Title: Integrated Asset Delivery Framework


1
Integrated Asset Delivery Framework
2
Integrated Asset Delivery Framework
Even if a Integrated Asset Delivery Framework
Building doesnt look unusual, it can save in the
order of 50 in energy and greenhouse gas
emissions, compared to current good practice.
Much of this is due to a new design process, one
based on the well-tested principles of skills and
teamwork.
3
What is Integrated Asset Delivery Framework?
  • Integrated Asset Delivery Framework is a program
    for the delivery of high-performance buildings.
    The goal is to help designers to achieve a very
    high level of performance, including
  • A 50 improvement in energy performance relative
    to current good practice,
  • Reductions in resource consumption, such as land,
    water and materials,
  • Significant reductions in atmospheric emissions,
    solid and liquid wastes,
  • Superior indoor air quality, thermal comfort,
    illumination and acoustic environment,
  • Improved functionality, adaptability and
    maintainability.

4
The conventional design process
  • To assess the Integrated Asset Delivery
    Framework, we first need to examine the
    conventional design process. It is essentially
    linear in nature

5
The conventional design process
  • It begins with pre-design functions, such as the
    preparation of a Design Brief and Functional
    Program, to be carried out by the client. This is
    followed by the first two phases within the
    responsibility of the design team, Schematic
    Design and Design Development. Percentage figures
    indicate recommended percentage of total fees
    allocated to the task.

Design Development 15
Schematic design 10
6
The conventional design process
  • These are in turn followed by Detail
    Documentation (drawings and specs), Tender
    Process, and Site Inspections during the
    Construction Stage. These three phases account
    for 75 of the total fees.

7
The conventional design process
  • In the conventional process, attempts are often
    made to introduce bright ideas during the
    preparation of construction documents (or even
    later!), since they were not considered earlier.
    This is costly and disruptive to the process.

8
The conventional design process
  • To summarise the problems
  • The main design parameters (massing, orientation,
    fenestration pattern) are often determined by the
    client and architect in the Schematic Design
    phase.
  • Input on orientation for passive solar,
    daylighting potential, measures to control solar
    overheating etc. is often only sought in the
    Design Development phase.
  • By this time, the client and architect may be
    locked into a sub-optimal solution

9
The conventional design process
  • problems
  • Engineers and specialists are locked out of the
    initial design decisions, and architects are
    poorly placed to acquire detailed knowledge about
    new technologies and processes such as
    performance simulation.
  • Advanced systems and features are often added
    on to the basic design in later phases, but this
    does not lead to very high levels of performance,
    disrupts the process, and is very costly.
  • Or design in haste, repent at leisure.

10
The two core processes compared
Integrated Asset Delivery Framework
Conventional Process
11
Integrated Asset Delivery Framework
  • We define the integrated development process as
  • Including a wide range of technical skills in the
    design team,
  • Adding a design facilitator and an energy
    simulation specialist to the team,
  • Commencing with teamwork from the very start of
    the Concept Design Stage,
  • Adding new functions to the process, and
  • Defining performance goals at the outset and
    referring to them throughout.

12
Integrated Asset Delivery Framework
  • What are the features of the Integrated Asset
    Delivery Framework?
  • It brings engineering and specialist skills to
    the table at a very early stage.
  • A broad range of performance issues are
    considered.
  • It keeps options open on the basic features of
    the design until the potential performance of
    alternatives can be assessed.
  • Conversely, the client is not hustled into a
    premature commitment to a primarily visual
    solution.

13
Integrated Asset Delivery Framework
  • What are the features...?
  • The architect plays the role of a team leader and
    is not the predominant decision-maker during
    Concept Design and Design Development.
  • Friction can be avoided by informing consultants
    about the process before they are retained.
  • The architect acquires valuable new technical
    skills, while the client and engineers gain
    insight into the complexities of architectural
    design.
  • Engineers have a chance to show how much they can
    contribute to the early design phases.

14
Integrated Asset Delivery Framework
  • What are the features...?
  • Integrated Asset Delivery Framework provides
    access to specialists as needed for short-term
    advice, such as daylighting, thermal storage,
    glazing characteristics, material selection, etc.
  • Note that, as in conventional projects, most of
    the hard work is up to the design team. The
    program is not intended for neophyte designers,
    and our process just provides support and helps
    the team to make the right decisions.

15
Integrated Asset Delivery Framework
The first step is to work with the client to
ensure that the right team is in place before
design begins
Integrated design team
Committed client
Committed and skilled design team
Specialists
Design Facilitator
16
Integrated Asset Delivery Framework
Core design team Team specialists
The relationship between the actors looks
something like this
Conventional roles
Committed client
Cost consultant
Management and technical advice
Contractor
Energy specialist
Environmental specialist
Design Facilitator
Facility manager
Management and technical support
O M staff, tenants...
17
Integrated Asset Delivery Framework
  • It is important to note that
  • The architect and engineers still retain their
    professional responsibilities and liabilities,
    and therefore are the final arbiters of design
    decisions.
  • The Design Facilitator is to be an adviser, and
    is to support the design team in their work
    without disrupting the process. This requires an
    ability to make rapid decisions and also to
    provide helpful information and support quickly.
  • The design professionals should be paid on a
    lump-sum basis or equivalent that will avoid
    penalising them financially for reducing the size
    and cost of mechanical systems.

