Title: The CERN Antiproton Decelerator AD
1The CERN Antiproton Decelerator AD
- Â
- Â Performance, developments and future
possibilities - Â
2The CERN Antiproton Decelerator
3Run statistics
4HW breakdowns in 2004
- PS ejection septum
- Water leak May 1 week stop to replace with
spare unit. - Spare unit develops same failure in July 3
weeks stop to repair spare and install. - AD electron cooler vacuum
- 2 weeks stop in June excessive outgassing in
collector region caused de-activation of NEGs.
Dissasembly, inspection, replacement of all
suspect parts, bakeout.
5Peak beam intensity
6Current status, ejected beam
() nominal/peak
7Multiejection
- Simple scheme introduced at 100 MeV/c using
existing RF-HW minimal modifications. - Bunching on h1,3 or 6 is possible with present
RF-HW. - 2.4 s. rep.rate imposed by ejection magnets.
- Good efficiencies and beam lifetime obtained. (12
s. longer coast at 100 MeV/c _at_ h6)
8Current limits beam intensity
- Proton beam 1.5E13 on target, only marginal
improvements can be obtained in the PS-complex,
mainly limited by spacecharge effects in PSB - 25 increase can be had with 5-bunch beam (now
4), need 2 injections/cycle into PS and 3.6 (now
2.4) s cycle. Modifications in PS required - Stacking mode studied, a certain increase can be
expected but tradeoff against cycle length.
Modifications in PS required - Target/collector set-up for reliability rather
than max. yield - Transverse acceptances close to optimum
- Losses during cycle balanced vs. cycle
length/rep. rate
9Current limits cycle length
10Current limits cycle length
- From 140 to 84 seconds in 5 years
- Ramp length
- Field lag modifies tunes/orbits during ramps and
arrival at plateaus, only B-main is compensated
at plateau arrival losses if ramps are too steep
(15 2GeV/c 300MeV/c) - Fast eddy currents in vacuum chamber can modify
tunes as much as 0.01 and provoke large orbit
excursions of up to 35mm _at_ 300MeV/c with current
slope, nothing can be done about this - Tunes cannot (yet) be measured on ramps
- Ramp shape can be further somewhat optimised
11Current limits cycle length
- Beam cooling
- Stochastic cooling well optimised. Some losses of
particles with large momentum offset at 3.5GeV/c
are caused by limited momentum acceptance of
cooling system - Electron cooling is slower than foreseen due to
- Alignment problems e-Pbar, better correctors
needed - Large initial emittances (see above) due to
adiabaticresonant blowup during ramps - Slow cooling at beginning of plateau due to field
lag - Attempts to find better parameter settings with
Betacool simulation will be done - Other.
12Current limits cycle length
13Current limits beam densityCapture and ejection
14Current limits beam density
- Cooled beam at 100MeV/c
- Vertical planeok
- Horizontal planeDense core with halo, caused
or aggravated by interaction between the
RF-system and the electron cooler
15Transverse beam profile at 100 MeV/c
- Severe halo structure develops mainly during
ejection bunching. - Debunching with ecooler at nominal voltage also
contributes. (was done to gain time) - Some overlap Vrf Vec was found at ejection
bunching.
16Transverse beam profile at 100 MeV/c, present
situation
- Ecooler voltage is close to zero during
debunching at beginning of plateau. - At ejection, ecooler voltage is ramped down just
before Vrf reaches max. - Bunch length around 100ns.
- Small residual halo still there.
17Reduction of dp/p
- Longitudinal phase-space tomography with moving
bucket - Deceleration 300-100 MeV/c with reduced voltage
(3kV 500V) - dp/p reduced by 50
18Current limits other
- Experimental area beamline switching
- Delays due to inherent AD stability problems at
low energy - Re-tuning of lines often necessary, slow process
due to slow repetition rate and destructive BPMs - Non-destructive BPMs would allow on-line
measurements and corrections - Tests of switching each cycle could be done if
needed, uncertain if possible with present
magnetic elements
192005 activities
- Improvement of ecooler
- Vacuum renew and add NEGs
- Ecooler BPMs improve shielding
- Improved correctors for better alignment at 300
MeV/c - AD consolidation programme worked out and
included in the general AB plan.
202006 run
- On the draft schedule (for the moment)
- Reduced physics run June 5 September 3
- 7d/7, 24h/24 approx. 2000 h of physics.
- Approval issues remain.
