Title: Economic Adequacy Target
1EconomicAdequacyTarget
- Resource Adequacy ForumSteering
CommitteeSeptember 27, 2007
2Outline
- Proposed economic risk measure
- Options for determining the appropriate level of
economic risk for the region - Steering Committee decision
3Proposed EconomicRisk Measure
- Objective choose a parameter that indicates the
regions exposure to high cost years - Process
- Simulate the power systems operation over many
different future conditions - Calculate the total cost for each future
- Plot a histogram of all costs
- Risk Measure the average cost for the top 10
percent highest cost futures (TVar90)
4Councils MethodAverage Cost and Economic Risk
for a Resource Plan
TVar90
Risk average of costsgt 90 threshold
Likelihood (Probability)
Power Cost (/kWh)-gt
5Options for Selecting an Appropriate Risk Level
- Calculate the average cost (over all futures) and
the risk for many different resource plans - Plot the cost and risk for each plan to create a
feasibility space - Viable plans lie along the efficient frontier
- The appropriate risk level depends on the choice
of resource plan along the efficient frontier
6Efficient Frontier
Minimizes Cost
Increasing Risk
Minimizes Economic Risk
Increasing Cost
7(No Transcript)
8Options Along the Efficient Frontier(Illustrative
)Note 1 The LR balances are based on firm
resources only.Note 2 The implied NRF LR
balance target is zero but it should use
available resource generation instead of expected
generation.
Efficient Frontier
Physical Target LOLP 5Firm Bal - 1,500 MWa
Physical LimitLOLP 5LR Bal -1500 MWa
Implied NRF/20 lt LOLP lt 5LR Bal 0 MWa
Council PlanLOLP 0LR Bal 1500 MWa
Current StatusLR Bal 200 MWa/1
9Determining an Economic Target
- Select the desired point along the efficient
frontier - Derive the implied LOLP from the corresponding
resource plan - Use that LOLP to set the energy and capacity
economic targets (same method that is used to set
the physical targets)
10Technical Committee Recommendations
- The Technical Committee recommends using the
TVar90 parameter for economic risk. - The committee does not have a recommendation for
a target point along the efficient frontier
11Steering Committee Options
- Use the Councils process to choose a target
point - Use the 5th plan to set the current target
- Engage in the Councils pubic process to develop
a new target for the 6th plan - Develop a separate method to choose a target
point - Use a modified NRF/White Book calculation
- Come up with a new method
12Options Pros and Cons