Title: Salinity Management Pipeline, Phase 1E
1Salinity Management Pipeline, Phase 1E
- Mandatory Pre-Bid Meeting and Site Visit
- May 21, 2009
This presentation is not a part of the Contract
Documents.
2Introductions
- Calleguas MWD Project Owner and Construction
Manager - Kristine McCaffrey, P.E. (Project Manager)
- Construction Inspector TBD
- Perliter Ingalsbe Design Engineer
- Rean David Kunitake, P.E. (Project Manager)
3Schedule of Activities for Pre-Bid Meeting and
Site Visit
- Pre-Bid Meeting (9 am 1000 am)
- Mandatory Site Visit directly following Pre-Bid
Meeting (1030 am) - 1st Meeting Point Edison Dr. and Hueneme Rd.
Intersection (NE Corner) - 2nd Meeting Point Perkins Rd. and Hueneme Rd.
(SE Corner) - 3rd Meeting Point Port Hueneme Beach Park
Parking Lot on Surfside Dr. - Attendance will be taken at each stop.
4Bid and Award Schedule
5Project Overview
- 9,921 LF of 48 WSP from Edison Dr. and Hueneme
Rd. along Hueneme Rd. and Surfside Dr. to Port
Hueneme Beach Park Parking Lot A. - 894 LFof 12 WSP along Perkins Rd.
- Five casings installed via trenchless methods
(pipe ramming and/or auger boring). - Connections to existing 48 PVC and 30 WSP.
6Project Overview
- Cast-in-place flow control and meter vaults,
including electrical, communications, and
instrumentation equipment.
7Project Overview
- Manholes, valves, blow-offs, automatic vacuum and
air release valve assemblies, and sampling
station. - Traffic control.
- Surface restoration, including paving, overlay,
hydroseeding, landscape, hardscape, and striping.
8Schedule for Completion and Liquidated Damages
(SC 1-02)
9Allowable Working Times
- Seasonal Work Limitations
- No work shall occur and no equipment, materials,
or facilities shall be allowed within Surfside
Drive between April 16 and September 15 of any
year. (SC 1-03) - No Work Days
- Memorial Day
- Independence Day
- Labor Day
- Thanksgiving Day
- Day after Thanksgiving
- Christmas Day
- New Years Day
- Except traffic control maintenance and flaggers.
(SC 1-04) - Additionally, no work in Port Hueneme on their
city holidays. (Appendix C)
10Allowable Working Times
- Allowable Work Hours and Days
- See Traffic Control Plans.
11Work Area Limitations
- Encroachment Permits
- Permanent and Temporary Easements
- Temporary Right-of-Entry
12Encroachment Permits(Appendix C)
- The Owner has obtained encroachment permits from
the County of Ventura and City of Port Hueneme
and conditions for an encroachment permit from
the City of Oxnard. (County of Ventura permit to
be provided via addendum.) - The Contractor shall obtain a duplicate
encroachment permit from Port Hueneme and obtain
an encroachment permit from Oxnard. - All construction shall conform to the provisions
of the public agencies encroachment permits and
any of their special conditions.
13Permanent and Temporary Easements (Appendix H)
- Permanent and temporary easements have been
obtained for a portion of the pipeline alignment
paralleling Hueneme Rd. roughly between Conner
Dr. and Perkins Rd. - Easements also encompass meter and control valve
vaults.
14Temporary Right-of-Entry(Appendix H)
- The Owner has entered into a right-of-entry
agreement with The Bungalows at Beach House HOA
for placement of traffic control signs only on
private roads. - Signs must be posted so as not to damage pavement
or landscaping.
15Traffic Control Issues (SC 1-21, Section 13520,
Appendix C)
- If the Contractor requests any changes to the
TCPs, the Contractor will be required to prepare
revised TCPs submit them to the Engineer and
Calleguas for review and approval prior to
submittal to the agencies and pay the
Engineers, Owners, and agencies fees for
reviewing the TCPs. - Temporary traffic control during tasks not
directly related to main pipeline installation is
the responsibility of the Contractor. Any
required new TCPs shall be submitted to the
Engineer and Calleguas for review and approval
prior to submittal to the agencies having
jurisdiction. - The Contractor shall allow for 4 weeks for review
of each TCP submittal by the agencies.
