Title: Integrated Financial Management Information Systems (IFMIS)
1Integrated Financial Management Information
Systems (IFMIS)
Presentation of Zambian IFMIS
- Chitundu N Mwango
- Accountant General
- Ministry of Finance and National Planning
- Lusaka, Zambia
- Telephone 260 (1) 251471
- Email cnmwango_at_zamtel.zm
2Background
- The Government has been implementing the Public
Service Reform Programme (PSRP) from 1993. - The aim of the PSRP is to improve the quality,
efficiency and effectiveness of Public Service
delivery. - In 1999 a concern arose as to whether the
measures taken under the PSRP framework had
resulted in improved performance. - It was acknowledged then that these measures had
not led to tangible improvements in the delivery
of public services. - Therefore, Public Service Capacity Building
Project (PSCAP) was designed to support the
implementation of the Public Service Reform
Programme. - PSCAP is financed by the World Bank and managed
at Cabinet Office - One of the PSCAP component was the Financial
Management, Accountability and Transparency - IFMIS is a project within the Financial
Management, Accountability and Transparency
component
3Background
- In 2000 a local consulting firm was engaged for 6
months and produced the IFMIS roadmap - In 2001 a local short term consultant was
recruited to initiate the implementation of IFMIS - Assisted in recruiting Project Manager, Manager
IT and Manager Accounting. - Other Managers (Budget, Audit, Debt, Training)
identified by roadmap were not recruited due to
lack of funds - Initiated the process of engaging a consulting
firm to analyse and design IFMIS - Government seconded one principal accountant and
three principal analysts to the Project team but
did not stay because of lack of incentives
4IFMIS Design
- In 2002 Government issued a tender for a long
term consultant to analyze and design IFMIS - However the tender for the long term consultant
was annulled (cancelled) because of disagreement
between the Government and Bank on the
procurement process - An IFMIS advisor was recruited through Bank but
was based in Washington and Government terminated
the contract - Government decided to use the local IFMIS Project
team to analyze and design IFMIS - This saved Government about 1million
- The Project team undertook a comprehensive
assessment of user requirements and conducted
IFMIS sensitization workshops
5IFMIS Design
- The local team designed the IFMIS chart of
accounts which took into consideration the GFS
and IPSAS - Produced the IFMIS assessment report,
Requirements Specification, and Chart of Accounts
as part of IFMIS design - Undertook study tours of IFMIS implementation in
Tanzania and Uganda - Initiated a tender for installation and
implementation of IFMIS using the World Bank
procurement guidelines
6Implementation Plan
- Zambian IFMIS will be implemented in three phases
- Phase 1 (Pilot Implementation 8 months)
- A total of 3 Ministries and 2 Provinces will be
hooked to the Data Centre (Accountant General). - Interface with Bank of Zambia and Zambia Revenue
Authority for the Treasury Operations. - The pilot sites are
- Ministry of Finance and National Planning, Lusaka
- Ministry of Education, Lusaka.
- Ministry of Works and Supply, Lusaka
- North-Western Province, Solwezi
- Eastern Province, Chipata
- Phase 2 (Rollout Implementation 20 months)
- 41 Ministries, Provinces and Spending Agencies
will be hooked to Data Centre - Phase 3 (Interface Implementation 6 months)
- Local authorities, parastatals will interface
with Data Centre
7(No Transcript)
8Status on IFMIS tender
- Prepared two bidding documents (pre-qualification
and IFMIS main bid) - Pre-qualification bid documents were issued in
Jul 2003 and (19) applicants were received. - Initially 4 firms were pre-qualified but later
increased to 7 firms and main bid documents were
issued to 7 firm in Dec 2004 - Only 3 bids were received and after evaluation
undertook post-qualification assessment of the
lowest evaluated bidder in Jun 2004 - Pre-contract negotiation held in Aug/Sep 2004 and
requested for no objection from the World Bank to
sign contract
9Progress/Achievements Systems and Infrastructure
- Developed the Activity Based Budgeting (ABB)
software and MTEF in 2003 and implemented in 2004 - Parts of the IFMIS chart of accounts adopted in
the ABB and FMS - Upgraded the FMS and commitment control system
using the local team (the system was appreciated
by IMF and IDA) - Implemented the Payroll Management and
Establishment Control (PMEC) system using SAP to
efficiently manage and control public service
payroll - Currently piloting CAATS in two ministries
10Progress/Achievements Systems and Infrastructure
