMENTAL BASELINE DATA
- EA PROCESS
- SECTORAL EA
- PROJECT DESCRIPTION
- PROJECT LEVEL EA
- EMP AT SECTOR LEVEL
- EMP FOR PROJECTS
- R R RAP and CEMP
12AIR QUALITY BASELINE DATA
13AMBIENT AIR QUALITY 1998 2000
Note Above yearly averages are taken for
financial years (March to April) from ESR of
MCGM. C commercial I Industrial R
Residential Â
14AIR QUALITY AT TRAFFIC INTERSECTIONS Â
Note Above yearly averages are taken for
financial years from ESR of MCGM. Â
15EA PROCESS
16EA PROCESS
Comprehensive Transportation Study 4 strategic
options 1. Do Minimum 2. Public transport
option 3. Public transport Demand Management
4. Road Investment option
- Sectoral Level Environmental Assessment (SLEA)
- Evaluation of strategic options with respect to
the following criteria - Impact on Air, noise,
- social,
- ecological resources, and
- transportation service quality
Selection of strategic option (PT DM)
17Screening of projects with respect to potential
impacts
Micro-level Environmental Assessment (MLEA)
Subprojects selected road improvements,
suburban railway Impact on traffic, air, noise,
water landuse, social and ecological resources.
Programmatic Level Environmental Assessment
(PLEA) Sub-projects selected ROBs, pedestrians
subways Analysis of traffic transport Impact
on air, noise, social and ecological resources,
landuse
Public Consultation
Preparation of updated and consolidated EA and
project specific EMPs
Public Consultation
Draft Consolidated EA
Final Consolidated EA
18SECTORAL EA
19SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
- Essential to assess environmental impacts due to
transport sector as a whole. - SLEA includes assessment of environmental impact
due to physical transportation activities (air,
noise pollution etc.), government policies and
other traffic management measures. - SLEA was carried out for the 4 transport options
viz. Do Minimum, PT, PTDM and RI defined in the
CTS.
20SECTORAL ENVIRONMENT ASSESSMENT
- Sectoral Environment Assessment (SLEA) will help
-
- Ensure integration of environmental concerns into
long-term transport planning. - Provide framework for adopting appropriate legal,
policy and administrative measures - Designing long term investment programme and
- Institutional capacity building for sector
management.
21SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
- Components used for SLEA were
- Ambient Air Quality
- Noise
- Ecology
- Social (Resettlement and Rehabilitation)
- Transport Service
- Impacts on the above components were evaluated
for 4 sub-regions of MMR - Island City, Western Suburbs, Eastern Suburbs
and Rest of MMR.
22(No Transcript)
23SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
Environmental Impact Indicators/Indices Used in
SEA
Environmental Index Air Quality CO concentration in mg/NM3 SO2 concentration in ?g/NM3 NOx concentration in ?g/NM3 Pb concentration in ?g/NM3 PM10 concentration in ?g/NM3 Description Ambient CO conc. due to transport option Ambient SO2 conc.due to transport option Ambient NOx conc.due to transport option Since unleaded petrol has been introduced this index is no longer valid Ambient PM10 conc.due to transport option
24Environmental Index Noise Traffic Noise Index (Day) TNI (day) Traffic Noise Index (Night) TNI (night) Ecology Ecological Impact indicator (Natural system) EI-1 Ecological Impact indicator (Man-made system) EI-2 Description of length of road links exceeding daytime standard weighted by population with 150 m of the curb of length of road links exceeding nighttime standard Weighted total area of road/rail alignment intercepted by natural ecological system classified into different categories according to their importance Weighted total area of road/rail alignment intercepted by man-made natural systems classified into different categories according to their importance
25Environmental Index Social RR impacts Service Indices Traffic efficiency Index Traffic congestion Index Railway crowding Index Description Number of displaced households Index reflecting efficiency in terms of speed and fuel consumption of link lengths in the sub-regions exceeding the Volume /Capacity ratio Link length weighted by Volume / Capacity Ratio
26SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
- For each of the environmental component, baseline
status was determined for the year 1996 and
incremental impacts due to the projects were
predicted for the year 2011. - These impacts were predicted for all the 4
sub-regions of MMR under each of the 4 transport
options.
