Title: Los Alamos National Laboratory


1
Los Alamos National Laboratory
  • Maintenance Work Planner Training and
    Qualification Program

2
Program Initiation
  • Perceived performance problems
  • DOE implementation plan for NNSA Recommendation
    2004-1
  • DOE O 5480.20A
  • Commitment to DOE field office to improve
    maintenance programs

3
Planner TQ Program Purpose
  • Provide incumbent Work Planners a
    performance-based TQ program
  • Provide a graded approach to Work Planner
    qualification based on complexity of planning
    assignments
  • Provide a performance-based Work Planning TQ
    program for newly assigned work planning
    personnel
  • Provide a continuing training (refresher) program
    for qualified Maintenance Work Planners
  • Implement consistency across the Lab in work
    planning
  • Allow the movement of qualified Work Planners
    across departments and divisions maintaining a
    consistency in planning methodologies

4
Job Analysis
  • DOE Handbook for Alternative Systematic
    Approaches to Training (DOE-HDBK-1074-95)
  • Identified Maintenance Work Planners as technical
    staff
  • Interviews and table-top analysis

5
Curriculum Identification and Development
  • 28 classes / 86 classroom hours
  • No read and sign
  • Credit for previously completed training

6
Training Directly Linked to ISM
  • While most training can be linked to ISM, some
    are more pointed than others

7
Qualification Card
  • Training conducted by LANL SMEs
  • OJT used extensively
  • Evaluation by Lead Planners and OJT
    Instructors
  • Metrics being established
  • MWP performance evaluation
  • Work package generation time
  • Cost estimate accuracy
  • Correct permitting identified

8
On-the-Job Evaluation
  • Evaluated work package development
  • Evaluated on level of hazards involved
  • Must pass to qualify
  • Considering linking PassPort authorities to
    qualification status

9
Continuing Training
  • Attendance required to maintain qualification
  • Significant facility system and component
    changes
  • Applicable procedure/manual/program changes
  • Applicable industry operating experience
  • Other training as needed to correct identified
    performance
  • problems

10
Conclusion
  • Excellent attendance to date
  • Excellent management support
  • Excellent support from SMEs and their
    organizations
  • Program feedback is being used revise materials
    and curriculum
  • Preparing for a New Planner training class
  • Eventually will transition the program to the
    Central
  • Training Organization

11
Contacts
  • Donald Shoemaker, MSS-DO Deputy Division Leader
  • (505) 667-4917
  • donalds_at_lanl.gov
  • Todd Siverling, MSS-MSE Group Leader
  • (505) 667-3360
  • todds_at_lanl.gov
  • Mike Penovich, Program Developer
  • (505) 665-0953
  • penovich_at_lanl.gov