Salinity Management Pipeline, Phase 1E - PowerPoint PPT Presentation

1 / 51
About This Presentation
Title:

Salinity Management Pipeline, Phase 1E

Description:

LDs if Work is Not Completed within Time(s) for Completion or by Fixed Calendar ... Any required new TCPs shall be submitted to the Engineer and Calleguas for ... – PowerPoint PPT presentation

Number of Views:93
Avg rating:3.0/5.0
Slides: 52
Provided by: krist48
Category:

less

Transcript and Presenter's Notes

Title: Salinity Management Pipeline, Phase 1E


1
Salinity Management Pipeline, Phase 1E
  • Mandatory Pre-Bid Meeting and Site Visit
  • May 21, 2009

This presentation is not a part of the Contract
Documents.
2
Introductions
  • Calleguas MWD Project Owner and Construction
    Manager
  • Kristine McCaffrey, P.E. (Project Manager)
  • Construction Inspector TBD
  • Perliter Ingalsbe Design Engineer
  • Rean David Kunitake, P.E. (Project Manager)

3
Schedule of Activities for Pre-Bid Meeting and
Site Visit
  • Pre-Bid Meeting (9 am 1000 am)
  • Mandatory Site Visit directly following Pre-Bid
    Meeting (1030 am)
  • 1st Meeting Point Edison Dr. and Hueneme Rd.
    Intersection (NE Corner)
  • 2nd Meeting Point Perkins Rd. and Hueneme Rd.
    (SE Corner)
  • 3rd Meeting Point Port Hueneme Beach Park
    Parking Lot on Surfside Dr.
  • Attendance will be taken at each stop.

4
Bid and Award Schedule
5
Project Overview
  • 9,921 LF of 48 WSP from Edison Dr. and Hueneme
    Rd. along Hueneme Rd. and Surfside Dr. to Port
    Hueneme Beach Park Parking Lot A.
  • 894 LFof 12 WSP along Perkins Rd.
  • Five casings installed via trenchless methods
    (pipe ramming and/or auger boring).
  • Connections to existing 48 PVC and 30 WSP.

6
Project Overview
  • Cast-in-place flow control and meter vaults,
    including electrical, communications, and
    instrumentation equipment.

7
Project Overview
  • Manholes, valves, blow-offs, automatic vacuum and
    air release valve assemblies, and sampling
    station.
  • Traffic control.
  • Surface restoration, including paving, overlay,
    hydroseeding, landscape, hardscape, and striping.

8
Schedule for Completion and Liquidated Damages
(SC 1-02)
9
Allowable Working Times
  • Seasonal Work Limitations
  • No work shall occur and no equipment, materials,
    or facilities shall be allowed within Surfside
    Drive between April 16 and September 15 of any
    year. (SC 1-03)
  • No Work Days
  • Memorial Day
  • Independence Day
  • Labor Day
  • Thanksgiving Day
  • Day after Thanksgiving
  • Christmas Day
  • New Years Day
  • Except traffic control maintenance and flaggers.
    (SC 1-04)
  • Additionally, no work in Port Hueneme on their
    city holidays. (Appendix C)

10
Allowable Working Times
  • Allowable Work Hours and Days
  • See Traffic Control Plans.

11
Work Area Limitations
  • Encroachment Permits
  • Permanent and Temporary Easements
  • Temporary Right-of-Entry

12
Encroachment Permits(Appendix C)
  • The Owner has obtained encroachment permits from
    the County of Ventura and City of Port Hueneme
    and conditions for an encroachment permit from
    the City of Oxnard. (County of Ventura permit to
    be provided via addendum.)
  • The Contractor shall obtain a duplicate
    encroachment permit from Port Hueneme and obtain
    an encroachment permit from Oxnard.
  • All construction shall conform to the provisions
    of the public agencies encroachment permits and
    any of their special conditions.

13
Permanent and Temporary Easements (Appendix H)
  • Permanent and temporary easements have been
    obtained for a portion of the pipeline alignment
    paralleling Hueneme Rd. roughly between Conner
    Dr. and Perkins Rd.
  • Easements also encompass meter and control valve
    vaults.

14
Temporary Right-of-Entry(Appendix H)
  • The Owner has entered into a right-of-entry
    agreement with The Bungalows at Beach House HOA
    for placement of traffic control signs only on
    private roads.
  • Signs must be posted so as not to damage pavement
    or landscaping.

