Title: Hacienda La Puente Unified School District


1
Hacienda La Puente Unified School District
  • Measure A Program Report
  • Program Compression Analysis

2
Recap of Original Program Design and
Construction Plan
  • Construction Budget Based on Measure A Bond
    Program of 100 million
  • Design Based on Measure A Bond Program plus
    anticipated District State Modernization
    Eligibility Grants of approximately 56 Million
    for a total Program of 156 Million
  • Four years Construction Program to include
    Board priorities
  • Construction to be sequenced in 6 Groups each
    containing multiple school sites

3
September 27, 2001 Board Directives
  • Determine Design Development Opportunities
  • Evaluate Bond Draw Flexibility
  • Develop Project Compression Options and Impact
    Analysis

4
DSA Requirements
  • October 3, 2001 met with DSA to present District
    Priorities - Power and HVAC acceleration
  • DSA design requirements
  • 20 minimum ADA compliance of Construction Budget
  • 20 minimum Fire Life Safety compliance of
    Construction Budget
  • Non compliance may cause Red Tag
  • All approved design elements and requirements
    must be constructed within a certain time period
  • DSA design review timeline is estimated at 5 to 6
    months

5
Design OptionsWhat Did We Consider?
  • Classrooms Only
  • Prioritize by level of schools
  • Power and HVAC first, then ADA, Fire Life Safety,
    Restroom Renovation, etc.
  • BARD HVAC Units where possible instead of Roof
    Top or Split System Units
  • Interim Housing Campus vs. Interim Housing by
    school site
  • Postponing or finding alternative sites for
    Summer School Programs

6
Compression Challenges, summary
  • Contractor Acceleration Costs
  • Equipment Procurement Costs
  • Architect and Program Management Administration
    Costs
  • Interim Housing Costs
  • Other Regulatory Agency Requirements
  • Impact to Instructional Program
  • Funding Sources

7
Program Compression Analysis - Construction Phase
8
Program Compression Analysis Cost Impact
CICost Impact, Increase
9
2-Year Compressed Plan
2001
2002
2003
2004
2005
2006
Bond funds Exhausted
Design DSA
Group 1 HVAC
Group 1 Mods
  • ASSUMPTIONS
  • Focus on commencement of construction
  • Duration driven by cost estimates and interim
    housing requirements
  • Three (3) to Four (4) month per building
    construction cycle
  • Funding availability
  • Adequate as-built, supporting documents and
    surveys
  • Meeting Minimum DSA requirements within funding
    limits

Group 2 HVAC
Group 2 Mods
Group 3 HVAC
Group 3 Mods
Group 4 HVAC
Group 4 Mods
Group 5 HVAC
Group 5 Mods
Group 6 HVAC
Group 6 Mods
No High Schools Included
10
3-Year Compressed Plan
2001
2002
2003
2004
2005
2006
Bond funds Exhausted
Design DSA
Group 1 HVAC
Group 1 Mods
  • ASSUMPTIONS
  • Focus on commencement of construction
  • Duration driven by cost estimates and interim
    housing requirements
  • Three (3) to Four (4) month per building
    construction cycle
  • Funding availability
  • Adequate as-built, supporting documents and
    surveys
  • Meeting Minimum DSA requirements within funding
    limits

Group 2 HVAC
Group 2 Mods
Group 3 HVAC
Group 3 Mods
Group 4 HVAC
Group 4 Mods
Group 5 HVAC
Group 5 Mods
Group 6 HVAC
Group 6 Mods
11
Original Plan
2001
2002
2003
2004
2005
2006
Design DSA
Group 1
  • ASSUMPTIONS
  • Focus on commencement of construction
  • Duration driven by cost estimates and interim
    housing requirements
  • Three (3) to Four (4) month per building
    construction cycle
  • Funding availability
  • Adequate as-built, supporting documents and
    surveys
  • Meeting Minimum DSA requirements within funding
    limits

Group 2
Group 3
Group 4
Group 5
Group 6
12
Program Budgets
13
Next Steps
  • Continue with the current course of Design to the
    156 million Program using the two design package
    plan
  • Board approval of Architect Notice of Intent

14
Communication Plan
  • Reporting Mechanisms
  • Quarterly News Letters
  • Monthly Program and Project Brief
  • District Web Page
  • Meetings
  • District
  • School Site
  • Community
  • Frequency
  • Beginning on 2nd Quarter Issue
  • Monthly, Beginning October 2001
  • Monthly, Beginning October 2001
  • As Agreed, Beginning October 2001

15
Questions Answers
16
Appendix
17
Interim Housing Campus
18
Design Options- Option A
19
Design Options Option B
20
Design Options Option C