Working Group Status - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Working Group Status

Description:

Formally close group last meeting 21st October ... Execute engagement calendar for formal review using agreed review guidelines. 13. 13 ... – PowerPoint PPT presentation

Number of Views:96
Avg rating:3.0/5.0
Slides: 14
Provided by: neilarmstr
Category:

less

Transcript and Presenter's Notes

Title: Working Group Status


1
Working Group Status
RAG
Oct 08
Architecture Framework Network
Structure Systems Processes Products Interc
onnect Portfolio Broadband Line
Access Point to Point Implementation
Migration Communications Contracts
G
G
A
A
G
R
A
G
G
2
Network Structure
  • RAG Status Green
  • Key Issues

Key Milestones
  • October Achievements
  • Complete work on communication of Inventory
    datasets
  • Move group into new C21 Structure
  • Formally close group last meeting 21st October
  • Compile a list of actions/issues to take to the
    Portfolio group as part of the new structure
  • WVC condoc summary response issued and work
    started on E2E process
  • Nov Work plan
  • To be determined by issues taken to Portfolio
    group

Time (A)
Cost (G)
Quality (G)
Customer Satisfaction (A)
Information (G)
Status
3
Systems Processes (SP)
  • Key Milestones
  • Sept/Oct 2008 Achievements
  • SP (now including 21C Customer Experience (21C
    CE))
  • The main activity this period was progressing the
    key customer impacting areas of our CE programme.
    Please see the CE reports available _at_
    http//www.btwholesale.com/21CCE for more
    details, to raise issues or make comments.
  • Web calls and expert groups run in the period by
    SP WG, some jointly with NICC B2B 21C CE.,
    covered billing, service catalogue and inventory,
    address matching and appointing. See the 2008
    Meetings page on the Consult21 Systems
    Processes Working Group web site for more
    details.
  • Please note the Consult21 Systems Processes
    Working Group (SPWG) web pages have been updated
    to reflect the relationship to NICC B2B 21C CE
    and list all the meetings in one place.
  • NICC B2B Standards Best practice
  • Four NICC B2B meetings were held in this period
    to progress the work programme for 2008 based on
    the highest priority industry issues below
  • The Address Location Identification principles
    paper has been approved for publication. It is
    now proposed that Appointing and Access will be
    progressed via the new 21CN product development
    for WBCC/WVC. Once E2E scenarios and detailed
    scenarios for appointing and arranging access
    have been agreed we will agree generic standard
    for reuse on future products. Billing will now be
    progressed on the basis of BT to its customers to
    start. Any generic issues requirements will, if
    applicable, be added to the NICC B2B standards
    best practice work programme.
  • All CPs are encouraged to comment and contribute
    to the work. Please contact graham.crane_at_bt.com
    for more information or visit the
    www.niccb2b.org.uk web site
  • Oct/Nov 2008 Work plan
  • SP WG/21CCE The next in a series of 21C CE
    events is being arranged for early December. This
    will kick off a programme for CPs of information
    sharing web calls followed up with experts groups
    where required.
  • A web call has been set up on 22th October for
    (high volume) call conveyance billing. A follow
    up call for the low volume billing workshop will
    be arranged late Nov. A meeting to discuss
    service catalogue and inventory has been arranged
    for 23rd October.
  • Details of all past and future meetings and
    audios including SPWG, NICC B2B 21C CE will
    appear on the SPWG meeting pages
  • The SP WG would continue to provide support to
    IM WG on operational support systems issues as
    DSP progresses and product WGs as required.
  • RAG Status Green
  • Key Issues (For Discussion)
  • Issues discharged from here to the relevant WG,
    ie IM WG in most cases.

