Title: Electric Transmission System Development in Alberta
1Electric Transmission System Development in
Alberta
- Neil J. Brausen, P. Eng., Director System
Planning - APEGGA Calgary Branch Luncheon
- March 17, 2004
2Electric Transmission System Development in
Alberta
- Industry Background and Structure
- AESO Core Business Functions
- Transmission Planning Process
- Transmission System Development
- Questions
3Industry Background and Structure
4Albertas Electric Industry
- single control area of 660,000 km²
- 20,000 km transmission 450 substations
- B.C. Sask. interconnections
- 8,570 MW system peak
- over 130 generating units
- 10,515 MW internal capacity net to grid
- over 200 market participants
BC
Alta
Sask
5Albertas Electric Market
TransAlta/ATCO/EP
Existing Generating Units
New Generation (IPPs)
Balancing Pool
Marketer
Market
Transmission
Transmission Facility Owners
Distribution Wire Service Provider
Retailer
Retailer
F
F
H
6Industry Model Post-Restructuring
Vertically Integrated Utility
Functional Separation
competitive forces
Generation
natural monopoly
Transmission
natural monopoly
Distribution
competitive forces
Retail
7AESO Core Business Functions
8Who Is the AESO?
- Statutory organization integration of previous
Power Pool and Transmission Administrator
functions - Not-for-profit
- Revenue generated from trading charge and
transmission tariff - Hold no assets
- Impartial - no affiliation with industry players
- Regulated by the Energy and Utilities Board
- Governed by board of directors appointed by the
Minister of Energy
9Industry Structure (June 2003)
Electric Utilities Act
Minister of Energy Appoints Board members , MSA
EUB Chair
Balancing Pool
Market Surveillance Administrator (MSA)
Alberta Electric System Operator
Alberta Energy Utilities Board (EUB) Regulates
AESOs Transmission business
Wholesale Energy Market
Load Settlement
Transmission
Real-time Alberta Electric System Operator
10Transmission Planning Process
11Transmission Planning - The Process
- Determine the inputs.
- Identify the anticipated problems.
- Develop the alternatives.
- Analyse the alternatives.
- Choose the preferred solution.
- Initiate the project(s).
12Transmission Planning - The Inputs
- Load - forecast, location, timing, peak vs.
off-peak - Generation - size, location, timing, merit order
- Existing system - capacity, equipment ratings,
operating constraints - Planning criteria - bulk system, subtransmission,
load supply stations - Externalities - siting and routing
considerations, planning horizons for other
stakeholders, other jurisdictions
13Transmission Planning - Project Initiation
- AESO determines need for system expansion or
upgrade. - AESO prepares Need Application and files with
Energy and Utilities Board (EUB). - EUB considers application and makes decision.
- Following receipt of EUB approval AESO procures
project from a transmission facility owner (TFO). - TFO prepares and files Facility Application with
EUB. - EUB considers application and makes decision.
- Following receipt of EUB approval TFO proceeds
with construction of project.
14Transmission System Development
15AESO Transmission Strategy Objectives
- To define a transmission system development
strategy that will enable the timely approval and
construction of transmission facilities so as to - Provide adequate transmission facilities that
will meet defined reliably and performance
criteria and provide efficient service - Facilitate the development of new generation in
the system - Facilitate the competitive wholesale electricity
market so as to allow market forces to minimize
the overall delivered wholesale cost of
electricity to consumers - Strategy Deliverable The Conceptual Plan
16The Conceptual Plan
- Objectives
- 20 year outlook for system development
- primary focus on 500 kV development
- Better understanding of the implications of
alternative generation and export scenarios on
the development of the transmission system - Preliminary evaluation of the impact on the
overall costs of generation and transmission
costs of the alternative generation and export
scenarios - 3 generation scenarios - Ft. McMurray, Edmonton
area, southern Alberta area - 3 export scenarios - 0, 1000 and 2000 MW
- 2 load forecast scenarios - expected, high
17(No Transcript)
18North - South Upgrade
- 1. Convert the south Keephills to Genesee to
Ellerslie circuit to 500 kV operation by 2006,
estimated cost 32M - 2. Build 1st north - south 500 kV cct from
Genesee to Langdon by 2009 estimated cost 300 M - 3. Acquire right-of-way for 2nd north - south 500
kV cct from Keephills to Langdon estimated cost
11 M - 4. Acquire right-of-way for /- 500 kV HVDC line
from Fort McMurray area to Calgary area
estimated cost 45 M
FM
EL
KH
1
GN
3
4
2
LD
19Southwest Alberta - Staged Development, Triggers
and Cost Estimate
20Proposed Development - Southwest Alberta
21Other Transmission Constraints
- To northwest Alberta
- Into southeast Alberta, including tie to
Sask. - Local Edmonton and Calgary areas
- Other regional and local upgrades
22Questions?
23Contact Us
Current Prices and Market Statistics Historical
Reports News, Announcements Market and
Transmission Access www.aeso.ca
24(No Transcript)