15
Traffic Control Issues (SC 1-21, Section 13520,
Appendix C)
  • If the Contractor requests any changes to the
    TCPs, the Contractor will be required to prepare
    revised TCPs submit them to the Engineer and
    Calleguas for review and approval prior to
    submittal to the agencies and pay the
    Engineers, Owners, and agencies fees for
    reviewing the TCPs.
  • Temporary traffic control during tasks not
    directly related to main pipeline installation is
    the responsibility of the Contractor. Any
    required new TCPs shall be submitted to the
    Engineer and Calleguas for review and approval
    prior to submittal to the agencies having
    jurisdiction.
  • The Contractor shall allow for 4 weeks for review
    of each TCP submittal by the agencies.

16
Traffic Control Issues (SC 1-21, Section 13520,
Appendix C)
  • Traffic control performed within the County of
    Ventura jurisdiction shall be done by an
    independent 3rd party whose sole responsibility
    is for traffic control.
  • The Contractor may not, without written
    permission from the Owner, install any temporary
    traffic controls for pipeline construction in the
    public ROW prior to having all pipe and fittings
    necessary to complete the work to be constructed
    under that traffic control set up on site or at a
    local storage yard.
  • Contractor must take photos of traffic control
    setups daily and submit those photos weekly.

17
Traffic Control Issues (SC 1-21, Section 13520,
Appendix C)
  • The Contractor shall designate a Traffic Control
    Manager (TCM), who must be present at the Site
    during times when the Contractor requires traffic
    control and is performing construction work.
  • The Contractor shall maintain 24-hour telephone
    numbers at which the TCM can be contacted and be
    available upon request outside normal working
    hours.
  • The TCM shall have the appropriate personnel,
    equipment and material available at all times in
    order to expeditiously correct any deficiency in
    the traffic control system.

18
Pipe Requirements
  • Pipe Pre-Submittal Meeting
  • Spare Pipe
  • Pipe Testing

19
Pipe Pre-Submittal Meeting (SC 1-13)
  • The Contractor shall attend a pre-submittal
    meeting attended by the following
  • Contractors Project Manager
  • Contractors Project Engineer or person
    responsible for technical assembly of Submittals
  • Representative(s) for the WSP and fittings
    fabricator(s)
  • Shop superintendent(s) or direct subordinate
    responsible for the manufacturing of 24 WSP and
    fittings
  • If these representatives are not present, the
    meeting will be cancelled and rescheduled at no
    additional cost to the Owner. The Contractor
    shall verify and communicate verification to the
    Owner at least 7 Calendar Days prior to the
    meeting that each of the WSP related attendees
    have received a copy of the portions of the
    Specifications related to their work.

20
Spare Pipe (Section 02620 and Bid Item 39)
  • Additional pipe and fittings shall be provided as
    follows
  • Two 48 20 lay length pipe PE x Bell
  • Two 48 30 lay length pipe PE x PE
  • Two 48 buttstraps
  • All pipe and fittings shall be designed and
    fabricated as Class 75 pipe with an assumed 20-
    foot earth overburden.
  • Minimum cylinder thickness shall be as specified
    and as additionally required.
  • Pipes and fittings shall be compatible with other
    48 pipe installed in the Work.

21
Pipe Testing(Section 02660)
  • Test in accordance with AWWA C200 - Steel Water
    Pipe 6 In. and Larger.
  • Required test pressure provided on key plan and
    profile sheets. (Test GradientElevation 200
    feet)
  • Tie-in connection joint of the 48 WSP to the
    existing 48 PVC pipe shall be tested separately
    and to a maximum of 100 psi.

22
Factory Inspection(SC 1-35)
  • All materials shall be subject to inspection at
    the place of manufacture. Manufacturing
    activities requiring inspection may include
  • Review of the proposed manufacturing plant to
    verify its suitability for fabrication of the
    required materials and appurtenances.
  • Fabrication, including fittings and specials.
  • Application of plant-applied pipe linings and
    coatings.
  • Shop testing of all manufacturing processes and
    manufactured materials.
  • Processes used to transport materials to and from
    each manufacturing phase to preparing materials
    for transport to the Site.

