MUMBAI URBAN TRANSPORT PROJECT - PowerPoint PPT Presentation

About This Presentation
Title:

MUMBAI URBAN TRANSPORT PROJECT

Description:

Lack of adequate water and sanitation facilities. Environmental degradation ... High priority at promoting public transport, particularly suburban railways ... – PowerPoint PPT presentation

Number of Views:1740
Avg rating:3.0/5.0
Slides: 73
Provided by: rah89
Category:

less

Transcript and Presenter's Notes

Title: MUMBAI URBAN TRANSPORT PROJECT


1
MUMBAI URBAN TRANSPORT PROJECT CONSOLIDATED
ENVIRONMENTAL ASSESSMENT PRESENTATION for
PUBLIC CONSULTATION November 2001 Mumbai
Metropolitan Region Development Authority, Bandra
- Kurla Complex, Bandra (East) Mumbai
2
MUTP - Background
  • Mumbai that was a group of seven islands in the
    17th century has now grown to be a financial and
    commercial capital of India. The original seven
    islands have merged into Island City. Greater
    Mumbai including the Island City, Western Suburbs
    and the Eastern Suburbs supports a population of
    11 .8 million
  • The urban growth has spread much beyond the
    boundaries of Greater Mumbai along the rail
    corridors.

3
POPULATION GROWTH DENSITY
Sub region Area sq.km Population 1991 million Population 2001 million Density Per sq.km
Gr.Mumbai 467 9.9 11.8 25267
Island 72 3.2 3.3 45833
Western Suburbs 226 3.9 5.0 22123
Eastern suburbs 168 2.8 3.5 20833
Mira-Vasai-Virar 250 0.5 0.9 3600
Thane Kalyan 328 2.1 3.2 9756
Navi Mumbai 388 0.5 1.2 3092
Total 1433 13 17.1 11933
4
TRANSPORT PRESSING PROBLEM
  • Such phenomenal growth has given rise to
    problems commonly faced by most metropolitan
    cities in the developing world.
  • Acute shortage of affordable shelter
  • Lack of adequate water and sanitation facilities
  • Environmental degradation
  • But in Mumbai acute shortage of transport
    infrastructure is the most pressing problem.

5
EXISTING MODAL SPLIT
Number of Passengers per day
Passenger Kms per day
2
5
8
7
17
46
42
73
Rail
Bus
Private Vehicles
Taxis
6
TRANSPORT SCENARIO IN MUMBAI
  • In 1993 total peak hour passenger trips generated
    by population of about 15 million was 21,54,860 .
  • 88 were performed by public transport
  • In 1981-91 the population growth was 3 p.a
    whereas vehicular growth was 8.8 .p.a.
  • Private vehicle registration in MMR in 2011 is
    expected to more than double the 1991 level
    (13,56,498 vehicles)
  • Number of vehicles per 1000 persons is expected
    to increase from 44 in 1991 to 61.1 in 2011.

7
OVERCROWDING
8
ENVIRONMENTAL CONCERNS
  • The road transport is a major contributor to air
    and noise pollution.
  • As per the URBAIR Study of 1992, vehicular
    traffic contributes to 54of N0x emissions and
    24 of PM10 emissions in Greater Mumbai. Levels
    of Both N0x and PM10 exceed AAQ standards at
    many residential areas and traffic intersections.
  • Noise levels along the roads have been found to
    be in the range of 65dB(A) and 85 dB(A).
  • Given the trend of higher vehicle ownership,
    vehicular pollution and noise in Mumbai has
    become a cause of concern

9
COMPREHENSIVE TRANSPORTATION STRATEGY
  • MMRDA has prepared a long-term multi-modal
    Comprehensive Transport Strategy (1994) for the
    MMR.
  • The objective
  • To deal with the increasing travel demand in an
    effective and financially and environmentally
    sustainable manner.

10
COMPREHENSIVE TRANSPORTATION STRATEGY (CTS)
  • CTS identified four strategic options,
  • Do Minimum(DM) ,
  • Public Transport (PT),
  • Public Transport Demand Management (PTDM), and
  • Road Investment (RI)
  • CTS, based largely on economic and efficiency
    considerations, recommended the strategy
    comprising
  • Priority for investment in public transport
  • Strengthening road networks in suburbs especially
    east - west links
  • Introduction of demand management measures for
    controlling traffic congestion

