BNL, 16 July 2004. Silicon Strip Detector status report. Report on last year ... 1 RDO board died mid-february. 2 others RDO unplugged ! for pp ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 12
Provided by: star6
Learn more at: https://www.star.bnl.gov
Category:

less

Transcript and Presenter's Notes

Title: Jerome Baudot, Strasbourg


1
Silicon Strip Detector status report
STAR Collaboration MeetingBNL, 16 July 2004
? Report on last year Completion this year
Jerome Baudot, Strasbourg
2
SSD structure
  • Strip detectors
  • double sided
  • 2? in r?, -1lt?lt1
  • 500k channels
  • Performances
  • sRF 20 mm
  • readout 5 ms(4 RDO boards)
  • air cooled
  • Command (JTAG)
  • initialize FEE
  • slow control

a module
a ladder
3
How many ladders do we have ?
run III
run IV
½ SSD 10 ladders 160 modules
1 ladder 16 modules
4
Operations in run IV
  • Monitoring
  • 1st Slow Control version
  • 1st histos set in Online
  • No alarms handling
  • Electronic logbook
  • AuAu data 6014 Mevts
  • 1 RDO board died mid-february
  • 2 others RDO unplugged ! for pp
  • FEE eratically loosing bias (know how to fix)
  • 1 air compressor failure
  • No L2 accept

5
Data analysis
  • The basics
  • pedestal as expected
  • noise
  • S/N

6
We do see particles
Landau fit
P side
same charge collectedon both sides particles
N side
7
Data analysis pedestal instability
15 January
2 April
dead RDO board
8
Production status now
  • Modules
  • gt160 done
  • Ladders
  • (10 already installed)
  • 9 done
  • ladder 0
  • 2 spares done

Detector completedthis summer
1 new sector (out of 2) of 5 ladders
9
Installation for summer 2004
  • 2-22 August
  • get new sectors of 5 ladders
  • redispatch mounted ladders -gt sect 7 lad
  • test all 4 sectors (2x32x7)
  • shielding
  • test RDO boards (1 new)
  • install new power supplies
  • change pedestal compensation (against fluctuation)
  • gt23 August
  • rolling in
  • test
  • Integration
  • L2 acept
  • alarm handling
  • no more Reset (FEE bias)

run IV
run V
old sector
new sectors
old sector
10
SSD software integration
  • Already completed
  • Daq SsdReader
  • Ssd hit reconstruction
  • StiSsd (almost done, not yet reviewed, need to be
    tuned)
  • Almost done
  • Databases (Geometry and Calibration) defined,
    currenctly filling
  • Need more work
  • Alignement starting from StSvtAlignment ? (used
    for the SSD sometime ago)

11
SSD in GSTAR
Material distribution and radiation
length