Title: An Update on the Transformation Programme


1
Building a New Home Affairs
  • An Update on the Transformation Programme

Presentation to the Select Committee on Social
Services
4 JUNE 2008
2
The 2004-05 audit clearly indicated the need for
change
  • Following a disclaimer in the audit for 2004-5,
    the Minister of Home Affairs with the Ministers
    of Finance and Public Service and Administration
    mobilised a Support Intervention Team (SIT).
    The SIT began its work in June 2006.
  • The main work of the SIT was to analyse the root
    causes of the problems at the DHA and make
    recommendations.
  • Their report was made available in the first
    quarter of 2007 and accepted by the Committee of
    Ministers.

3
The Support Intervention Team confirmed deeply
rooted problems
  • The SIT reported that there were deeply rooted
    problems with
  • Leadership and Management
  • Human Resources and the organisational design
  • Information and Communication Technology
  • Service Delivery and
  • Financial Management and internal control.
  • The response of Minister, supported by the
    Cabinet, was to launch a comprehensive and
    well-resourced turnaround over three years

4
There are fundamental issues which must be
addressed at Home Affairs
Context
Scoping study for TAP Selected Observations
Case for Action
  • Qualified audit reports
  • Poor asset management
  • Fruitless and wasteful expenditure

Financial Management and Controls
Key Themes
  • Concept of citizen or customer as king alien
  • Cumbersome business management processes
  • Loss of key people on a regular basis

Service Delivery
  • Low motivation, poor supervision
  • Infringement of standard business rules breach
    of security
  • Aversion to technology
  • Scant attention to risk management
  • Weak management control processes

Corruption, Security Risk
  • Steeply hierarchical management structure
  • Over-centralised decision making
  • Limited business understanding who is the
    customer?
  • Inappropriate training
  • Limited management skills

Organisational Structure People
  • Unstable IT and communication Infrastructure,
  • Inadequate Infrastructure rollout to local and
    international offices)
  • Systems not linked to one another (e.g. Border
    Post immigration systems)
  • Duplication of systems and information
    (silo-based approach), which is costly and
    effects security
  • Inappropriate offices layout and limited
    footprint
  • Rudimentary asset management practices

IT Facilities
Source DHA Interviews, Inter Ministerial Report
5
Our objective for the Turnaround is clear
To transform the department into a modern,
efficient, cost-effective service organisation
responsive to the needs of South African
citizens, residents and visitors to our country
6
We have completed Phase 1 of the Turnaround which
focused on quick wins and designOur focus is now
on implementation
Building a new Home Affairs
Phase I
Phase 2
Early Value Realisation
Define
Design Develop
Embed Change
Implement
Stages
Transformation Implementation
Low
Piloting
Strategy Future End State Definition including
Roadmap
Criticality/ Urgency
Stabilisation Quick Wins
Time
High
  • Implement the transformation roadmap
  • Apply change management to ensure successful
    implementation
  • Embed changes by providing long term enabling
    incentives, structures and tools

Objectives (Why)
  • Stabilise key management processes
  • Implement early value initiatives" Quick Wins to
    galvanise support for the initiative
  • Define the future service delivery model
  • Determine roadmap to reach end state
  • Test rollout plans in a controlled setting before
    full implementation

Fundamentally Improve The Customer Experience
7
Phase I realised a number of key achievements
(1/2)
Phase I Overview and Key Achievements
Selected Achievements
8
Phase I realised a number of key achievements
(1/2)
Phase I Overview and Key Achievements
Selected Achievements
9
Phase I realised a number of key achievements
(2/2)
Phase I Overview and Key Achievements
Selected Achievements
10
In particular, the Vision Design team completed
the design of the New Home Affairs operating model
Overview of process followed and consultation
Current state analysis
Visioning
Design
  • In-depth analysis of current situation and issues
    by the different design teams
  • Interviews with stakeholders
  • Customer survey
  • 1st Visioning workshop Sept 10 to discuss and
    validate the current state analysis
  • 2nd Visioning workshop Sept 13 on Legislative
    framework
  • 3rd and 4th Visioning workshops Sept 27 and Oct 4
    to determine targets and principles for the new
    model and extent of separation between CS and NIB
  • 1st EXCO workshop 14 Nov discussion and
    validation of part 1 of the operating model
  • 2nd EXO workshop 27 Nov discussion and
    validation of part 2 of the operating model
  • EXCO presentation 4 Dec on integral New Home
    Affairs model

All workshops conducted with DHA wide management
representation present
Current state analysis
High-level operating model
DHA Executive leadership structure
New Home Affairs operating model
11
A unique feature in the model is that Customer
needs drove the design of the New Home Affairs
Service Delivery Model
Service Delivery Model
People
Facilities
Processes
Customer Cube
Operating model
IT
How?
What?
What processes will link our business
architecture to our customers in the delivery of
our services?
What IT and facilities do we need to deliver
services to our customers?
  • Which services will be offered to which customers
    through which channels?
  • What service and productivity levels are required?