11
ENVIRONMENTAL ASSESSMENT
THE CTS STRATEGY AND THE RESULTANT INVESTMENT
PROGRAM REQUIRED EA TO IDENTIFY ENVIRONMENTAL
IMPACTS AND TO PROPOSE ENVIRONMENTAL MANAGEMENT
PLANS TO MITIGATE ADVERSE IMPACTS.
  • THIS PRESENTAION OF EA OF MUTP IS DIVIDED INTO
    FOLLOWING SECTIONS
  • ENVIRONMENTAL BASELINE DATA
  • EA PROCESS
  • SECTORAL EA
  • PROJECT DESCRIPTION
  • PROJECT LEVEL EA
  • EMP AT SECTOR LEVEL
  • EMP FOR PROJECTS
  • R R RAP and CEMP

12
AIR QUALITY BASELINE DATA
13
AMBIENT AIR QUALITY 1998 2000
Note Above yearly averages are taken for
financial years (March to April) from ESR of
MCGM. C commercial I Industrial R
Residential  
14
AIR QUALITY AT TRAFFIC INTERSECTIONS  
Note Above yearly averages are taken for
financial years from ESR of MCGM.  
15
EA PROCESS
16
EA PROCESS
Comprehensive Transportation Study 4 strategic
options 1. Do Minimum 2. Public transport
option 3. Public transport Demand Management
4. Road Investment option
  • Sectoral Level Environmental Assessment (SLEA)
  • Evaluation of strategic options with respect to
    the following criteria
  • Impact on Air, noise,
  • social,
  • ecological resources, and
  • transportation service quality

Selection of strategic option (PT DM)
17
Screening of projects with respect to potential
impacts
Micro-level Environmental Assessment (MLEA)
Subprojects selected road improvements,
suburban railway Impact on traffic, air, noise,
water landuse, social and ecological resources.
Programmatic Level Environmental Assessment
(PLEA) Sub-projects selected ROBs, pedestrians
subways Analysis of traffic transport Impact
on air, noise, social and ecological resources,
landuse
Public Consultation
Preparation of updated and consolidated EA and
project specific EMPs
Public Consultation
Draft Consolidated EA
Final Consolidated EA
18
SECTORAL EA
19
SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
  • Essential to assess environmental impacts due to
    transport sector as a whole.
  • SLEA includes assessment of environmental impact
    due to physical transportation activities (air,
    noise pollution etc.), government policies and
    other traffic management measures.
  • SLEA was carried out for the 4 transport options
    viz. Do Minimum, PT, PTDM and RI defined in the
    CTS.

20
SECTORAL ENVIRONMENT ASSESSMENT
  • Sectoral Environment Assessment (SLEA) will help
  • Ensure integration of environmental concerns into
    long-term transport planning.
  • Provide framework for adopting appropriate legal,
    policy and administrative measures
  • Designing long term investment programme and
  • Institutional capacity building for sector
    management.

21
SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
  • Components used for SLEA were
  • Ambient Air Quality
  • Noise
  • Ecology
  • Social (Resettlement and Rehabilitation)
  • Transport Service
  • Impacts on the above components were evaluated
    for 4 sub-regions of MMR
  • Island City, Western Suburbs, Eastern Suburbs
    and Rest of MMR.

22
(No Transcript)
23
SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
Environmental Impact Indicators/Indices Used in
SEA
Environmental Index Air Quality CO concentration in mg/NM3 SO2 concentration in ?g/NM3 NOx concentration in ?g/NM3 Pb concentration in ?g/NM3 PM10 concentration in ?g/NM3 Description Ambient CO conc. due to transport option Ambient SO2 conc.due to transport option Ambient NOx conc.due to transport option Since unleaded petrol has been introduced this index is no longer valid Ambient PM10 conc.due to transport option
24
Environmental Index Noise Traffic Noise Index (Day) TNI (day) Traffic Noise Index (Night) TNI (night) Ecology Ecological Impact indicator (Natural system) EI-1 Ecological Impact indicator (Man-made system) EI-2 Description of length of road links exceeding daytime standard weighted by population with 150 m of the curb of length of road links exceeding nighttime standard Weighted total area of road/rail alignment intercepted by natural ecological system classified into different categories according to their importance Weighted total area of road/rail alignment intercepted by man-made natural systems classified into different categories according to their importance
25
Environmental Index Social RR impacts Service Indices Traffic efficiency Index Traffic congestion Index Railway crowding Index Description Number of displaced households Index reflecting efficiency in terms of speed and fuel consumption of link lengths in the sub-regions exceeding the Volume /Capacity ratio Link length weighted by Volume / Capacity Ratio
26
SECTORAL ENVIRONMENTAL ASSESSMENT (SLEA)
  • For each of the environmental component, baseline
    status was determined for the year 1996 and
    incremental impacts due to the projects were
    predicted for the year 2011.
  • These impacts were predicted for all the 4
    sub-regions of MMR under each of the 4 transport
    options.