23
Factory Inspection(SC 1-35)
  • At his discretion, the Owner shall arrange for
    and pay a Materials Inspector to perform
    inspections on behalf of the Owner for the
    following items.
  • Steel pipe and fittings 12 and larger (including
    linings and coatings)
  • Butterfly Valves 12 and larger
  • Control panel

24
Factory Inspection(SC 1-35)
  • The Contractor shall provide the Owner with 10
    Working Days advanced written notice of the date
    when fabrication will begin.
  • If fabrication begins later than that date, the
    Contractor shall pay to Calleguas all costs for
    an inspector to wait on standby for the
    fabrication or testing to begin, including hourly
    wage, per diem, and expenses.
  • Failure on the part of the Contractor to provide
    the notice required shall be just cause for the
    Owner to reject the materials fabricated without
    such notice.

25
Factory Inspection(SC 1-35)
  • The Contractor shall provide for the manufacturer
    to furnish safe access and to cooperate with the
    Materials Inspector in the performance of his
    duties.
  • The Materials Inspector shall have free entry at
    all times to the manufacturers facilities while
    tests and inspections are being conducted.
  • Adequate facilities shall be furnished to allow
    the Materials Inspector to perform his
    inspections, including taking photographs.
  • Retain on file and make available upon request,
    copies of all specified reports, test results,
    and quality control documentation.

26
Factory Inspection(SC 1-35)
  • All pipe of each material shall be fabricated at
    one location in US.
  • Linings and coatings may be applied at separate
    facilities, but these must also be within the US.
  • All valves subject to shop inspection and testing
    shall be manufactured in the US.

27
Potholing Requirements(GC 5.25 and SC 1-40)
  • The Contractor shall pothole
  • All utilities where crossings, interferences, or
    connections to the new pipelines or other
    facilities are marked by the utility companies or
    indicated by surface signs or other surface
    markers or indications.
  • All utilities parallel to and within 15 ft of the
    pipeline. Parallel utilities shall be potholed at
    sufficient intervals to verify the location of
    the utility relative to the pipeline or structure
    being constructed.
  • All utilities adjacent to and within 5 ft of all
    buried structures. The number of potholes shall
    be sufficientto determine plan location and
    direction and depth of all said utilities.

28
Potholing Requirements(GC 5.25 and SC 1-40)
  • If a utility that is required to be potholed as
    described above is not found at the expected
    depth, the Contractor must continue to pothole
    deeper until either the utility is located or
    the pothole reaches 1 ft below the elevation of
    thebottom of the planned pipeline or structure
    without encountering the utility.
  • Additional potholing requirements in Sections
    02315 and 02320 for trenchless crossings.

29
Tunneling Requirements(Sections 02315 and 02320)
  • Five trenchless crossings are required on this
    project.
  • Contractor may select auger boring (Section
    02315) or pipe ramming (Section 02320) for each
    trenchless crossing.
  • Both methods require a pilot tube to be used for
    increased accuracy.

30
Construction for Port Hueneme and Oxnard (SC 1-07)
  • Port Hueneme Sewer Relocation
  • Contractor shall install the relocated sewer with
    the existing sewer line in service.
  • Tie-ins between the relocated sewer and the
    existing sewer shall only be performed Mon-Fri
    between 7am and 4pm.
  • 7 Working Day notice to Owner required.
  • Oxnard Water Line Relocation
  • 5 Calendar Day shutdown allowed for relocation of
    existing water line.
  • 5 Working Day notice to Owner required.

31
Southern California Edison/Verizon Coordination
  • SCE Coordination Electrical service connection
    design from SCE is included in Appendix F. The
    Contractor shall notify the Owner, in writing, 40
    Calendar Days in advance of requiring the
    services of SCE to perform electrical service
    work. (SC 1-37)
  • Verizon Service Connection and Coordination
    Communication service connection shall be
    obtained by the Owner. Construction of any
    Verizon facility shall be performed in accordance
    with Verizon standards and requirements and the
    requirements of the Contract Documents. The
    Contractor shall notify the Owner, in writing, 40
    Calendar Days in advance of requiring the
    services of Verizon to perform communications
    work. (SC 1-38)

32
Permits(Appendix C)
  • Oxnard/Port Hueneme/County Encroachment
  • VCWPD Encroachment
  • Railroad Encroachment
  • Stormwater NOI
  • Dewatering Discharge
  • Hydrostatic Discharge
  • Oxnard Coastal Development Permit
  • Port Hueneme Coastal Development Permit
  • CalOSHA Tunnel Classification