27Comparison of Options based on Absolute Values of
Air Pollutants
28(No Transcript)
29(No Transcript)
30(No Transcript)
31SLEA FINDINGS
- All indicator values (air, noise, ecology etc)
did not favour any single option. Thus Decision
Matrix and other methods were used to determine
an optimum transport option. - Overall the PUBLIC TRANSPORT DEMAND MANAGEMENT
(PTDM) option emerged as the best transport
option for MMR as a whole.
32SELECTION OF BEST OPTION
33PROJECT DESCRIPTION
34MUTP SUB-PROJECTS
- MUTP has been formulated by selecting
sub-projects that are subsets of the PTDM
option. The strategy followed in designing MUTP
is - High priority at promoting public transport,
particularly suburban railways - Relieving road congestion by developing roads and
ROBs in suburban areas - Relieving automobile traffic congestion in Island
City through Area Traffic Control and Traffic
Management Measures.
35MUTP RAIL SUB-PROJECTS
-
- Borivali-Virar Quadrupling project Laying of 2
railway lines between Borivali and Virar. - Provision of 5th and 6th lines between Kurla and
Thane - Provision of 5th line between Santacruz and
Borivali - DC to AC Traction Conversion
- Optimisation of Rail Operations including
procurement of additional rakes
36MUTP ROAD SUB-PROJECTS
- Jogeshwari Vikhroli Link Road (JVLR)
- Santacruz- Chembur Link Road (SCLR)
- Construction of ROBs at Jogeshwari (South and
North) and at Vikhroli. - Pedestrian subways and bridges at about 25
locations - Station Area Traffic improvement Schemes (SATIS)
- Other traffic management schemes
- Procurement of Buses Mainly CNG
37(No Transcript)
38PROJCET LEVEL EA
39PROJECT LEVEL ENVIRONMENTAL ASSESSMENT
- MLEA and PLEA of the projects included the
following analysis during construction and
operation stages - - Impact on Traffic - Impact on Land Use
- - Water Quality Impacts - Air Quality Impacts
- Noise Impacts - Impacts on Ecological
Resources - Separate PLEA and MLEA reports including
mitigation measures for the identified adverse
environmental impacts were prepared in 1998 for
major projects viz. JVLR, BVQR, ROB Vikhroli,
SATIS, Pedestrian Subway
40PROJECT LEVEL ENVIRONMENTAL ASSESSMENT
- The environmental impacts identified during the
construction and operation phases of the projects
are as follows - Construction Phase
- Displacement of population
- Nuisance to residential areas from noise and dust
- Sanitation problems from labour camps at site
- Cutting of existing plantation
- Land degradation at quarry sites
- Worker and public safety
41PROJECT LEVEL ENVIRONMENTAL ASSESSMENT
- Operation Phase
- Mild to moderate increase in air pollution and
noise levels from road traffic and increased
noise levels due to train movement. - Beneficial impacts on traffic.
42ENVIRONMENTAL IMPACTS OF SUB- PROJECTS
JOGESHWARI VIKHROLI LINK ROAD
- During Construction Phase
- Partial closure of existing roads leading to
diversion/disruption of traffic. - Fugitive air emissions due to earthwork, rock
cutting, transportation of construction materials
etc. - Residential and sensitive areas in the immediate
vicinity will have impact of noise pollution - Loss of vegetation along the road side.
- All impacts will be temporary in nature
43- JOGESHWARI VIKHROLI LINK ROAD
- Operation Phase
- Positive impacts due to free flow of traffic,
higher operating speeds, safety, preventing
traffic jam, etc. - Moderate impacts due to increase in PM10, CO
levels. - Residential and sensitive areas in the
immediate vicinity of sub- projects will have
noise pollution impacts due to the vehicular
movements.
