Design and Analysis of a Turbine Blade Manufacturing Cell - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Design and Analysis of a Turbine Blade Manufacturing Cell

Description:

Created a hybrid coding scheme for three turbine blade part numbers (P/N) to be ... A I Shipping Blade Cell Vendor Insp. Blade Cell E X. U U E. Vane Cell A O. A O ... – PowerPoint PPT presentation

Number of Views:652
Avg rating:3.0/5.0
Slides: 10
Provided by: raysu
Category:

less

Transcript and Presenter's Notes

Title: Design and Analysis of a Turbine Blade Manufacturing Cell


1
Design and Analysis of a Turbine Blade
Manufacturing Cell
Term Project Presentation
  • MEAE-6960H01
  • Professor Ernesto Gutierrez-Miravete
  • Presenter Ray Surace

2
Project Overview
  • Created a hybrid coding scheme for three turbine
    blade part numbers (P/N) to be produced in a
    group technology environment
  • Reviewed the performance of an initial turbine
    blade cell design with 12 workstations
  • Developed an improved cell design with 10
    workstations
  • Created a facility layout using the Column-Sum
    Insertion Heuristic
  • Used a modified Approximate Three-Stage Markov
    Chain Model to determine the optimum size of
    buffers placed before and after an airfoil
    overlay coater
  • Performed a Mean Value Analysis to validate the
    final design of a turbine blade manufacturing cell

3
Part Coding
  • Three (3) P/Ns with common features were grouped
    to form a composite part family
  • An alphanumeric hybrid coding scheme was derived
    from the machining sequence
  • The code makes use of the chain property each
    character place in the code has a specific
    meaning Example P/N
    100b1
  • Code 1 b 1 y 3
  • first digit
    part stage cooling
    hole
  • of engine model i.e.
    1STG1 code
  • part type coating?
  • bblade
    yyes, nno
  • Cooling hole code 0no cooling holes, 1laser
    cooling holes, 2EDM cooling holes, 3laser and
    EDM cooling holes

4
Performance of 12 Workstation Cell Design
  • Initial cell design incorporated 12 workstations
    into a U-shaped cell layout to complete
    machining and finishing operations on P/N 100b1,
    200b1, and 100b2 turbine blade castings.
  • 1 2 3 4
    5 6
  • isle 12 11 10 9
    8 7

5
Performance of 12 Workstation Cell Design
  • Customer demand rates for all 3 P/Ns dictate that
    9.12 parts must be produced per hour
  • Thus, cycle time C, must be 0.11 hrs. for each
    workstation
  • Processing time of the precipitation heat treat
    furnace is 24 hours the retort can hold 150
    blades. Thus, C 0.16. This is
    unacceptable.
  • To meet customer demand rates the furnace retort
    must have a capacity of
  • Checking utilization we find that the heat treat
    furnace is a bottleneck operation
  • Thus, Um, furnace 1.46
  • If a furnace with a capacity of 219 blades is
    purchased, WIP would increase by 69 pcs
  • 219 blades - 150 blades 69 blades
  • By removing the heat treat furnace from the cell,
    the overall WIP (WIPPxT) of the cell can be
    reduced by 150 pcs.
  • New cell design to include 10 workstations
    precipitation heat treat and shot peen machines
    moved to a separate department

6
Layout of 10 Workstation Cell Design
  • Final turbine blade manufacturing cell design
    incorporates 10 workstations into a U-shaped
    cell layout
  • coater input buffer
  • 5 4 3 2 1
  • 6
  • coater output 7 8 9
    10
  • buffer isle

7
Turbine Airfoil Manufacturing Facility Layout
  • Column Sum-Insertion heuristic used to create a
    block plan of a turbine airfoil manufacturing
    facility with the following departments
  • Receiving
  • Vendor Inspection (incoming casting inspection)
  • Blade Cell
  • Vane Cell
  • Heat Treat / Sot Peen Department
  • Shipping
  • Receiving
  • A Receiving
  • Vendor Inspect
    I
  • A I
    Shipping Blade
    Cell Vendor Insp.
  • Blade Cell
    E X
  • U U E
  • Vane Cell
    A O
  • A O
  • Heat Treat/Peen
    O Heat Treat /
    Peen Vane Cell
  • A
  • Shipping

8
Analysis of Coater Buffer Capacity
  • Buffers are required before and after the coater
    in order to maintain a cycle time of 0.11 hrs.
  • An Approximate Three-Stage Markov Chain Model was
    modified to determine the optimum buffer size
  • The following modeling assumptions were made
  • Cell modeled as a paced transfer line with M10
    stages
  • Coater capacity of 19 blades
  • Assumed the average mean time to failure, a-1 of
    workstations 1-5 and 7-10 approaches 0.
    Therefore a1-5,7-10 1e-6
  • Assumed acoater1. Once the coater starts a
    cycle, any incoming parts go into the incoming
    buffers
  • The avg. mean repair time (coater cycle time)
    for the coater b-118.18cycles, or b0.05
  • The results of the Three-Stage model analysis are
    as follows
  • The effectiveness of the cell without buffers,
    E00.53282
  • The maximum cell effectiveness is E21.53284
  • Therefore, the optimum buffer size before and
    after coating is Z21

9
Performance of 10 Workstation Cell Design
  • A Mean Value Analysis (MVA) was performed to
    validate the 10 workstation blade cell design
  • The cell was modeled as a closed network with
    single servers
  • It was assumed that each P/N (p) may visit each
    workstation (j) in that parts processing
    sequence once
  • A visit count (Vjp) table was constructed
  • To initialize the algorithm, a queue length
    (Ljp) of 1 was assumed in front of each
    workstation
  • The algorithm was calculated using the following
    formulas
  • (eqn. 11.24 AS) ,
    (eqn. 11.26 AS) ,
    (eqn. 11.27 AS)
  • After three (3) iterations the algorithm
    converged
  • The total production rate of the cell,
    Xtotal9.92 parts per hour. This exceeds the
    demand, 9.12 parts per hour by 8. Thus, the 10
    workstation cell design is acceptable.
Write a Comment
User Comments (0)
About PowerShow.com