Commissioning Experience for the SNS Linac - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Commissioning Experience for the SNS Linac

Description:

Commissioning Experience for the SNS Linac. A. Aleksandrov, S. Assadi, I. Campisi, ... Chopping structure. 38. mA. time. Chopping. Measured effect of chopper on ... – PowerPoint PPT presentation

Number of Views:129
Avg rating:3.0/5.0
Slides: 22
Provided by: alexan61
Category:

less

Transcript and Presenter's Notes

Title: Commissioning Experience for the SNS Linac


1
Commissioning Experience for the SNS Linac
  • A. Aleksandrov, S. Assadi, I. Campisi, P. Chu, S.
    Cousineau, V. Danilov, G. Dodson, J. Galambos,
    D.Jeon, S.Henderson, N. Holtkamp, L.Kravchuk, S.
    Kim, M. Plum, M. Stockli, E. Tanke
  • ORNL, Oak Ridge, TN 37830 USA

2
Introduction the SNS Project
Parameters P beam on target 1.44MW I beam
aver. 1.44mA Beam energy 1 GeV Duty
factor 6 Rep. rate 60Hz Pulse width 1ms
3
SNS Linac Layout
402.5 MHz
805 MHz
HEBT
To Ring and TGT
MEBT
DTL
CCL
SRF, ß0.61, 0.81
RFQ
Injector
1000 MeV
86.8 MeV
186 MeV
2.5 MeV
Normal conducting linac
157 MeV
186 MeV
4
Commissioning runs
Run 1 - Front End - beam stop for design beam
power - 800 hours of operation (24/7) Run 2 -
Front End DTL tank 1 - beam stop and radiation
shield for design beam power - 1136 hours of
operation (24/7) Run 3 - Front End DTL tank
1,2,3 - Beam stop and radiation shield for
reduced beam power (50us, 1Hz) - 288 hours of
operation (24/7) Run 4 - Front End, DTL , CCL
modules 1,2,3 - Beam stop and radiation shield
for reduced beam power (50us, 1Hz) - in
progress
5
H- Ion source and LEBT
Radio frequency, multi-cusp ion
source. Electrostatic low energy beam transport
line Electrostatic pre-chopper in the LEBT
Current mA
Ion source availability Run 1 85.6 Run 2
92.4 Run 3 97.8
Life time test at hot spare test 1.2ms, 60Hz (7
duty factor)
6
402.5 MHz four-vane RFQ
RFQ transmission vs. RF power Simulations (blue)
and measurements (red)
Output energy measured by Time Of Flight in MEBT
2.45MeV (2 below design)
During run2 experienced resonant frequency shift
of 500kHz. Returned to operation after retuning
the cavity.
7
2.5MeV MEBT
Schematic MEBT Layout
RMS beam envelope in MEBT. Simulation (solid) and
wire scanner measurements (dots).
Beam current after RFQ (red), MEBT (blue)
8
Measured emittance after MEBT
Design value .3 ? mm mrad (RMS normalized)
Dependance of RMS emittance upon peak beam current
Beam emittance after MEBT. Vertical (top) and
horizontal (bottom)
9
Chopping
Measured effect of chopper on the beam (LEBT top,
MEBT bottom )
10
402.5 MHz DTL with permanent magnet focusing
RF tuning C.Deibele, THP65
11
Setting DTL phase and amplitude
DTL phase scan. Measured dependence of beam
phase at tank exit vs. tank RF phase compared
with simulations (solid lines) for different RF
amplitudes (different colors).
DTL acceptance scan. Transmission through energy
degrade vs. tank phase
12
Measured emittance after DTL tank 1
Vertical normalized RMS emittance 0.3 ?
mmmrad
Horizontal normalized RMS emittance 0.4 ?
mmmrad Absolute calibration of horizontal
scanner is under investigation due to discrepancy
with wire scanner measurements
13
805MHz Coupled-Cavity Linac
14
Delta-T procedure for CCL tuning
15
Beam trajectory after correction
Beam trajectory from RFQ exit to CCL beam dump.
Vertical scale - 1mm
16
FE-MEBT-DTL-CCL beam transmission
17
Longitudinal bunch profile in CCL
18
Transverse beam profile and losses in CCL
Beam profile measured by wire scanner in
CCL4 Beam loss pattern in DTL-CCL
19
Diagnostics performance
  • Beam position and phase monitors
  • Position resolution lt.2um
  • Phase resolution lt.5 deg
  • Beam current monitors
  • 1-2 accuracy for short pulses
  • Wire scanners
  • 1000 dynamic range
  • Require individual bias adjustment depending on
    energy, beam current
  • Loss monitors
  • Commissioned but did not use
  • Other devices tested
  • Laser based profile monitor for superconducting
    linac
  • Laser based beam in gap measuring system
  • Fast Faraday cup

20
Commissioning results vs. goals
21
Summary
  • Successfully commissioned Front End, Drift Tube
    Linac, Coupled-Cavity Linac modules 1-3
  • Demonstrated high power operation of Front End
    and Drift tube Linac tank 1
  • Design requirements for peak current, energy are
    met for 50us pulse at 1Hz for warm linac
  • Developed tuning procedures, commissioned all
    diagnostics systems
  • Will commission last CCL module 4 together with
    Super Conducting Linac in summer 2005
Write a Comment
User Comments (0)
About PowerShow.com