18
Integrated Asset Delivery Framework
  • Before design work begins, some preliminary
    questions should be asked
  • Could a renovation serve the purpose instead of a
    new building?
  • If new construction is needed, has the best site
    been chosen, e.g. avoiding the use of
    agricultural land?
  • Has the design brief and functional program been
    developed with due care?

19
Integrated Asset Delivery Framework
Preliminary energy analysis
Perform a global performance assessment
Define performance goals
Concept Design Report
Design iterations
Integrated design team
Develop concept design(s)
Concept Design Phase
Examine functional requirements
Examine site development issues
20
Designiterations
Develop preliminary building envelope design
Select building structural system
Develop preliminary lighting and power system
design
Develop preliminary design for ventilation,
heating and cooling systems
Develop preliminary fenestration design
Design Development Phase
21
New technologies and procedures are implemented
22
Design iteration is sometimes necessary but not
recommended
Schematic Design Report
Pre-Construction Report
Final Life Cycle Cost Analysis
Complete contract documentation, including
working drawings and specifications
Develop Quality Management strategies for
construction and commissioning
Develop Quality Management strategies for
operation
Contract Documentation and Beyond
23
Construction, Commissioning and Operation
Commissioning Report
Provide as-built documentation and operating
manuals
Operate
Site Inspections (Construction)
Carry out commissioning
Procure materials and equipment
Monitor operational performance
Train operating staff
24
Integrated Asset Delivery Framework - in full
Contract Documentation and Beyond
Construction, Commissioning and Operation
Concept Design
Design Development
25
New technologies and procedures are implemented
A way to summarise the technical aspects of the
process is to think of it this way
  • First make use of the passive solar potential by
    using orientation and configuration to maximize
    solar potential during the heating season and
    daylighting all year around
  • Second, reduce heating and cooling loads through
    the use of a high-performance building envelope,
    carefully located glazing and by reducing
    electrical consumption
  • Then meet the reduced load requirements through
    efficient plant systems and distribution
    systems...
  • while always remembering the need for a
    high-quality indoor environment, maintainability,
    economy and measures to reduce environmental
    loads.

26
New technologies and procedures are implemented
Specific design features depend on the specific
building and its location nevertheless consider
the following
  • Provision of adequate space for bicycles and
    solid waste recycling,
  • High-volume flyash cement and a lean structure,
  • Trees as part of the solution to reduce cooling
    loads,
  • Spectrally-selective glazing with exterior
    sunshades and light shelves to maximize
    daylighting potential,
  • High-efficiency direct/indirect ambient lighting
    plus task lighting,
  • Daylight sensors for perimeter lighting zones,

27
New technologies and procedures are implemented
Specific design features to consider...
  • Use of natural ventilation where possible,
  • Operable windows or a backup ventilation system,
  • 100 displacement fresh air system with heat
    recovery,
  • Sizing of drives, boiler chillers to maximize
    operation at full loads.
  • Minimal size of lighting and HVAC zones,
  • Control systems that are user-friendly and are
    consistent with the complexity of building
    systems,
  • Materials chosen for low emissivity and embodied
    energy, use of recycled materials, and an
    assembly design that focuses on future
    demountability.

28
Integrated Asset Delivery Framework
What are the results?
  • More time is spent in Concept and Design
    Development tasks, but time is saved and problems
    are minimized during the contract documentation
    stage.
  • The process results in better buildings ones
    with energy and emission performance roughly half
    of current good practice, healthier and more
    comfortable indoor environments, and with more
    ability to adapt to changing future needs.
  • Operating costs are considerably reduced because
    of reduced operating energy consumption.
  • Maintenance and replacement costs are reduced
    because of smaller mechanical plants and more
    efficient equipment.

29
Integrated Asset Delivery Framework results
Selected data on some high performance buildings
30
Integrated Asset Delivery Framework
Available support tools
  • The Environmental Performance Guide for Buildings
    internet site at asset.gov.com.au/environmentguide
    .
  • Environmental Performance Guide for Buildings
    assessment for spreadsheet used for quick global
    performance assessments during concept and design
    development.
  • Energy analysis software, for preliminary energy
    performance analysis.
  • Energy simulation software.
  • A technical and economic screening of
    possibilities for renewable energy.

31
Integrated Asset Delivery Framework
Finally...
  • We can help you and your designers to design a
    better building, one that is more functional and
    more environmentally responsible.
  • and you can help us to improve the program.

For further information, contact Chris Oh
chris.oh_at_dpws.nsw.gov.au