44BORIVALI VIRAR QUADRUPLING OF RAIL LINES
- Construction Phase
- Fugitive air emissions of NOx and particulates
due to earthwork, rock cutting, transportation of
construction materials etc - Residential and sensitive areas in the immediate
vicinity will have impact of noise pollution - Loss of vegetation along the existing rail
corridor. - All impacts will be temporary in nature
45- Operation Phase
- Positive impact due to fast trains running
between Borivali and Virar -
- No impact on air quality as electric trains will
be operated - Residential and sensitive areas in the immediate
vicinity will have noise pollution impacts due to
the train movements
46ENVIRONMENTAL MANAGEMENT PLANS
47ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
- At the sectoral level, a variety of policy, legal
and administrative measures will be used to
manage and mitigate adverse environmental
impacts. - Responsibilities and Time frames for implementing
these measures have been proposed.
48ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
- Air Quality
- Encourage supply and use of clean fuels CNG, LPG
- Measures to prevent fuel adulteration
- Upgrade infrastructure for strict implementation
of vehicle emission standards. - Promoting vehicle inspection and monitoring
program - Enhance current AAQ monitoring network of MCGM.
- RR
- Strict adherence to RR policy of GOM
49ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
- NOISE
- Policy for noise reduction from vehicle engines,
exhaust, tires and roads. - Monitoring of noise levels at sensitive receptors
- Noise abatement by using noise barriers to the
extent feasible. - Ecological Impacts
- Strict enforcement of Development Rules and CZMP
50ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
- Traffic Management and Road Safety
- Strengthening transport and traffic planning
- Modal integration outside railway stations ,
managing traffic demand etc. - Enforcement of road safety rules
51SECTORAL LEVEL EMP MONITORING
- Monitoring plans have been prepared for
- Environmental Quality AAQ, Noise etc.
- Social (RR) Components
- Traffic movement.
- Regular monitoring and reporting will assist in
assessing the effectiveness of EMPs and
re-casting of EMPs, if required.
52EMPS FOR SUB-PROJECTS
- The EMPs for the sub-projects were prepared in
1998. These EMPs are currently being updated to
encompass the changes in baseline data and site
conditions that may have changed since the year
1998. - Site specific EMPs have been prepared for
significant environmental impacts/issues such as - Ambient Air Quality Deterioration
- Increase in Noise Levels
- Adverse Impacts on Ecology (Flora/Fauna)
- Population displacement
- Land degradation, Surface and groundwater
degradation - Occupational health and safety
53EMPS FOR SUB-PROJECTS
- CONSTRUCTION STAGE
- Construction requiring street closure will be
carried out during off peak hours - Enclosure of construction areas, periodic water
sprinkling, using dust covers to avoid air
quality related impacts. - Reducing noise related impacts by providing
mufflers on equipment, installing temporary noise
barriers, not carrying out the activities
producing noise above 95db(A) during night time. - Construction of noise barriers along ROBs
54CONSTRUCTION STAGE (....contd.)
- Proper management of labour camps,
- Planting of trees and vegetation and compensatory
afforestation - Use of appropriate construction equipment, Proper
disposal of excess earth material, - Satisfactory restoration of quarry sites, before
they are abandoned, - Traffic management at construction and quarry
sites.
55- OPERATION STAGE
- Development of emergency plan in the event of
road accident involving vehicles carrying
hazardous material, - Establishment of no honking Zones near the
sensitive areas such as schools, hospitals, etc. - Tree plantations along the transport corridors
and its maintenance - Enforcement of road safety rules
56SUB-PROJECT LEVEL EMP MONITORING
- Environmental monitoring plans are developed for
the specific MUTP sub-projects, involving
monitoring sites, monitoring parameters, time and
frequency of monitoring and the reporting of
monitored data. The objectives of the
monitoring plan are -
- To record the impact of MUTP on urban
environmental quality To evaluate the
effectiveness of the mitigation measures - To satisfy the legal and community obligations
- To respond to the unanticipated environmental
issues at an early stage and to verify the
accuracy of environmental impact prediction.
57SUB-PROJECT LEVEL EMP MONITORING
- At the project level, the vital parameters or
performance indicators that will be monitored
during construction and/or operation stages of
the project include - Ambient air quality SO2, PM10, CO, N0x
- Noise levels near sensitive locations
- Re-plantation success/ survival rates
- Traffic volume and characteristics
- Methodology used for sampling and analysis will
be as per prevalent requirements of Ministry of
Environment and Forest and Indian Standard (IS)
codes.
