Title: DOI Enterprise Resource Management Program
1DOI Enterprise Resource Management Program
- CPIC Advance
- Last Updated January 2005
- Prepared by Samantha Goldstein
- Enterprise Resource Manager
United States Department of the Interior
2ERM Program Highlights
- ERM Program was officially established in
February 2003 to support the Administrations
E-Government Goal emphasizing improved delivery
of IT products and services at reduced costs. - Key ERM Program Objectives are to
- - Coordinate and consolidate the acquisition and
management of IT hardware software products
across DOI. - - Ensure that acquired IT products and services
comply with standards and specifications
prescribed by enterprise architecture (updated
TRM versions). - - Provide marketing and outreach to DOI users on
enterprise-wide contracts to ensure that they can
quickly and easily obtain the products that they
need through on-line ordering systems. - Key information related to the contracts
covered under the ERM Program, is posted on DOIs
password-protected storefront -
http//www.doi.gov/ocio/erm/ - Prior to establishment of ERM Program, DOI
bureaus contracted out separately for IT products
and services without any type of acquisition
coordination. This lead to wasted resources, and
acquiring products that did not always support
DOIs technical infrastructure.
3Key Phases of Acquisition Process Used to
Establish DOI-wide Agreements
Phase 1 Establish Technical Working Group
Phase 2 Define Requirements
Phase 4 Establish Procurement
Identify Requirements
DOI Stakeholder
Draft SOW
Conduct Price Evaluation
Issue RFQ
Obtain Vendor Responses
Request Clarification
Establish Range Considerations
Conduct Negotiations
Issue RFI
Appoint Program Manager
DOR ARB
Conduct Technical Evaluation
Phase 3 Develop Solicitation
DOI Architect
Appoint Technical Team
Obtain Best and Final Offer
Evaluate RFI
Issue Award
Complete Source Selection
Finalize Award Decision
Administer Contract
DOI IPT
Appoint CO
Finalize Acquisition Strategy
DOI ERM
Document Standardization Decision
Appoint Price Evaluation Team
Draft Solicitation
4Hardware BPA Highlights
- Vendors Currently warded BPAs
- PCs Servers - Dell Corp.
- Ultralight Laptops - NCS Technologies,
Inc. - Traveler / Telecommuter Laptops - IBM Corp.
- Tape Library - loDynamix
- Duration of Agreement
- Established in June August 2003, with a 1
year base period and 1 Option Year for renewal. - Contract Re-compete Deadline
- Contracts are currently up for re-competition
/ renegotiation. - Emphasis is placed on reviewing and revamping
existing requirements for select hardware
equipment that will be used as basis for new
solicitations. - New awards for select equipment need to be
made between June September 2005. -
5Hardware BPA Highlights
- Key Advantages of Using Hardware BPA
- Establishes Product Standards for Select
Equipment. All hardware equipment products on
BPA have standard configurations with select
options that conform to the requirements
developed and agreed to by DOIs Platform Domain
Architecture Team (DAT), and the acquisition
community. This ensures that appropriate
equipment is in place to support key DOI
infrastructure initiatives. Requirements will be
continuously reviewed and updated. - Yields Substantial Cost Savings. DOIs combined
savings for FY 2003 and FY 2004 total nearly 11
million, or 19 below GSA-schedule pricing. - Provides for Flexibility in Purchasing. BPA
contract type allows DOI customers to purchase
desktops, laptops, and servers directly off the
contract at anytime throughout the duration of
the contract, without having to commit to
specific quantities up-front. - Promotes Acquisition of Up-to-Date Products.
Each BPA goes through a technology refresh review
by the DAT on a quarterly basis to ensure that
DOI is taking advantage of the latest
technological advances. - Promotes E-Commerce Goals. Established on-line
orderings systems for each BPA/vendor allow DOI
customers to place orders and make purchases on
the spot.
6Hardware BPA HighlightsDOI GSA Cost
Comparisons for FY 2003 2004(IDIQ
Basis)(Dollars in Millions)
7Software ELA Highlights
- Following Software ELAs are Established
- - Oracle Enterprise Agreement - Environmental
Systems Research Institute (ESRI) - - Microsoft Enterprise Agreement - MAXIMO
Facility Management Software - - Symantec Enterprise Agreement - FBMS-support
Software Licenses - ELA Structure Consists of Two Types
- Minimum Seat Enrollment - Commitment is
required up-front for a specified number of seats
for DOI to obtain maximum cost-savings. This
offering usually consists of license bundles and
maintenance that best fits DOI needs. The
estimated savings to DOI from entering into ELAs,
total over 58 million, or 51 below
GSA-schedule pricing. - Additional BPA Purchase Option ELAs also
include a true-up option where DOI customers
can purchase additional quantities of select
products offered by Oracle, Microsoft, Symantec
throughout the duration of the contract. In FY
2004, DOI saved another 1 million, or 23 below
GSA-schedule pricing for these optional products.