27
Comparison of Options based on Absolute Values of
Air Pollutants
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
SLEA FINDINGS
  • All indicator values (air, noise, ecology etc)
    did not favour any single option. Thus Decision
    Matrix and other methods were used to determine
    an optimum transport option.
  • Overall the PUBLIC TRANSPORT DEMAND MANAGEMENT
    (PTDM) option emerged as the best transport
    option for MMR as a whole.

32
SELECTION OF BEST OPTION
33
PROJECT DESCRIPTION
34
MUTP SUB-PROJECTS
  • MUTP has been formulated by selecting
    sub-projects that are subsets of the PTDM
    option. The strategy followed in designing MUTP
    is
  • High priority at promoting public transport,
    particularly suburban railways
  • Relieving road congestion by developing roads and
    ROBs in suburban areas
  • Relieving automobile traffic congestion in Island
    City through Area Traffic Control and Traffic
    Management Measures.

35
MUTP RAIL SUB-PROJECTS
  • Borivali-Virar Quadrupling project Laying of 2
    railway lines between Borivali and Virar.
  • Provision of 5th and 6th lines between Kurla and
    Thane
  • Provision of 5th line between Santacruz and
    Borivali
  • DC to AC Traction Conversion
  • Optimisation of Rail Operations including
    procurement of additional rakes

36
MUTP ROAD SUB-PROJECTS
  • Jogeshwari Vikhroli Link Road (JVLR)
  • Santacruz- Chembur Link Road (SCLR)
  • Construction of ROBs at Jogeshwari (South and
    North) and at Vikhroli.
  • Pedestrian subways and bridges at about 25
    locations
  • Station Area Traffic improvement Schemes (SATIS)
  • Other traffic management schemes
  • Procurement of Buses Mainly CNG

37
(No Transcript)
38
PROJCET LEVEL EA
39
PROJECT LEVEL ENVIRONMENTAL ASSESSMENT
  • MLEA and PLEA of the projects included the
    following analysis during construction and
    operation stages
  • - Impact on Traffic - Impact on Land Use
  • - Water Quality Impacts - Air Quality Impacts
  • Noise Impacts - Impacts on Ecological
    Resources
  • Separate PLEA and MLEA reports including
    mitigation measures for the identified adverse
    environmental impacts were prepared in 1998 for
    major projects viz. JVLR, BVQR, ROB Vikhroli,
    SATIS, Pedestrian Subway

40
PROJECT LEVEL ENVIRONMENTAL ASSESSMENT
  • The environmental impacts identified during the
    construction and operation phases of the projects
    are as follows
  • Construction Phase
  • Displacement of population
  • Nuisance to residential areas from noise and dust
  • Sanitation problems from labour camps at site
  • Cutting of existing plantation
  • Land degradation at quarry sites
  • Worker and public safety

41
PROJECT LEVEL ENVIRONMENTAL ASSESSMENT
  • Operation Phase
  • Mild to moderate increase in air pollution and
    noise levels from road traffic and increased
    noise levels due to train movement.
  • Beneficial impacts on traffic.

42
ENVIRONMENTAL IMPACTS OF SUB- PROJECTS
JOGESHWARI VIKHROLI LINK ROAD
  • During Construction Phase
  • Partial closure of existing roads leading to
    diversion/disruption of traffic.
  • Fugitive air emissions due to earthwork, rock
    cutting, transportation of construction materials
    etc.
  • Residential and sensitive areas in the immediate
    vicinity will have impact of noise pollution
  • Loss of vegetation along the road side.
  • All impacts will be temporary in nature

43
  • JOGESHWARI VIKHROLI LINK ROAD
  • Operation Phase
  • Positive impacts due to free flow of traffic,
    higher operating speeds, safety, preventing
    traffic jam, etc.
  • Moderate impacts due to increase in PM10, CO
    levels.
  • Residential and sensitive areas in the
    immediate vicinity of sub- projects will have
    noise pollution impacts due to the vehicular
    movements.