Time (G)
Cost (G)
Quality (G)
Customer Sat. (G)
Information (G)
Status
4
Interconnect Portfolio
  • RAG Status Amber
  • Key Issues (For Discussion)
  • Awaiting early feedback from CPs following BTs
    presentation of the Options considered in light
    of the introduction of a 2nd Call Server. The
    full implications for NGN CC are yet to be
    scoped.
  • Key Milestones
  • October Achievements
  • Ongoing work on NGN CC billing actions, and NGN
    CC contract schedules.
  • Agree NGN CC related tasks and any other IP
    related tasks to put forward to the Portfolio
    meeting on 6th November.
  • November Work plan
  • Review NGN CC Interoperability meeting Date TBC
  • NGN CC contracts meeting Date TBC
  • Implement new Experts Groups for NGN CC
  • Ensure an Expert Group is set up to assess the
    impact of the 2nd Call Server on NGN CC, and
    agree what consultation needs to take place.
  •  

Time (A)
Quality (G)
Customer Sat. (A)
Information (A)
Cost (G)
Status
5
Broadband
Key Milestones
  • RAG Status Amber
  • Key Issues
  • Committed launch date for WBMC consuming IPSC
  • DDQ Real-time elements of WBC Indicative Launch
    pricing
  • WBC DDQ pricing is key to a successful
    consultation on IPstream Datastream sunsetting
  • October Achievements
  • BBWG held on 25th September covered updates on
    FTTx, WCC, WBC Roadmap and WBMC consuming IPSC
  • FTTx Workshop held on 10th October to review
    opportunities and requirements for Superfast BB
    and understand how BTW can consume the new
    Openreach NGA products into the WBC product.
  • WBC QoS Webcall planned for 23rd October to
    provide a tutorial on the proposed QoS model,
    including commercials, SLAs and associated
    measures. Will help to raise awareness and set
    the scene for a follow-up workshop looking at
    VoIP/Real Time requirements for WBC/WBMC.
  • November Work plan
  • The restructure is likely to mean that the BBWG
    will not continue in its current format.
    Intending to hold a 6 weekly update call starting
    early in November to allow CPs to keep in touch
    with progress and developments across the BB
    portfolio.
  • WCC workshop scheduled for 5th November to review
    the technical design/commercial proposal for this
    product and progress interest in a market trial
    in January 2009
  • Resilience workshop to be held to understand
    requirements for the new BB products (WBC, WBMC
    and IPSC) from an end-to-end perspective
    (including MSIL access)
  • Draft and issue the consultation closure
    documents for IPstream Sunsetting and SDSL Market
    Analysis consultations.
  • Issue next Datastream Sunsetting CONDOC

Time (A)
Cost (G)
Quality (G)
Customer Satisfaction (A)
Information (A)
Status
6
Line Access
  • RAG Status Green
  • Key Issues

Key Milestones
  • Oct Achievements
  • WVC condoc summary response issued and work
    started on E2E process
  • Further update on WBCC product development and
    project plans
  • Technology trial of WBCC discussed
  • Implement new C21 structure formally close group
    and agree issues and actions plans for new
    experts group.
  • Last meeting 21st October
  • Nov Work plan
  • None group closed

Time (A)
Cost (G)
Quality (G)
Customer Satisfaction (G)
Information (G)
Status
7
Point to Point as of 20th October 08
  • RAG Status Red
  • Key Issues (For Discussion)
  • Exchange Openings and Closures. workshop held
    14th August, with cross BT LoBs in attendance,
    good progress being made
  • There is a potential dispute between BT and CPs
    over what constitutes mutual interconnect and
    this has implications on space allocation, BTW
    and Openreach RAD now engaged
  • TDM fease for 21CN PPCs based on EOO not EOI,
    regulatory position and product impact needs to
    be clarified.

Key Milestones Sep/Oct Achievements Continued TDM
exerts group with successful meeting in early
September September WG held with 3 CP in
attendance 10G MSIL now launched (IBH/APH
variants) with final testing of key processes
substantially complete with no major outstanding
issues Progress made on exchange management via
group portfolio forum (gaining lock in with
LoBs)
Oct/Nov Work plan Next meeting set for 7th
November as an audio following the TDM experts
meeting Conclude TDM (2Mbit/s) feasibility
progress, initiate sub 2Mbit feasibility
work Resolve final exchange management
questions
Time (R)
Cost (G)
Quality (G)
Customer Sat. (G)
Information (G)
Status
8
Implementation Migration (CT)
  • Key Milestones
  • Sep/Oct Achievements
  • Completed the evaluation process to underpin
    longer term solution for PSTN TCP Pre migration
    activity
  • Reviewed the CP hand book and have a tactical
    solution for Nelson
  • Statement issued to confirm the understanding of
    the MDS and provided a feedback loop
  • Initial plans for operational readiness war
    gaming discussed and agreed with CPs
  • Oct/Nov Work plan
  • Update pathfinder definitions document for
    Pathfinder activity (C21-IM-013) in support of
    21CN Deployment Plan BT/CP discussions to date
  • Complete the evaluation process to underpin
    longer term solution for grooming and ISDN230
    pre migration activity
  • Execute the operational readiness war gaming and
    process walk troughs'
  • Document the scenarios within the CP handbook
  • Line regression war gaming
  • RAG Status Amber
  • Key Issues (for discussion)
  • Further clarity is required on ISDN timeframes,
    migration dates and methodologies that relate to
    CPs and end customers
  • Pre-migration scheduling solution required for
    national migration including grooming ISDN
  • Fit for purpose MCC portal and handbook in place
    for start of PF migration.
  • Clarity on the impacts of the detail that will be
    included in the MDS
  • accuracy of PEW s is still an issue