Additional information provided on subsequent
slides.
33
Stormwater NOI(Appendix C and Section 02970)
  • Implement all measures necessary to comply with
    construction stormwater runoff requirements in
    SWRCB Order No. 99-08-DWQ, NPDES General Permit
    No. CAS000002.
  • Prepare a SWPPP which complies with the
    requirements of the General Permit.
  • SWPPP must be prepared, submitted, and accepted
    prior to any construction work, including
    potholing.
  • Amend the SWPPP as required by the General
    Permit.
  • Furnish, install, and maintain all erosion and
    sediment control measures described in the
    approved SWPPP.
  • Implement monitoring programs, record keeping,
    maintenance, inspection, repair, training, and
    sampling as required in the General Permit.

34
Dewatering Discharge(Appendix C and Section
02140)
  • Design, furnish, install, operate, monitor,
    maintain and remove a temporary dewatering system
    as required to lower and control water levels
    below subgrades of excavations to permit
    construction in the dry.
  • Collect and properly dispose of all discharge
    water from the dewatering system in accordance
    with California RWQCB NPDES Permit No. CAG994004,
    CI-9469.
  • Allowable discharge points are shown on the
    Drawings.Contractor may discharge into sotrm
    drains that connect to these discharge points.

35
Dewatering Discharge(Appendix C and Section
02140)
  • Contractor shall submit to the Owner, within the
    first 5 days of the month, the total volume of
    water discharged during each day of the previous
    month.
  • The Owner will take the samples required by
    Permit No. CAG994004, CI-9469 and submit the
    required reports to the RWQCB. The Owner will
    notify the Contractor if his discharge fails to
    comply with the permit requirements.
  • The Contractor shall take daily samples of the
    discharge and analyze them in the field each day
    for turbidity. Dewatering and treatment system
    must maintain an average turbidity below 50 NTU.

36
Additional Information Available
  • Record Pipeline Information Appendix J contains
    CD of record drawings and record pipeline layout
    drawings for the portion of the 48 PVC to be
    connected to and design drawings for the 30 WSP
    be connected to. This information is provided as
    a convenience to the Contractor only, and all
    information contained therein shall be field
    verified prior to pipe fabrication (SC 1-23).
  • Geotechnical Information Geotechnical reports
    are available at www.calleguas.com/planholders.htm
    , but are not a part of the Contract Documents
    (SC 1-17).

37
Mitigation Measures
  • Mitigation monitoring plan can be found in
    Appendix E.
  • Specific mitigation measures of interest include
  • Archaeologist Orientation/Training (SC-28)
  • Flat Blade Bucket Excavation (Section 02220)
  • Noise and Vibration Control and Monitoring
    (Section 01560)

38
Buy American Provision(SC 1-42)
  • When possible, the Contractor shall provide, use,
    and install only iron, steel, and manufactured
    goods produced in the United States in the Work.
    More information on federal Buy American
    requirements can be found at http//www.arnet.gov/
    far/current/html/Subpart2025_1.htmlwp1118857

39
Labor Compliance Program (SC 1-43 and Appendix
I)
  • The Work is subject to the requirements of an
    LCP. Calleguas has retained the services of a 3rd
    party LCP administrator. The Contractor shall
    cooperate fully with the administrator in
    submitting information and cooperating with site
    visits and other required LCP activity.
  • The Contractor shall post at the Site the contact
    information for the administrator.
  • Calleguas reserves the right to withhold progress
    and final payment on this project until all
    appropriate certified payroll forms and related
    LCP documents are submitted and found to be in
    compliance.

40
Labor Compliance Program(SC 1-43 and Appendix I)
  • The following language is hereby inserted at the
    end of Article 6.3.8 of the GCs (3) Any sums it
    believe may be necessary in response to failure
    to fully comply with LCP requirements for the
    Work.
  • Only individuals who are legally able to work in
    the US shall be employed for the Work.
  • As California prevailing wage statutes and
    regulations are also applicable to the Work, the
    more restrictive requirements will be applied.
  • Calleguas requires that certified payrolls be
    submitted electronically via LCP Tracker or
    similar electronic service designated by
    Calleguas.