21Future possibilities
22Future possibilities ELENA
- How do we gain in intensity with an added
decelerator/cooler ? - Beam from AD 3 107 antiprotons per 84s cycle at
5.3 MeV kinetic energy with transverse emittances
1 to 2 p mm mrad. - Use a small ring to further decelerate beam to
100 keV, increase density by electron cooling - Use of a much thinner degrader will significantly
reduce adiabatic blowup and scattering gt two
orders of magnitude gain in intensity is expected
for ATHENA and ATRAP. - Beam emittances after deceleration and cooling in
ELENA will be much smaller than after the RFQD gt
one order of magnitude gain in intensity is
expected for ASACUSA. - 100 keV kinetic energy is close to optimal both
from the point of view of beam intensity,
momentum spread and separation of transfer line
and trap vacuum.
23Future possibilities ELENA
- Compact machine located inside of AD Hall with
minimum of rearrangement. - Energy range from 5.3 MeV to 100 keV.
- Equipped with electron cooler
- Machine assembling and commissioning has to be
done without disturbing current AD operation. - A similar ring for decelerating antiprotons
from LEAR was proposed by H.Herr in 1982.
24ELENA ring configuration
25ELENA main parameters
26ELENA cycle
- No electron cooling is performed at injection
beam is already cooled in AD. After injection
beam is decelerated immediately. - One intermediate cooling (at 40 MeV/c probably)
is needed to avoid beam losses
27ELENA in the AD hall
28ELENA in the AD hall
29Current status
- ELENA proposal supported by SPSC
- AB department is waiting for decision by CERN
management - Consequences for AB if we follow SPSC
- Need to do a study that defines
- Expected beam density increase
- Costs
- Beam sharing between users
- Set-up and commissioning plan
30Conclusions
- AD routinely surpasses the design goals for pbar
flux and beam density - Further (limited) improvements could be
considered - Tuning and development is slow due to long cycle
and low beam intensities - ELENA would open up new possibilities and
challenges..
31Longitudinal phase-space tomography, 2 GeV/c
32Longitudinal phase-space tomography, 3.5 GeV/c
33Longitudinal phase-space tomography, 100 MeV/c
34Future possibilities ELENA
- Beam from AD 3 107 antiprotons per 84s cycle at
5.3 MeV kinetic energy with transverse emittances
1 to 2 p mm mrad. - How antiprotons are decelerated further today
- Experiments with antihydrogen program (ATHENA and
ATRAP) use degraders to slow the beam further
poor efficiency due to adiabatic blow up and
scattering in the degrader. - ASACUSA uses RFQD for deceleration down to around
100 keV kinetic energy. Due to absence of
cooling, beam deceleration in RFQD is accompanied
by adiabatic blow up (factor 7 in each plane)
which reduces trapping efficiency.
35ELENA how we define limit on tune excursion?
- MD studies in AD for investigation
- of the beam stable area in tune
- diagram.
- Machine is stable when tunes are
- inside of polygon. Beam is lost
- when tunes approach 5.5
- (2nd order resonance) and 5.33
- (3rd order resonance).
- CERN Booster experience tune excursion of
0.4 is possible for a short time with careful
compensation resonance driving terms. CERN PS
experience tune excursion of 0.2 is possible
with similar precautions.
36ELENA Lattice considerations
- Beam focusing is achieved by proper choice of
edge angles of the dipoles. Economical solution
for cost and space saving neither gradient
magnets, nor quadrupoles needed! - Large area in tune diagram should be available
for tune excursion caused by space charge.
Conservative estimate for coherent tune shift ?Q
0.10 was accepted which is based on CERN Booster,
PS and AD experience. - Tunes Qx1.45, Qy1.43 (with similar fractional
parts as in the AD) fit requirements. - Choice of tunes together with required straight
section length defines machine circumference
about 22m.
37ELENA Beam lifetime considerations
- Intrabeam scattering (IBS) is important at very
low energies in a short bunch with small
emittances. With reasonable choice of beam
parameters (1.5 107 particles, emittances 5p mm
mrad and ?p/p10-3) emittance rising times for
coasting beams are more than 1 minute. For
bunched beam 1.3m long they are in the order of 1
second. - Residual gas scattering produces beam blow up
0.5p mm mrad/s at 100 keV and pressure 3 10-12
Torr. - Electron cooling at 100 keV will be strong enough
to successfully counteract intrabeam and residual
gas scattering. - For fast extraction, the beam blow up is limited
by the time of beam bunching and bunch rotation
(if needed), which takes a few hundred msec.