Title: Introduction to Trenchless Methods
1Introduction to Trenchless Methods
Presented by Glenn M. Boyce, PhD, PE Senior
Associates
April 21, 2009
2Presentation Objectives
- Provide a better understanding of trenchless
methods used for new installations - Learn the advantages and limitations of the
methods - Discuss contractor qualifications
3Types of Infrastructure
- Gas Pressure
- Water Pressure
- Sewer Gravity
- Drainage Gravity
- Power Non-gravity
- Communications Non-gravity
4Trenchless Methods
- Impact moling
- Pipe ramming
- Auger boring
- Pilot tube
- Pipe jacking / Microtunneling
- Conventional tunneling
- Horizontal directional drilling
- Pipe bursting
5Generic Size and Length
- Method Size LengthMoling 2 - 12
150Ramming 8 - 72 300Auger Bore 8 -
60 250Pilot Tube 6 - 42
300Microtunneling 12 - 108 1,500Pipe
Jacking gt54 3,000HDD 2 - 48
6,500Tunneling gt60 Any length
6What to Do?
- Choose the right method
- Use established Standards
- Collect information/investigate
- Plan ahead
- Conduct risk assessments
- Include mechanisms to handle conflicts
7Use the Right Method
- Open cut
- Horizontal Directional Drilling
- Auger boring
- Pipe ramming
- Pipe jacking
- Microtunneling
- Tunneling
Pilot Tube
1996
8Auger Boring
- Road crossings
- Cohesive soils
- Short distances
- Above water table
- Need steel casing
- Minor steering
960-inch Diameter SBU-A
10Pilot Tube Method
- Medium distances
- Straight alignments with good accuracy
- Variety of soils
- Smaller shafts
- Moderate equipment costs
11Step 1
12(No Transcript)
13 14 15Step 2
16Pilot Tube Plus
- Now used as a guide for other method
- Auger boring
- Pipe Ramming
17Pipe Ramming
- Wide range of diameters
- Soils only
- Continuously supported
- Typically lt 300
- Above and below water table
- Need steel casing
- No steering control
18Installation Method
- Ramming in continuous length or segments
19Rammingin Progress
20Pilot tube
21Pipe Jacking
- Large diameters
- Soils and mixed ground
- Face supported
- Long distances
- Above the water table
- Steerable
22Microtunneling
- Range of diameters (gt 12)
- All ground types
- Continuous face support
- Long distances
- Above or below water table
- Range of pipe materials
- Steerable to line and grade
23Micro vs Utility Tunneling
Remotely operated Precise guidance Pipes jacked
from launch pit Continuous support to face
Conventional Rib Lagging Tunnel
Microtunnel
24Tunnel Shield Construction
Lining is built within shield. Lining does not
move longitudinally after placement.
25Required Axial Thrust versus Length of Drive for
Same Diameter
26Opposite Approaches
- Open Cut
- What happens happens
- Trenchless
- Understand and plan
27What to Do?
- Understand the site history and potential
obstructions - Look at old aerial photos
- Conduct a geotechnical program
- Locate all utilities
28Potential Obstructions
- Cobbles or Boulders
- Wood
- Fill materials
- Hard zones
- Mixed faces
29Typical Machine Sizes
- Piercing 2 to 3 inches
- Pilot Tube 6 to 36 inches
- HDD 6 to 54 inches
- Auger Boring 10 to 60 inches
- Pipe Jacking/MT 12 to 96 inches
- Pipe Ramming 12 to 144 inches
- Shield 60 to 144 inches
30Typical CMP Culverts
31Replacement Issues
- Need to increase size for aquatic passage
- Must keep existing culvert active during
construction - Minimize costs
- Develop the best cross section
- Use the right materials
32Possible Solutions
33Consume the Culvert
34Use Liner Plate Tunnel
35Design Solutions
- Built a parallel pipe barrel
- Increases capacity
- Allow the existing to remain in service
- Get to use the materials you want
- Slipline the existing after new
- Built a new entry and exit apron
36Closing Thoughts
- Methods still evolving
- Many hybrid methods emerging
- Better alignment control emerging in auger
boring applications - Must identify potential obstructions (or get
X-ray vision)
37HORIZONTAL DIRECTIONAL DRILLING (HDD)
Samuel T. Ariaratnam, PhD, PE Arizona State
University
38Background
- Lengths up to 8,400 feet
- Diameters of 2 54
- Applications
- Utility conduits
- Pipelines
- Gravity sewers
- Force mains
- Horizontal remediation wells
- Geotechnical investigations
39Pilot Bore and Tracking
Pilot Bore
40(No Transcript)
41Drill Bits
42(No Transcript)
43Reaming/Hole Enlargement
Reaming
44Reamers
45CLAY
ANNULAR SPACE REGION
46SAND
ANNULAR SPACE REGION
47Pipe Material Distribution
Underground Construction Magazine 9th Annual
Survey, June 2007
48(No Transcript)
49(No Transcript)
50(No Transcript)
51(No Transcript)
52(No Transcript)
53(No Transcript)
54(No Transcript)
55(No Transcript)
56(No Transcript)
57(No Transcript)
58(No Transcript)
59Conclusions
- HDD is a minimally-intrusive trenchless
construction method suited for highly congested
urban areas and high traffic zones - Horizontal Directional Drilling equipment is
capable of installing a wide range of utilities - HDD will never replace traditional open-cut
methods however, they complement each other
60PIPE BURSTING
Samuel T. Ariaratnam, Ph.D., P.E. Arizona State
University
61Pipe Bursting
- Lengths typically 300-600 ft
- Diameters up to 42
- Applications
- replacement of force mains
- replacement of gravity sewers
Static Head
Pneumatic Head
62Common Types of Bursting Systems
Pneumatic Systems - Usually include a pneumatic
tool and winch and bursts the pipe using the
kinetic energy of the tool. The pipe is usually
attached to either the burst head or tool.
