Title: Mr. Mike Salawou, NEPADIPPF Task Manager, Nepad Division, ADB
1NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Presented by
- Mr. Mike Salawou,NEPAD-IPPF Task Manager, Nepad
Division, ADB - 6th NEPAD-IPPF Oversight Committee Meeting,
Lusaka June 25th , 2007
2NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Outlines
- Togo-Benin-Ghana Power Interconnection
- Eastern African Submarine Cable Systems (EASSy)
- Kenyan-Uganda Oil Pipeline
- Tanzania-Zambia-Kenya Power Interconnector
3NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Togo-Benin-Ghana Power Interconnection
4NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Key Facts
-
- Date of IPPF Approval 27 October 2004
- Preparatory Activities Financing sources
- NEPAD-IPPF USD500,000
- DBSA-AFD PPF USD300,000
- BOAD USD510,333.31
- VRA USD359,611.69
- Physical Project Costs Estimates USD118 million
- Objectives
- To support the Governments of Benin, Togo, and
Ghana through their power utilities to update the
feasibility study and detailed designs of the
Benin-Togo-Ghana electricity interconnection, and
the development of a detailed Environmental
Impact Assessment for the project.
5NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Achievements so far
- The preparatory activities of the project for
which the NEPAD-IPPF grant was made had been
successfully completed. - On the basis of the outputs of the preparatory
activities supported by the IPPF, the project has
achieved financing for physical implementation
from ADF, IDA, IsDB and BOAD. - Based on the revised cost of the project
determined from activities supported by
NEPAD-IPPF, the ADF has approved financing of
USD48.36million, IDA has approved financing of
USD14.63million, IsDB has approved financing of
USD13.66million and BOAD has approved financing
of USD13.35million for the project.. The balance
of the funds of USD17.30million is provided by
the beneficiaries Volta River Authority
(USD7.40 million) and Central Electricity Board
of Togo and Benin ( USD9.90 million).
6NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Eastern Africa Submarine Cable System, EASSy
7NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Key Facts
-
- Date of IPPF Approval 23 August 2005
- Preparatory Activities Financing sources
- NEPAD-IPPF USD500,000
- DBSA-AFD PPFS USD142,210 EUR45,000
- DBSA USD500,000
- FAPA USD500,000
- Other DFIs
- EASSy USD39,600
- Physical Projects Estimated Costs USD235 million
- Project Company (SPV) Registered and
incorporated SPV as the Western Indian Ocean
Cable Company (WIOCC) - Objectives
- To assist in the transaction analysis phase of
the project as well as update the Environmental
and Social Impact Assessment (ESIA) to enable the
project to reach financial closure and physical
implementation.
8NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Achievements so far
- Project Company (SPV) Registered and
incorporated SPV as the Western Indian Ocean
Cable Company (WIOCC) - The financing plan for the EASSy project has been
finalised. Firm commitments to finance the
project has been secured from ADB, IFC, EIB. KfW,
DBSA, and AFD/Proparco. - With the exception of DBSA who have already
approved financing for the project, other
financiers are currently processing their
Investment proposals for presentation to their
respective Boards. It is projected that
financial closure for the project will be
achieved by the end of the 3rd quarter of 2007.
9NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Kenya Uganda Oil Pipeline
10NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Key Facts
-
- Date of IPPF Approval 5 November 2004
- Preparatory Activities Financing sources
- NEPAD-IPPF USD 454,000
- DBSA-AFD PPFS USD300,000
- GoK and GoU USD0,038 each
- Physical Project Estimated Costs USD 75million
- Objectives
- The objective of the grant for which the
NEPAD-IPPF was approved is to support the
Governments of Uganda and Kenya in the
solicitation process for a private sector
investor in the project. This entailed the
preparation of tender process leading to bidding,
evaluation, negotiation, award and contract for
joint venture with a private sector investment
partner, and assistance to the Governments of
Uganda and Kenya in securing financing for the
project.
11NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Achievements so far
- Following an international competitive bidding
process lunched in 2005, TAMOIL was selected as
the strategic partner and developer for the
project on July 2006. - Negotiation with the preferred bidder was held in
Kampala in August 2006. As a result of these
negotiations, a Heads of Agreement was signed
between the preferred bidder Tamoil and the
countries on - Following detailed negotiations, on January 27th
, 2007 a contract award of US80-million was made
to Tamoil to build and operate the
Eldoret-Kampala oil pipeline extension. - The construction works on the pipeline is
scheduled to commence by July 2007. Completion of
construction is scheduled for by August 2008. - Following the successful delivery of the project
as highlighted above, Rwanda is discussing with
the governments of Uganda and Kenya for extension
of the Pipeline to Rwanda. .
12NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Zambia-Tanzania-Kenya Power Interconnector
13NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Key Facts
-
- Date of IPPF Approval 17 December 2004
- Preparatory Activities Financing sources
- NEPAD-IPPF USD 500,000
- DBSA-AFD USD 300,000
- Physical Projects Estimated Costs USD million
- Objectives
- The scope of activities of the
Zambia-Tanzania-Kenya Electricity Interconnection
supported by the NEPAD-IPPF Special Fund consists
of four distinct phases, namely, Pre-Development
Phase, Investor Selection Phase, Concession
Negotiation Phase, and Financial Closure Phase.
The IPPF support is to facilitate the engagement
of a private sector participant in the project
and achievement of financing for physical
implementation.
14NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Achievements so far
- The first phase of activities, namely,
preparation of a Project Information Memorandum
(PIM) has been completed and is currently under
review by the Executing agency, the NEPAD-IPPF,
the DBSA-AFD PPFS and other stakeholders.
15NEPAD Infrastructure Project Preparation Facility
(NEPAD-IPPF)
- Contacts
- Focal Point
- Mike M. B. SALAWOU
- NEPAD-IPPF Task Manager
- NEPAD, Regional Integration and Trade Department
- African Developement Bank
- Tel (216) 71 10 30 77
- Fax (216) 71 33 26 94
- m.salawou_at_afdb.org
- Ini Urua
- Manager, NEPAD Division
- Tel (216) 71 10 3053
- Fax (216) 71 33 26 94
- E-mail u.ini_at_afdb,org
16- Thank you for your kind attention