44
BORIVALI VIRAR QUADRUPLING OF RAIL LINES
  • Construction Phase
  • Fugitive air emissions of NOx and particulates
    due to earthwork, rock cutting, transportation of
    construction materials etc
  • Residential and sensitive areas in the immediate
    vicinity will have impact of noise pollution
  • Loss of vegetation along the existing rail
    corridor.
  • All impacts will be temporary in nature

45
  • Operation Phase
  • Positive impact due to fast trains running
    between Borivali and Virar
  • No impact on air quality as electric trains will
    be operated
  • Residential and sensitive areas in the immediate
    vicinity will have noise pollution impacts due to
    the train movements

46
ENVIRONMENTAL MANAGEMENT PLANS
47
ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
  • At the sectoral level, a variety of policy, legal
    and administrative measures will be used to
    manage and mitigate adverse environmental
    impacts.
  • Responsibilities and Time frames for implementing
    these measures have been proposed.

48
ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
  • Air Quality
  • Encourage supply and use of clean fuels CNG, LPG
  • Measures to prevent fuel adulteration
  • Upgrade infrastructure for strict implementation
    of vehicle emission standards.
  • Promoting vehicle inspection and monitoring
    program
  • Enhance current AAQ monitoring network of MCGM.
  • RR
  • Strict adherence to RR policy of GOM

49
ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
  • NOISE
  • Policy for noise reduction from vehicle engines,
    exhaust, tires and roads.
  • Monitoring of noise levels at sensitive receptors
  • Noise abatement by using noise barriers to the
    extent feasible.
  • Ecological Impacts
  • Strict enforcement of Development Rules and CZMP

50
ENVIRONMENTAL MANAGEMET PLANS FOR SECTORAL LEVEL
  • Traffic Management and Road Safety
  • Strengthening transport and traffic planning
  • Modal integration outside railway stations ,
    managing traffic demand etc.
  • Enforcement of road safety rules

51
SECTORAL LEVEL EMP MONITORING
  • Monitoring plans have been prepared for
  • Environmental Quality AAQ, Noise etc.
  • Social (RR) Components
  • Traffic movement.
  • Regular monitoring and reporting will assist in
    assessing the effectiveness of EMPs and
    re-casting of EMPs, if required.

52
EMPS FOR SUB-PROJECTS
  • The EMPs for the sub-projects were prepared in
    1998. These EMPs are currently being updated to
    encompass the changes in baseline data and site
    conditions that may have changed since the year
    1998.
  • Site specific EMPs have been prepared for
    significant environmental impacts/issues such as
  • Ambient Air Quality Deterioration
  • Increase in Noise Levels
  • Adverse Impacts on Ecology (Flora/Fauna)
  • Population displacement
  • Land degradation, Surface and groundwater
    degradation
  • Occupational health and safety

53
EMPS FOR SUB-PROJECTS
  • CONSTRUCTION STAGE
  • Construction requiring street closure will be
    carried out during off peak hours
  • Enclosure of construction areas, periodic water
    sprinkling, using dust covers to avoid air
    quality related impacts.
  • Reducing noise related impacts by providing
    mufflers on equipment, installing temporary noise
    barriers, not carrying out the activities
    producing noise above 95db(A) during night time.
  • Construction of noise barriers along ROBs

54
CONSTRUCTION STAGE (....contd.)
  • Proper management of labour camps,
  • Planting of trees and vegetation and compensatory
    afforestation
  • Use of appropriate construction equipment, Proper
    disposal of excess earth material,
  • Satisfactory restoration of quarry sites, before
    they are abandoned,
  • Traffic management at construction and quarry
    sites.

55
  • OPERATION STAGE
  • Development of emergency plan in the event of
    road accident involving vehicles carrying
    hazardous material,
  • Establishment of no honking Zones near the
    sensitive areas such as schools, hospitals, etc.
  • Tree plantations along the transport corridors
    and its maintenance
  • Enforcement of road safety rules

56
SUB-PROJECT LEVEL EMP MONITORING
  • Environmental monitoring plans are developed for
    the specific MUTP sub-projects, involving
    monitoring sites, monitoring parameters, time and
    frequency of monitoring and the reporting of
    monitored data. The objectives of the
    monitoring plan are
  • To record the impact of MUTP on urban
    environmental quality To evaluate the
    effectiveness of the mitigation measures
  • To satisfy the legal and community obligations
  • To respond to the unanticipated environmental
    issues at an early stage and to verify the
    accuracy of environmental impact prediction.

57
SUB-PROJECT LEVEL EMP MONITORING
  • At the project level, the vital parameters or
    performance indicators that will be monitored
    during construction and/or operation stages of
    the project include
  • Ambient air quality SO2, PM10, CO, N0x
  • Noise levels near sensitive locations
  • Re-plantation success/ survival rates
  • Traffic volume and characteristics
  • Methodology used for sampling and analysis will
    be as per prevalent requirements of Ministry of
    Environment and Forest and Indian Standard (IS)
    codes.

