Integration of Variable Generation Task Force IVGTF - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Integration of Variable Generation Task Force IVGTF

Description:

7 Issues Identified by NERC Staff & RAS, prioritized: Greenhouse gas reductions ... PC assigns RIS, RAS & TIS to develop list of emerging issues ... – PowerPoint PPT presentation

Number of Views:60
Avg rating:3.0/5.0
Slides: 20
Provided by: KarenS123
Category:

less

Transcript and Presenter's Notes

Title: Integration of Variable Generation Task Force IVGTF


1
Integration of Variable Generation Task Force
(IVGTF) Emerging Issues
Mark LaubyManager, Reliability
Assessments mark.lauby_at_nerc.net
2
About NERC
  • The electric industrys self-regulatory
    organization for reliability
  • Balances the interests of all stakeholders
  • Represents industry consensus
  • Independently acts in the best interest of
    reliability
  • International charter lending government
    support and oversight to SRO activities, ensuring
    that the best interests of society-at-large are
    represented
  • Federally recognized Electric Reliability
    Organization in the U.S.
  • Agreements in place with several Canadian
    provinces and developing these agreements in
    others

3
About NERC Mission
To ensure the reliability of the North American
bulk power system
  • Develop enforce reliability standards
  • Assess current and future reliability
  • Analyze system events recommend improved
    practices
  • Encourage active participation by all
    stakeholders
  • Pursue mandatory standards in all areas of the
    interconnection

4
2007 LTRA Report
Integration of Wind Solar Resources Require
Special Considerations in Planning, Design,
Operation
  • Operational challenges must be resolved
  • Transmission needed to support renewable
    development
  • Clean Energy Superhighway
  • NERC to monitor federal carbon legislation for
    impact on reliability

5
NERCs Actions
  • Evaluate operational requirements
  • Recommend standards.
  • Develop a consistent approach for rating variable
    resources
  • Available capacity at time of system peak
  • Developed Integration of Variable Generation Task
    Force

6
Engaging Industry Experts
  • Integration must support a reliable bulk power
    system
  • Variable Resources affect planning/operations
  • Reviewed by the Operating Planning Committees
    in December 2007
  • Integration of Variable Generation Task Force

7
IVGTF Scope
  • The Task Force will prepare
  • A concepts document that includes the
    philosophical and technical considerations for
    integrating variable resources
  • Specific recommendations for practices and
    requirements, including reliability standards,
    that cover the planning, operations planning, and
    real-time operating timeframes.
  • The document will include
  • Planning timeframe issues, such as contribution
    to reserve margins and modeling requirements to
    test system reliability,
  • Operational Planning and Real-time operating
    timeframe issues, including Interconnection
    frequency, and primary and secondary generation
    control
  • Review NERC Standards for any gaps
  • Conclusions and recommendations.

8
IVGTF Guiding Principles
  • Bulk power system reliability must be
    maintained, regardless of the generation mix
  • All generation must contribute to overall bulk
    power system reliability
  • Standards and criteria established must be fair,
    transparent and performance-based
  • Planners and operators must understand the
    challenges presented by large scale integration
    of variable generation
  • Wind and other variable generation must
    effectively integrate into planning and
    operations practices to ensure reliability
  • New Planning/operating tool requirements will be
    described in terms of bulk power system
    reliability performance

9
IVGTF Outline of White Paper
  • Characteristics of Variable Generation
  • Planning and Technical Impacts
  • System Operations
  • Other and Future Considerations
  • NERC Standard Review
  • Conclusions Recommendations
  • Glossary

10
IVGTF Status
  • High Industry Interest
  • 50 Nominations received
  • Liaisons being built with Industry Groups
  • American Wind Energy Association (AWEA)
  • Canadian Wind Energy Association (CanWEA)
  • Utility Wind Integration Group (UWIG)
  • Solar Energy Industries Association (SEIA)
  • IEEE-PES
  • EPRI
  • U.S. Department of Energy
  • Union for the Co-ordination of Transmission of
    Electricity (UCTE)

11
IVGTF Status Work Plan
12
Emerging Issues Scenarios
13
2008 Key Findings Emerging Issues
  • Collaborative Effort with NERC Staff
  • Packaging
  • Condense focus to no more than five key
    emerging issues
  • Broader issues do not change year to year create
    separate document
  • Divide Key Findings section into
  • Key Findings from Regional Assessments
  • Emerging Issues from the industry
  • Specific Emerging Issues identified
  • Progress from 2007 Report section

14
Risk Assessment of Emerging Issues
  • Emerging Issues is critical driver for
  • Assessment concentration
  • Scenario analysis
  • Industry experts to identify Emerging Issues for
    prioritization
  • Ranking based on combination of likelihood
    severity (consequences)
  • To manage expectations and speculation by
    regulators legislators about how utilities
    should respond to these issues
  • To inform the policy debate

15
2008 LTRA Emerging Issues
  • 7 Issues Identified by NERC Staff RAS,
    prioritized
  • Greenhouse gas reductions
  • Fuel storage transportation
  • Rising global demand for energy equipment,
    increased off-shore manufacturing of raw
    finished materials
  • Increasing adoption of demand-side distributed
    generation resources
  • Replacing and upgrading transmission
    infrastructure for the 21st century
  • Water usage
  • Mercury emissions
  • RAS will expand on a number of these in the 2008
    LTRA

Priority
16
Candidate Scenarios
  • Should have significant impact on the reliability
    of the bulk power system
  • Must be a future condition providing enough
    lead-time for assessment to inform a solution
  • Selected with consideration for the definition of
    Adequate Level of Reliability
  • Will be ranked by NERC PC based on likelihood
    severity

17
Emerging Issues Scenarios
Year 1
Year 2
LTRA Published
RAS Peer Review Scenario
PC assigns RIS, RAS TIS to develop list of
emerging issues
NERC Staff
Regions perform Scenario Reliability Assessment
PC agrees to scenarios for the following year,
based on risk assessment of emerging issues.
Scenario study outline peer reviewed by RAS PC
RAS assigns scenarios. Sends with LTRA Data
Request.
Regions develop Scenario Study Outline
18
2008 Emerging Issues Scenario Analysis
  • Scenario 1 Study renewable integration in
    2009. If there is little or no impact of
    Scenario 1 on a region, then the Region must
    perform Scenario 2
  • Scenario 2 A scenario picked by the Region for
    study in 2009
  • Details of scenarios would be proposed by
    Regions, coordinated with RAS, and approved by
    the PC at June 2008 meeting

19
Thank You