Static Systems Usually include a hydraulic
power source and a rod shuttling system and use
high tonnage to pull new line into place.
Small Portable Systems - Either pneumatic or
static for doing small diameter and short runs
(e.g. laterals).
63Introduction
- Emerging field of pipe replacement
- Replacement of the host pipe by fragmenting the
existing conduit and installing a completely new
pipe of equal diameter or larger in its place.
64Applications
- Total pipe replacement
- Typical upsize as much as 20 30
- Industrial Municipal - Main Line Laterals
- Various host and product pipe materials
- Continuous or Sectional pipe installation
65Pipe Bursting Feasibility
- May achieve lower costs compared to open trench
- Less construction time
- Minimal excavation
- Social cost savings
- Reduces ground settlement
- Low environmental impact
66Static Method (Continuous)
67Static Method (Sectional)
68Pneumatic Method
69Almost all types of pipe can be burst
- Cast iron
- Steel
- Ductile iron
- High Density Polyethylene
- Polyvinylchloride
- Concrete
- Reinforced concrete
- Asbestos cement
- Clay
70Various Host Materials
VITRIFIED CLAY
STEEL
CAST IRON
71650mm (26)
750mm (30)
350mm (14)
72Conclusions
- Pipe bursting is the only trenchless method
capable of installing a new pipe of equal or
larger diameter as a replacement option - Almost any type of existing pipe can be burst and
replaced with most pipe materials - Proper planning is critical to project success!
73CONTRACTOR QUALIFICATIONS PRE-QUALIFICATION
74Introduction
- The majority of trenchless contractors are
reliable and follow good installation practices - However, agencies must be aware of those few
cowboy contractors - Qualifying contractors is a recommended practice
for trenchless projects to ensure use of
competent contractors
75Specifications
- Manufacturers Recommended Specifications
- Industry/Association Specification Guidelines
- Project Specific
76Testing Inspection
- Quality Assurance Controls in Specifications
- Trained Inspectors
- Testing by Owner Laboratory
- Final CCTV Inspection of the Installed Pipe
77Protection of Existing Utilities
- Call in Locates
- Obtain As-Built Maps (Shared Responsibility)
- Mark Utilities (Utility Owners)
- Confirm Utilities (Pothole) (Excavator)
- Protect (Excavator)
78Protection of Existing Utilities Locate Marks
79As-Builts, Operator Logs, Notes
- Contractor is responsible for marking the plans
to indicate any and all vertical and horizontal
deviations between the design and actual
installation - Operator logs/notes should be maintained and
updated daily by the Contractor and should
include - Pipe number, depth, pitch, steering commands, and
notes
80Logbook/Field Notes
81Contractor Submittals
- Proof of success on prior similar projects
- Pipe material, diameter, length
- Make/model of equipment, guidance equipment,
fluid mixture - Slurry disposal plan
- Contingency plan
- Safe plan and protocols
- Certification by the manufacturer that the
Contractors personnel are trained in the use of
the equipment - Training certification for pipe installation
- Fusion training certification for HDPE
- Construction Plan Installation Schedule
- Traffic Control Plan
82Damage Avoidance
83Trenchless Training Courses
- Horizontal Directional Drilling Good Practices
- Pipe Bursting Good Practices
- New Installation Methods Good Practices
- Cured-in-Place Pipe (CIPP) Good Practices
- Sewer Laterals Rehabilitation Replacement
(www.nastt.org)
84Caltrans Inspector Training
Classroom
Field Exercises
85Conclusions
- Well-written specifications are important to
minimize claims - Hiring a competent contractor can be achieved
through pre-qualification - There are numerous available trenchless
technology options