8Software ELA Highlights
- Key Advantages of Establishing Software ELAs
- Provides a Standard Microsoft Operating System
Across DOI Organization. DOI standardized on
Microsoft desktop and server products in
September 2002, and is deploying the Active
Directory throughout the Department to ensure
that critical systems are consistently secured
and managed across the enterprise. - Promotes Using Standard Software to Support
Major IT Projects / Systems. Established ELAs
enable project managers to have easy access to
the appropriate IT tools needed to implement
major IT initiatives that support DOIs key
missions and programs. - Enables DOI to Leverage Higher Volume
Purchasing Power for Widely Used IT Products. By
pooling together common requirements, DOI is
able to obtain software at significantly lower
cost than the individual bureaus would be able
to obtain on their own.
9Software ELA Highlights DOI GSA Cost
Comparisons for Basic ELA Offerings(Minimum Seat
Enrollment Required)(Dollars in Millions)
10Summary of ERM Program Accomplishments to Date
- Established ERM Program Umbrella for Hardware
and Software Contracts. Prepared marketing
packages that outlined specific products
offerings available under each contract to DOI
users, and the savings generated from pursuing
consolidated acquisitions in comparison with
GSA-schedule pricing. - Developed Process to Capture DOI Cost-Savings /
Avoidance. Given current data constraints, the
comparison is based on comparing DOI costs for
select products covered under each contract, with
GSA-schedule costs for similar products. The
underlying assumption is that without the
consolidated contract, DOI customers would have
still purchased the same product quantities off
the GSA-schedule. - Expanded Marketing Outreach for Existing
Contracts. Revamped and updated the storefront
link http//www.doi.gov/ocio/erm/ to provide
DOI customers with most up-to-date information so
that they can easily access the products that
they need off established contract vehicles. - Strengthened Collaboration Role w/ Domain
Architecture Teams, ESRI rep, and Other Technical
Experts. Participated in ongoing phone
conferences and monthly meetings held by Platform
DAT to address issues surrounding the existing
hardware BPA, and plans to re-compete for select
equipment, based on changing DOI-user
requirements. - Defined Acquisition Process Used for
Establishing Future DOI-wide Contracts.
Consistent with product standards and
specifications outlined in the updated TRM
version, the majority of future DOI-wide
contracts will be established according to four
key phases prescribed by the Federal Acquisition
Process.
11ERM Program Challenges / Opportunities
- Inconsistent Tracking of Hardware Software
Licensing Costs that Support Major Infrastructure
Initiatives - - In concert with OMBs budget guidance for FY
2006, DOIs Office of Budget (POB) and the OCIO
IT-PMD are emphasizing the need for more
consistent tracking of investments reflected in
the IT Infrastructure Business Case. This
includes the hardware and software licensing
costs that support the major infrastructure
initiatives. - - Currently, the bureaus are all tracking
hardware and software licensing costs
differently, making it difficult for DOI to
accurately capture 41 million in hardware
costs, and 56 million in software licensing
costs in the Infrastructure Business Case, and in
Part II of Exhibit 53. - - Given the magnitude of these licensing costs,
there is an opportunity to capture them more
accurately and consistently in the FY 2007
budget cycle by allocating them according to the
defined OMB Budget Cluster and Category.
12Categorization of DOI-wide Agreements by Budget
Cluster and Category
13Next Steps
- Achieving More Consist Tracking of Licensing
Costs in FY 2007 Infrastructure Business Case - - Formal guidance will be issued by the OCIO IT
PMD for the FY 2007 budget cycle to provide
direction to the bureaus on how to allocate their
respective hardware and software licensing costs
by the appropriate Budget Category and Cluster,
as provided in the table. - - In the meantime each bureau should be getting
ready for updating the business case by striving
to accurately capture their respective licensing
costs for the mentioned hardware and software
agreements. - - The OCIO will also be developing a breakout of
these costs by bureau that the bureaus can
in-turn use for reference as they proceed to
reconcile their initial figures against those
provided by the Department.