- Developed and implemented a Static Arrears
database in June 2003 (saved 90,000) - Developed and implemented an Asset register for
moveable assets in line ministries which will be
an input to the IFMIS assets module - Currently upgrading the LAN at MOFNP compatible
to IFMIS - Currently completing the preparation of the five
(5) IFMIS pilot sites
11Progress/Achievements Training Change mgt
- 400 Accountants trained in FMS and CCS
- 50 Procurement Officers trained in Commitment
Control System - 12 Persons trained in Prince2 project management
- 120 internal auditors and Auditor General staff
trained in Computer Aided Audit Techniques
(CAATs) - Sensitized members of Parliament (Public Accounts
Committee and Estimates Committee), Permanent
Secretaries, Directors in Ministries, accountants
and auditors in IFMIS - Salary officers in all line ministries trained in
PMEC systems - Developed an in-service syllabus (including
IFMIS) in Government accounts for accountants,
auditors and non-accounting staff
12Progress/Achievements Other initiatives
- Revised the Finance Act (currently being debated
by parliament) - Constituted the PEMFAR steering committee to
provide policy guidance to the IFMIS project
(with representation from Zambia National Tender
Board, Auditor General, Bank of Zambia, Revenue
Authority, Clerk of National Assembly) - Formed six (6) IFMIS implementation working
groups to facilitate stakeholder involvement in
IFMIS implementation and ensure sustainability
after the project ends - Internet Connection to commercial banks to
download the bank statements
13Benefits of interim measures
- Improved cash monitoring through internet
connection to the banks - Bank reconciliation on time due interface with
banks - Timely production of financial reports (the 2003
financial report is being printed) - Production of monthly expenditure returns by
Ministries, Provinces and Spending Agencies
within 15 days - Eliminate ghost workers and other irregularities
by linking (matching) establishment to the payroll
14Way Forward - PEMFA Programme
- In 2003 Government and the World Bank completed
the Public Expenditure Management and Financial
Accountability Review (PEMFAR) which is a
diagnostics tool - Comprehensive Integrated Reform
- Focus on inter-linkages ensures appropriate
sequencing and timing - Entire public expenditure management procedure
chains reformed - Table on next slide summarises the 12 components
identified within the Government Strategy
Document.
15Way Forward - PEMFA Programme
16Way Forward - PEMFA Programme
17Challenges/Lesson Learnt Procurement issues
- The IFMIS procurement procedures are too long,
for example it has taken about 20 months to
procure the IFMIS system - Delays in obtaining no objections and approvals
from stakeholders - Pressure from strong stakeholders causes delays
and selection of suppliers who may not deliver,
eg increasing the pre-qualified firms - Conflict between procurement procedures and
standard Information Systems development
procedures - For example, procurement procedure did not allow
all pre-qualified firms to demonstrate their
solution to Government before making final
selection
18Challenges/Lesson Learnt HIPC Benchmark
- IFMIS as a HIPC Benchmark helped to sensitizes
stakeholders on importance of IFMIS and secured
political will - Puts pressure on Governments to rush the
implementation of IFMIS
19Challenges/Lesson Learnt Financing issues
- Shortage of equipment and lack of connectivity
(LAN) delayed the pace of implementing the
retooled FMS and CCS - IFMIS costs are huge (US24million) and difficult
to find partners who are willing to finance - Financing arrangement of IFMIS project through
third party delayed implementation - Justification of IFMIS in view of competing
social needs such as education, health and
development projects - Continued support by cooperating partners is not
easy to maintain
20Challenges/Lesson Learnt Human issues
- User resistance and other important stakeholders
not participating - Change management issues
- Power and politics as to who is the IFMIS
Champion - Retention of core team to implement the IFMIS and
the issue of incentives for civil servants
21Conclusion
- Although the IFMIS main contract has not yet been
signed with the Supplier due to lengthy
procurement procedures, Government has made a
number of significant achievement in public
financial management and preparing for full
implementation of IFMIS - Experience acquired from development and
implementation of ABB, FMS and CCS as well as
study tours will help Government in the
implementation of IFMIS
22Conclusion
23Development of FMS
24Development of FMS Major Reports