Title: Highwall Safety for Metal and Nonmetal Surface Mines
1Highwall Safety for Metal and Nonmetal Surface
Mines
- Mine Waste and Geotechnical Engineering Division
- Pittsburgh Safety Health Technology Center
2Ground Control
- Maintaining mass stability by controlling the
movement of excavations in the ground, which can
be either rock or soil
3Ground Control Problems
- Scale
- Mass Stability/Instability - Failure or
movement of massive sections of a highwall or
spoil bank - Falling Rocks - movement of relatively small
loose rocks that are not firmly attached to a
highwall or spoil bank
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10RISK
- CONDITION (HAZARD)
- EXPOSURE
11Preface
- While ground control failures are often easy to
explain after-the-fact, they are often very
difficult to predict before-the-fact. - Minimizing exposure to potential hazards is
always the best policy.
12Risk Avoidance
- Use common sense
- expect the unexpected
- stay alert
- Never place yourself or others in a vulnerable
position, no matter how good the wall or bank
looks
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17Outline
- Highwall Stability
- Spoil Bank Stability
- Stockpile/Surge Pile Stability
- Impoundments / Refuse Piles
18Highwall Stability
19Factors Influencing Rock Cut Stability
- Properties of Intact Rock
- Properties of Rock Mass- joints, faults,
fissures, bedding planes - Water Conditions- rainfall, snow melt, springs or
seeps, ice on highwall face, etc. - Environmental Factors - freeze/thaw, soil/rock
decomposition, etc. - Mining-induced Factors - stress changes, blasting
effects, equipment vibration, etc.
20Types of Highwall Failures
- Planar Failure
- Sliding Wedge Failure
- Toppling Failure
- Circular Failure
- Rock Falls
21(No Transcript)
22Planar Failure
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27Mohr-Coulomb Shear Strength Equation
- ? Shear Strength (psf)
- C Cohesion (psf)
- ? Normal Stress (psf)
- u Pore water Pressure (psf)
- ? Angle of internal friction (degrees)
28(No Transcript)
29(No Transcript)
30Wedge Failure
31(No Transcript)
32Wedge Failure Conditions
- Two discontinuities meet
- Intersection point daylights on highwall
- Line of intersection dips toward the pit
- Weight of sliding wedge exceeds frictional
resistance along the bottom
33(No Transcript)
34(No Transcript)
35(No Transcript)
36(No Transcript)
37Toppling Failure
38(No Transcript)
39(No Transcript)
40(No Transcript)
41(No Transcript)
42(No Transcript)
43(No Transcript)
44Localized Failure -Loose Rocks
45(No Transcript)
46(No Transcript)
47(No Transcript)
48(No Transcript)
49(No Transcript)
50(No Transcript)
51(No Transcript)
52How Do We Handle Loose Rocks?
- The answer depends on whether it is in an area
that requires temporary or permanent stability?
- Longer stability is warranted for - highwall
above portal, road cut, rock-cut spillway, etc.
53Rock-removal methods for slope stabilization.
54(No Transcript)
55(No Transcript)
56(No Transcript)
57(No Transcript)
58(No Transcript)
59Rock slope reinforcement methods
60Slope stabilization with rock bolts.
61Rock BoltUsed to tie multiple pieces of rock
together.
62(No Transcript)
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67Benching
- - Reduces weight (Driving Force) on existing
discontinuities! - - Eliminates some discontinuities!
- - Acts as an effective Rock Catcher!
68(No Transcript)
69(No Transcript)
70Angle Drilling
- In some cases, angle drilling can significantly
reduce the potential for rock falls from a
highwall
71(No Transcript)
72Slope Stability and Water
- Groundwater in slopes is often a contributory
cause of instability. - Water adds weight to the sliding mass, lubricates
the failure planes, and acts as a driving force.
73Effect of Water in Joints
74(No Transcript)
75(No Transcript)
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80Effects of Ice
81(No Transcript)
82(No Transcript)
83(No Transcript)
84Remedies
- Flatten Slopes
- Better Scaling
- Wider Benches
- Monitoring
- Visual
- Instrumentation
85Circular Failure
86(No Transcript)
87Circular Slope Failure
88(No Transcript)
89(No Transcript)
90(No Transcript)
91(No Transcript)
92(No Transcript)
93(No Transcript)
94(No Transcript)
95(No Transcript)
96Working Above and Near the Edge of a Slope or
Highwall
97(No Transcript)
98(No Transcript)
99(No Transcript)
100(No Transcript)
101(No Transcript)
102(No Transcript)
103Causes
- Dragline was not on a firm level bench in full
contact with the ground - elevating the edge aggravated the situation by
causing uneven load distribution with greatest
load right at the edge. - bubble levels were not checked
- Dragline was very close to the edge
- no allowance for change in ground conditions
- Sidewall was not examined for overhangs, etc.
104(No Transcript)
105(No Transcript)
106(No Transcript)
107(No Transcript)
108(No Transcript)
109Causes
- Leveling Jack Set on Soft Material
- Contributing
- Position of the drill
- Long Axis Parallel to Highwall
- Close to the highwall
- Operators cab on lower highwall side
- Lack of Inspection or Recognition of Ground Hazard
110Wedge Failure in Open Pit Highwall
111(No Transcript)
112(No Transcript)
113(No Transcript)
114(No Transcript)
115(No Transcript)
116(No Transcript)
117Highwall Safety
- Program Information Bulletin
- P00-7
- Metal and Nonmetal Mine Safety and Health
118Highwall-Related Accidents 1990-2000
- Highwall Failures
- 6 Fatal Accidents
- Falling Rocks
- 4 Fatal Accidents
- 60 Non-fatal Accidents
- Near Misses ?
119Alerts Mine Operators to
- Hazards Associated with unstable highwalls
- overhangs
- unstable walls, banks, and slopes
- Hazards associated with loose rock accumulating
on or near highwall faces
120- 30 CFR 56/57.3200 any unsafe ground condition
existing where persons work or travel must be
taken down or supported prior to starting work or
traveling in the area.
121- 30CFR56.3130 Mining methods shall be used that
will maintain wall, bank, and slope stability in
places where persons work or travel in performing
their assigned tasks. When benching is
necessary, the width and height shall be based on
the type of equipment used for cleaning of
benches or for scaling of walls, banks, and
slopes.
122- 30 CFR 56.3131 In places where persons work or
travel in performing their assigned tasks, loose
or unconsolidated material shall be sloped to the
angle of repose or stripped back at least 10 feet
from the top of the pit or quarry wall. Other
conditions at or near the perimeter of the pit or
quarry wall which create a fall-of-material
hazard to persons shall be corrected.
123Examination
- 30CFR56/57.3401 Persons experienced in examining
and testing for loose ground shall be designated
by the mine operator. Appropriate supervisors or
other designated persons shall examine and, where
applicable, test ground conditions in areas where
work is to be performed prior to work commencing,
after blasting, and as ground conditions warrant
during the work shift.
124Examination
- 30CFR56/57.3401 (continued) Highwalls and banks
adjoining travelways shall be examined weekly or
more often if changing ground conditions warrant.
125Conclusion
- Preventing ground control problems is one of the
greatest challenges facing surface coal mine
inspectors. - Clues to impending ground instability can often
be found in unlikely places - on top of highwalls
and on the slope of spoil banks - Focus should be on minimizing exposure to
potential ground hazards