58
INSTITUTIONAL SET-UP, COORDINATION AND
STRENGTHENING
  • A strong coordinating authority to coordinate the
    activities
  • Institutional capacity building through
    training.
  • Improving air quality and noise monitoring, and
    effective dissemination of information

59
INSTITUTIONAL SET-UP, COORDINATION AND
STRENGTHENING
High Power Steering Committee
IMP
Project Coordination Committee
World Bank
MMRDA Project Director, MUTP JPD (Environment),
MUTP
MSRDC/PWD
MRVC
MCGM
BEST
PMC
PMC
PMC
PMC
Contractor
Contractor
Contractor
Contractor
60
EMP COST-ESTIMATES
  • Cost estimates have been prepared for EMPs
    related to the following tasks
  • Relocation of Utilities
  • Compensatory and Road/Track Side Plantation
  • Pollution control during construction
  • Noise level reduction
  • Labour Camp sanitation, Road safety
  • Environmental Monitoring
  • . The estimated cost of EMP implementation for
    MUTP sub-projects is Rs. 19.38 Million.

61
CONDITION OF CONTRACT DOCUMENT
  • In order to facilitate smooth implementation of
    EMPs, the PIA shall include specific obligations
    in respect of EMP implementation in all tender
    and contract documents. The bidding and contract
    documents shall include the following information
  •  
  • EMP requirements and obligations
  • Environmental Monitoring Requirements
  • Reporting requirements
  • Indicative EMP cost estimates

62
RR- RAP and CEMP
63
RESETTLEMENT REHABILITAION
Total number of PAH 19228 (Project Affected
Households) Number affected by railway
projects 14479 Number affected by road projects
4749. Number of PAH resettled by
June 10118 2001 Total Cost of resettlement Rs.
4607 Million
64
RESETTLEMENT POLICY
  • Objectives of R R Policy are
  • To minimize resettlement
  • Where displacement is unavoidable, displaced
    persons to be compensated for their losses
  • To accord formal housing rights to the PAHs
  • To develop and implement resettlement program
    through active community participation
  • To improve environmental health and hygiene of
    the PAHs
  • To educate, motivate and organise the community
    to manage its environment
  • To retain existing community network in the
    resettlement area and to minimize the adverse
    impact, if any, on the host community

65
RESETTLEMENT POLICY
Entitlement
  • Every eligible household losing a dwelling place
    shall be allotted a dwelling unit of minimum of
    225 sq.ft. at an alternate site.
  • Similarly every PAH losing a commercial structure
    shall be eligible for an alternate place for
    commercial use of equivalent area.
  • Compensation for economic losses e.g extra travel
    cost.

66
ENCROACHMENTS/TRESPASSING
67
PERMANENT TENEMENTS
68
TRANSIT QUARTERS
69
COMMUNITY ENVIRONMENTAL MANAGEMENT PLAN (CEMP)
  • Every site specific RIP will include a Community
    Environmental Management Plan (CEMP).
  • The objectives of CEMP are
  • to provide access to basic urban environmental
    infrastructure services
  • alleviate the environmental health risks of the
    community.

70
CEMP
  • The communities will be trained and motivated to
    follow discipline that can avoid environmental
    problems.
  • Separate Environmental Management Committees
    (EMCs) will be formed to take up this
    responsibility.
  • The CEMP provides preventive maintenance schedule
    for water supply, sanitation, solid waste etc in
    simple local language.
  • Maintenance measures are translated into a simple
    format in the form of "Do's" and "Don'ts" in
    local languages for the community.

71
ORGANISATIONAL RESPONSIBILITIES
  • High Power Steering Committee to oversee the
    progress of MUTP including RR and provide
    necessary policy directions.
  • A Project Co-ordination Committee to supervise
    timely implementation of MUTP including
    inter-agency coordination,
  • An Independent Monitoring Panel (IMP) comprising
    eminent citizens of Mumbai for ensuring
    compliance with accepted policies in project
    implementation

Aggrieved PAH can go to the Grievance Redressal
Committee appointed by the PMU comprising of
officials and representatives of NGOs
72
FEEDBACK
  • Your feedback sent to
  • Project Director MUTP
  • MMRDA
  • Bandra Kurla Complex, Bandra (East)
  • Mumbai 400 051
  • Will be appreciated.

THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com