What staff with what skills do we require?
The organizational structure will result from
not drive the design of the service delivery
model
Source A.T. Kearney
12
Going forward, 55 projects - clustered in 7
workstreams - have been identified to achieve the
total transformation, to be completed over a 2-3
year period
Proposed High-Level Programme Structure 2008
and Beyond
Civics
Support Services
IT
Finance
NIB
2
3
1
4
5
  • 5 Functional Workstreams
  • Civics
  • NIB
  • Support Services
  • Finance
  • IT

Communications Transformation(1)
Finance Transformation(1)
ID Process Transformation1
FIFA 2010 Design and Planning
Online Verification Roll Out
Budgeting Split
Security Investigations Transformation(1)
Marpless System Implementation
Late Registration Roll-Out
Performance Mgmt Implementation
IT Application Realignment to New Architecture
Memory ID Card Pilot
Security Upgrade
Revenue Mgmt Roll-Out
Permits Transformation1
Passport Machine Process Implementation
MOUs and SLAs with 3rd parties
Policy Process Optimisation
Payroll verification
Refugee Transformation and Footprint Roll-Out
B/M/D redesign (incl certificate decentralisation
Procurement Transformation(1)
HR Transformation(1)
NPR Data Clean Up
Contact Centre Ramp-Up
2nd Wave SLAs
HR Policy and Strategy
Lindela Contract Optimisation
Birth Network Expansion
Supplier Sourcing
EDMS
Information Mgmt Trans-formation (incl. Archiving)
Inspectorate Transformation(1)
Audit Risk Implementation Monitoring
Evaluation
Centre of Excellence
Network Infrastructure Upgrade
Establishment of PMO
Footprint Optimisation (incl. MPCCs)
Foreign Office and Ports of Entry Review
Business continuity
Office Refurbishments
Fleet Optimisation
Mobile Unit Optimisation
Real Estate Optimisation
5
12
7
5
6
  • 2 Cross-Functional Workstreams
  • Organisational Implementation
  • Organisational Governance Operational Control

6
Leadership Appointments
Change Management
Employee Relations
Reporting Line Split
Job Profiling Skills Gap Analysis
Matching Staff Redeployment
Recruiting
Training
Employee Database Baseline
Performance Agreement Realignment
Payment Level Adjustments
11
7
Government Relations Strategy Plan
Operations Management Roll-Out
Delegation of Authorities Implementation
Policy Framework Legislative Programme
Committee Structure Roll-Out
5
Programme Management Office (PMO)
Organisational Projects Evaluation Monitoring
Project Communications
Scaffolding
GPW Corporatisation Oversight
4
Work-stream
Project
PMO
Sub-project
Note (1) Transformation is a holistic
implementation programme of a specific function
beyond just the reorganisation It includes
sub-projects involving process, system,
facilities and capability changes It will work
closely with the organisational implementation
team on the staff implications
13
The 5 functional workstreams will focus on
transforming Home Affairs to dramatically improve
the customer experience
Illustrative
High Level Functional Workstream Descriptions
Note (1) Benefits will be driven by the change
scenario and projects that DHA selects
14
2 cross-functional workstreams and the PMO will
centrally drive the reorganisation,
organisational governance and the overall
programme
High Level Cross-Functional Workstream
Descriptions
Illustrative
Note (1) Benefits will be driven by the change
scenario and projects that DHA selects
15
Work on the implementation has already begun
Illustrative1
Transformation Road Map and Selected Milestones
2008
2009
2010
15-25
55-65
Completion of Transformation Programme
75-85
16
We have designed the programme for Phase 2 based
on five principles
Principles of the Programme Design
  • Bottom-up build All potential initiatives to be
    implemented in 2008 and beyond have been gathered
    from the workstreams and business units and
    grouped into projects
  • Top-down programme structure Projects have been
    grouped into a manageable set of 5-10 workstreams
    and set up either within the new organisational
    structure or as centrally-coordinated
    cross-functional activities
  • Prioritisation and sequencing Projects have
    been prioritised and sequenced within each
    workstream based on the degree of business
    benefit it will generate, costs and
    implementation dependencies
  • Governance Each project has a clear governance
    and support structure
  • Driven by the PMO and sponsor and supported by
    FeverTree-A.T. Kearney consultants
  • Driven by the PMO and sponsor and supported by
    another consultancy/ specialist
  • Monitored by the PMO and supported by another
    consultancy/ specialist
  • Monitored by the PMO and implemented by the
    business
  • Scenarios 3 change scenarios have been
    developed varying in scope and pace

17
Thank You