41
Experience and Contractors License Requirements
(N-9)
42
Experience and Contractors License Requirements
(N-9)
(a) The experience of a traffic control
subcontractor shall not substitute for or
supplement the Bidders traffic control
experience. The projects shall be those where
either the Contractor self-performed the traffic
control work or managed a subcontractor who
performed the traffic control work.
43
Experience and Contractors License Requirements
(N-9)
(b) The experience of the proposed auger boring
or pipe ramming subcontractor (as appropriate)
may be substituted for the Bidders
experience. (c) The experience of the proposed
auger boring or pipe ramming subcontractors
superintendent (as appropriate) may be
substituted for the Bidders Superintendents
experience. (d) The Contractors (or
Subcontractors) experience shall match with the
trenchless installation method(s) he proposes to
use. If the Contractor only plans to use one
trenchless method, then he is only required to
submit experience on that method if he plans to
use both methods, experience on both methods must
be submitted.
44
Experience and Contractors License Requirements
(N-9)
  • All qualifying experience must have been obtained
    in the past 15 years.
  • All qualifying experience must have been obtained
    on projects which have been successfully
    completed.
  • A single project may meet more than one of the
    experience requirements.
  • The Superintendent must have acted as
    Superintendent or Foreman on each project from
    project start through project completion.
  • The Project Manager must have acted as Project
    Manager on each project from project start
    through project completion.

45
Bid/Proposal Issues
  • Proof of Authority for Signature
  • Special Federal Provisions and Specifications
  • Manufacturers and Suppliers Experience
    Requirements
  • Information to be Submitted After the Bid
  • Insurance Requirements

46
Proof of Authority for Signature
  • Have bid signed by appropriate signatories
    (I-3).
  • Two signatures are required even if company
    policy allows one.
  • Furnish a resolution or other evidence
    demonstrating the authority of the Bidder to
    submit the Bid and the authority of each person
    executing the Contract, bonds and all other
    documents and instruments (I-3).
  • Provide notarization for forms in bid proposal.

47
Special Federal Provisions and Specifications
  • Federal funding is being used for this project
  • Federally Assisted Construction (N-14)
  • Special Federal Provisions and Specifications
  • Bid Proposal Forms
  • Certification of Bidder Regarding Equal
    Employment Opportunity
  • Certification by Proposed Subcontractor Regarding
    Equal Employment Opportunity
  • Certification regarding Debarment, Suspension and
    Other Responsibility matters Drug-free Workplace
    Requirements and Lobbying

48
Manufacturers and Suppliers Experience
Requirements (N-10)
  • Manufacturer of the 48 WSP and fittings must
    meet the following minimum requirements
  • The Pipe Manufacturer shall within the last 5
    years have manufactured at least 10,000 feet of
    48 or larger mortar lined and mortar coated WSP
    in conformance with AWWA C200 and C205 and the
    requirements similar to those in Section 02620 of
    these Specifications.
  • All aspects of the pipe fabrication process must
    be performed in the US.
  • Before a Contract is awarded, the Successful
    Bidder must demonstrate that the Pipe
    Manufacturer employs a CWI, certified in
    accordance with AWS QC1, and a NDT technician and
    operator qualified to a minimum of NDT Level II
    in accordance with ASNT SNT-TC-1A.

49
Information to be Submitted After the Bid
  • Within 3 Working Days from bid opening, submit
    Welded Steel Pipe Manufacturer Experience.
  • List the name of pipe fabricators and
    manufacturers who will provide pipe materials and
    fabrication for this project, and indicate their
    compliance with requirements as specified in
    Section N-10 of the NIB.

50
Insurance Requirements
  • Insurance documentation does not need to be
    submitted with the bid
  • Workers Compensation and Employers Liability
    Insurance Required of the Contractor (I-12)
  • Liability Insurance Required of the Contractor
    (I-13)
  • Certificates and endorsements shall be submitted
    for both the Successful Bidder and the
    subcontractor(s) performing trenchless work
    (I-10)
  • Coverage shall include railroads endorsement CG
    24 17 or equivalent on the CGL policy (I-13)
  • Additional insureds listed in SC 1-25

51
Questions
  • For bidding RFI/RFC
  • Use form in Appendix B and submit by June 23,
    2009 at 5 pm
  • Send to
  • Perliter IngalsbeAttention Rean David
    Kunitake, P.E.Fax (626) 398-9115
  • For planholders lists, geotech reports, this
    presentation, bid results, etc. visit
    http//www.calleguas.com/planholders.htm