58INSTITUTIONAL SET-UP, COORDINATION AND
STRENGTHENING
- A strong coordinating authority to coordinate the
activities - Institutional capacity building through
training. - Improving air quality and noise monitoring, and
effective dissemination of information
59INSTITUTIONAL SET-UP, COORDINATION AND
STRENGTHENING
High Power Steering Committee
IMP
Project Coordination Committee
World Bank
MMRDA Project Director, MUTP JPD (Environment),
MUTP
MSRDC/PWD
MRVC
MCGM
BEST
PMC
PMC
PMC
PMC
Contractor
Contractor
Contractor
Contractor
60EMP COST-ESTIMATES
- Cost estimates have been prepared for EMPs
related to the following tasks - Relocation of Utilities
- Compensatory and Road/Track Side Plantation
- Pollution control during construction
- Noise level reduction
- Labour Camp sanitation, Road safety
- Environmental Monitoring
- . The estimated cost of EMP implementation for
MUTP sub-projects is Rs. 19.38 Million.
61CONDITION OF CONTRACT DOCUMENT
- In order to facilitate smooth implementation of
EMPs, the PIA shall include specific obligations
in respect of EMP implementation in all tender
and contract documents. The bidding and contract
documents shall include the following information
- Â
- EMP requirements and obligations
- Environmental Monitoring Requirements
- Reporting requirements
- Indicative EMP cost estimates
62RR- RAP and CEMP
63RESETTLEMENT REHABILITAION
Total number of PAH 19228 (Project Affected
Households) Number affected by railway
projects 14479 Number affected by road projects
4749. Number of PAH resettled by
June 10118 2001 Total Cost of resettlement Rs.
4607 Million
64RESETTLEMENT POLICY
- Objectives of R R Policy are
- To minimize resettlement
- Where displacement is unavoidable, displaced
persons to be compensated for their losses - To accord formal housing rights to the PAHs
- To develop and implement resettlement program
through active community participation - To improve environmental health and hygiene of
the PAHs - To educate, motivate and organise the community
to manage its environment - To retain existing community network in the
resettlement area and to minimize the adverse
impact, if any, on the host community
65RESETTLEMENT POLICY
Entitlement
- Every eligible household losing a dwelling place
shall be allotted a dwelling unit of minimum of
225 sq.ft. at an alternate site. - Similarly every PAH losing a commercial structure
shall be eligible for an alternate place for
commercial use of equivalent area. - Compensation for economic losses e.g extra travel
cost.
66ENCROACHMENTS/TRESPASSING
67PERMANENT TENEMENTS
68TRANSIT QUARTERS
69COMMUNITY ENVIRONMENTAL MANAGEMENT PLAN (CEMP)
- Every site specific RIP will include a Community
Environmental Management Plan (CEMP). - The objectives of CEMP are
- to provide access to basic urban environmental
infrastructure services - alleviate the environmental health risks of the
community.
70CEMP
- The communities will be trained and motivated to
follow discipline that can avoid environmental
problems. - Separate Environmental Management Committees
(EMCs) will be formed to take up this
responsibility. - The CEMP provides preventive maintenance schedule
for water supply, sanitation, solid waste etc in
simple local language. - Maintenance measures are translated into a simple
format in the form of "Do's" and "Don'ts" in
local languages for the community.
71ORGANISATIONAL RESPONSIBILITIES
- High Power Steering Committee to oversee the
progress of MUTP including RR and provide
necessary policy directions. - A Project Co-ordination Committee to supervise
timely implementation of MUTP including
inter-agency coordination, - An Independent Monitoring Panel (IMP) comprising
eminent citizens of Mumbai for ensuring
compliance with accepted policies in project
implementation
Aggrieved PAH can go to the Grievance Redressal
Committee appointed by the PMU comprising of
officials and representatives of NGOs
72FEEDBACK
- Your feedback sent to
- Project Director MUTP
- MMRDA
- Bandra Kurla Complex, Bandra (East)
- Mumbai 400 051
- Will be appreciated.
THANK YOU