Time (A)
Cost (G)
Quality (G)
Customer Satisfaction (G)
Information (A)
Status
9
Pathfinder 1 Operational Readiness (for Nelson)
18.09.08
10
Interconnect Route Migration (DLE offload via
VICs) Review
  • BT has completed formal VIC Consultation closure
    process through IPWG no objections
  • CMRs are now available to CPs through the DEDs
    system on a weekly basis
  • Good feedback from CPs that transfer process now
    operating smoothly
  • Completion of T3a activity by all CPs will give
    final validation that all green elements can be
    moved to blue for complete
  • Progressing early visibility of DLE Offload
    schedule (6-12 months) to facilitate early start
    to the programme

Update 16/09/08
11
Migration Communications
  • RAG
  • status
  • Green

October 08 achievements Webcalls The first
quarterly webcall on BTs 21CN programme was held
on 17th October with 78 attendees. Positive
feedback received, although feedback on the
content was that it was too general. A webcall on
WBC QoS will take place on 23rd October being
completed as part of the Broadband working
group. Switched-on information Switched-on door
drop will commence from Nelson onwards. The
corporate area of the switched-on website has
been refreshed and restructured a test link
will be sent to the comms working group for
feedback. The criteria for SME future mailings is
now defined as up to 250 employees, rather than
up to 250 employees and single site. This was
agreed at the October working group. Non engaged
CPs with customers in the Pathfinder area an
awareness campaign has begun, working closely
with the IMWG buddy and Openreach. An initial
hook email has been sent and will be followed
by a key information briefing. November 08 work
plan Communications working group 7th November
and will include an update on the switched-on
door drop evaluation ideas and methods Reseller
communications expert group 14th November A
webcall on CPE is planned for 26th
November Refresh of the reseller area of the
switched-on website Further work on the awareness
communications for those non-engaged CPs with
customers impacted by Pathfinder.

Time (A)
Cost (G)
Quality (G)
Customer Sat. (G)
Information (G)
Status
12
Contracts (MSA) as of 20th October 08
  • RAG Status Green
  • Key Issues (For Discussion)
  • Progress made but require final evidence on
    product launch process giving timely contractual
    documentation for next set of product launches

Key Milestones Sep/Oct Achievements Continued to
work through formal review. Have had a
productive session with the BTW MSIL product
line Have initiated review for WBC
Oct/Nov Work plan Execute engagement calendar for
formal review using agreed review guidelines
Time (A)
Cost (G)
Quality (G)
Customer Sat. (G)
Information (G)
Status
13
WG Issues RAGs
  • Working Group Issues are defined as problems that
    are within the WG scope and will impede the
    progress of the WG and cannot be totally
    resolved, without delaying known milestones, by
    the WG without outside help.
  • The outside help will be triggered by a formal
    escalation. Any WG that has one or more
    escalations currently flagged will be deemed to
    be in status Red (shown against time indicator).
    If an issue has the potential to delay a key
    milestone it should raise an Amber status flag,
    but no formal escalation will be raised. Once the
    escalation has been dealt with and appropriate
    guidance given the escalation will be closed and
    the WG status will revert.
  • Other WG RAG status influences will be Cost,
    Quality Customer Satisfaction Information, as
    in table below.
Write a Comment
User Comments (0)
About PowerShow.com