CERC%20Terms%20and%20Conditions%20of%20Tariff - PowerPoint PPT Presentation

About This Presentation
Title:

CERC%20Terms%20and%20Conditions%20of%20Tariff

Description:

Terms and Conditions of Tariff ... Some of the Electricity Boards made have made the point that working capital should not include one months O&M expenses. – PowerPoint PPT presentation

Number of Views:273
Avg rating:3.0/5.0
Slides: 15
Provided by: Dtrf
Category:

less

Transcript and Presenter's Notes

Title: CERC%20Terms%20and%20Conditions%20of%20Tariff


1
CERC Terms and Conditions of Tariff
  • This presentation will only highlight the
    relevant financial principles and operation
    norms. APERC would like to put forward for the
    consideration of CERC in the Policy paper to be
    issued on Terms Conditions of Tariff
  • Written response was sent to the Commission vide
    letter APERC/SECY/D.No. CERC-3/2003- 2.8.2003
  • The norms are based on the experience of APERC,
    however ERCs are open to improve these norms

2
Clarification on Intervening Transmission
facilities
  • View of CERC is sought on intervening
    transmission facility and why a separate
    treatment has been provided for in the Act when
    there is open access.

3
Financial Principles
4
Tariff Setting Financial Principles
  • Advocates forward looking principles
  • The rate of return must be commensurate the risks
    involved in the business and the macro economic
    environment.
  • Moving forward is critical
  • Compensate the developer for the risks incurred
    by allowing a margin over and above the current
    bank rate. The margin be open for negotiation.
  • The consumer to benefit from prevailing falling
    interest rate regime.

5
Tariff Setting Financial Principles
  • Cost of Capital
  • CERC to determine the rate base (either debt or
    equity or both) for computing returns
  • Interest shall be benchmarked to Prime Lending
    Rate plus debt margin to reflect credit
    worthiness
  • Return on Equity shall be pegged at Bank Rate
    plus a margin to reflect the investment risk in
    the power sector
  • Foreign Exchange Risk Variation
  • Foreign component may be converted into rupee
    terms at the Commissioning date

6
Tariff Setting Financial Principles
  • APERC accepts the suggestion of CERC that ROCE
    can be evolved by bench marking the debt equity
    ratio.
  • Debt to be pegged at PLR margin
  • Equity to be pegged at Bank Rate margin
  • The return should recognize the concept of time
    value of money and it should be ensured that only
    the approved return (IRR) should be permitted to
    the investor on annual basis
  • This should be applied uniformly for existing and
    new generation projects.

7
Tariff Setting Financial Principles
  • Depreciation
  • Depreciation rate should be linked to the life of
    the asset
  • To avoid front loading of tariffs by way of
    advance against depreciation, benchmarking the
    term of debt (12 yrs as followed earlier by CERC)
    could be considered, irrespective of tenure of
    debt.
  • The current practice of Short-Term Loans being
    utilised for funding the assets needs a re-look.
  • To explore Rolling of Debt by way of Call and
    Put options should be encouraged.
  • Treatment of Tax
  • Post Tax return shall be provided to protect the
    investors from changes in the law of land
  • However, adjustments shall be made in the revenue
    requirement to reflect actual outflow of taxes
    paid.

8
Tariff Setting Financial Principles response to
specific suggestions
  • CERC Suggestions
  • Aggregated rate base v/s disaggregated Rate Base
  • Initial capital expenditure will be the capital
    cost
  • Norms on capitalized initial spares as a
    percentage of approved project costs or actual
    expenditure whichever is lower.
  • APERC Response
  • Aggregated rate base total Fixed assets as per
    the balance sheet, less assets not related
    regulated business.
  • Initial capital expenditure will be the capital
    cost. But preferable to to include township
    rather than take it as additional capital
    expenditure. Maintenance of Asset Register
    should be mandatory.
  • Capitalizing of initial spares should be allowed
    on recommendations by the expert group

9
Tariff Setting O M
  • For new projects, the current CERC norm of OM be
    capped at 2.5 (Thermal) and 1.5 (Hydro) of the
    approved project cost at the start of a control
    period may be continued. The same may be
    reviewed at the end of the control period to
    check if the level of O M expenses.
  • For existing projects the OM cost for the first
    year of control period should be based on the
    average annual actual expenditure (excluding
    abnormal expenses) for the past five years.
  • The existing formula for escalation (60 WPI and
    40 CPI) be continued for the generation sector.
    For transmission sector the CPI weight age may be
    increased.
  • Benchmarking the OM expenditure to the approved
    project cost and in a situation of the project
    being awarded through competitive bidding route
    reduces the risk of over capitalisation. OM
    being computed based on macro numbers like RS Crs
    per MW etc will not provide a true reflection of
    the project cost and instead might involve many
    assumptions like separate numbers based on the
    fuel type, type of hydro project etc.

10
Tariff Setting Working Capital
  • Continue with the existing arrangement. Some of
    the Electricity Boards made have made the point
    that working capital should not include one
    months OM expenses. But the existing procedure
    of offering rebate of 2.5 for payment through LC
    and 1 for payment within the due date addressed
    this issue.

11
Tariff Setting Development Surcharge
  • There is no linkage between development surcharge
    and depreciation as the latter is meant to
    compensate for the wear and tear of existing
    projects and at best the repayment of loans.
    Whereas the development surcharge is intended to
    be used for setting up Central Generating
    Projects in future.
  • In future with the liberalisation of the
    generation sector (and consequent availability
    from IPPs and state generation) the requirement
    of power from Central Generating Stations may be
    reduced. Hence blocking the funds through such
    contributions will further deteriorate the
    financial health of the Utilities.

12
Tariff Setting Control Period
  • The tariff period may be kept as five years with
    a provision for review of the norms during the
    period to reflect improvements in technology and
    general macro economic environment.
  • However any changes in the norms must only be
    done with prospective effect.
  • The tariff for generation should be station
    specific.

13
Tariff Setting Availability Based Tariff
  • The implementation of separate tariffs for peak
    and off peak generation will be contingent upon
    the metering infrastructure, the ability of the
    constituents to manage their respective demand
    and also its co-ordination with ABT regime.
    Given the nascent stage of implementation of the
    ABT regime it is advised to have time
    differentiated generation tariffs at a later
    date.
  • The capacity should be declared ex-bus in MW
    terms
  • The auxiliary energy consumption should not
    include the supply for construction power and
    residential townships and must be computed
    station wise.

14
THANK You
Write a Comment
User Comments (0)
About PowerShow.com