16Traffic Control Issues (SC 1-21, Section 13520,
Appendix C)
- Traffic control performed within the County of
Ventura jurisdiction shall be done by an
independent 3rd party whose sole responsibility
is for traffic control. - The Contractor may not, without written
permission from the Owner, install any temporary
traffic controls for pipeline construction in the
public ROW prior to having all pipe and fittings
necessary to complete the work to be constructed
under that traffic control set up on site or at a
local storage yard. - Contractor must take photos of traffic control
setups daily and submit those photos weekly.
17Traffic Control Issues (SC 1-21, Section 13520,
Appendix C)
- The Contractor shall designate a Traffic Control
Manager (TCM), who must be present at the Site
during times when the Contractor requires traffic
control and is performing construction work. - The Contractor shall maintain 24-hour telephone
numbers at which the TCM can be contacted and be
available upon request outside normal working
hours. - The TCM shall have the appropriate personnel,
equipment and material available at all times in
order to expeditiously correct any deficiency in
the traffic control system.
18Pipe Requirements
- Pipe Pre-Submittal Meeting
- Spare Pipe
- Pipe Testing
19Pipe Pre-Submittal Meeting (SC 1-13)
- The Contractor shall attend a pre-submittal
meeting attended by the following - Contractors Project Manager
- Contractors Project Engineer or person
responsible for technical assembly of Submittals - Representative(s) for the WSP and fittings
fabricator(s) - Shop superintendent(s) or direct subordinate
responsible for the manufacturing of 24 WSP and
fittings - If these representatives are not present, the
meeting will be cancelled and rescheduled at no
additional cost to the Owner. The Contractor
shall verify and communicate verification to the
Owner at least 7 Calendar Days prior to the
meeting that each of the WSP related attendees
have received a copy of the portions of the
Specifications related to their work.
20Spare Pipe (Section 02620 and Bid Item 39)
- Additional pipe and fittings shall be provided as
follows - Two 48 20 lay length pipe PE x Bell
- Two 48 30 lay length pipe PE x PE
- Two 48 buttstraps
- All pipe and fittings shall be designed and
fabricated as Class 75 pipe with an assumed 20-
foot earth overburden. - Minimum cylinder thickness shall be as specified
and as additionally required. - Pipes and fittings shall be compatible with other
48 pipe installed in the Work.
21Pipe Testing(Section 02660)
- Test in accordance with AWWA C200 - Steel Water
Pipe 6 In. and Larger. - Required test pressure provided on key plan and
profile sheets. (Test GradientElevation 200
feet) - Tie-in connection joint of the 48 WSP to the
existing 48 PVC pipe shall be tested separately
and to a maximum of 100 psi.
22Factory Inspection(SC 1-35)
- All materials shall be subject to inspection at
the place of manufacture. Manufacturing
activities requiring inspection may include - Review of the proposed manufacturing plant to
verify its suitability for fabrication of the
required materials and appurtenances. - Fabrication, including fittings and specials.
- Application of plant-applied pipe linings and
coatings. - Shop testing of all manufacturing processes and
manufactured materials. - Processes used to transport materials to and from
each manufacturing phase to preparing materials
for transport to the Site.
23Factory Inspection(SC 1-35)
- At his discretion, the Owner shall arrange for
and pay a Materials Inspector to perform
inspections on behalf of the Owner for the
following items. - Steel pipe and fittings 12 and larger (including
linings and coatings) - Butterfly Valves 12 and larger
- Control panel
24Factory Inspection(SC 1-35)
- The Contractor shall provide the Owner with 10
Working Days advanced written notice of the date
when fabrication will begin. - If fabrication begins later than that date, the
Contractor shall pay to Calleguas all costs for
an inspector to wait on standby for the
fabrication or testing to begin, including hourly
wage, per diem, and expenses. - Failure on the part of the Contractor to provide
the notice required shall be just cause for the
Owner to reject the materials fabricated without
such notice.
25Factory Inspection(SC 1-35)
- The Contractor shall provide for the manufacturer
to furnish safe access and to cooperate with the
Materials Inspector in the performance of his
duties. - The Materials Inspector shall have free entry at
all times to the manufacturers facilities while
tests and inspections are being conducted. - Adequate facilities shall be furnished to allow
the Materials Inspector to perform his
inspections, including taking photographs. - Retain on file and make available upon request,
copies of all specified reports, test results,
and quality control documentation.
26Factory Inspection(SC 1-35)
- All pipe of each material shall be fabricated at
one location in US. - Linings and coatings may be applied at separate
facilities, but these must also be within the US.
- All valves subject to shop inspection and testing
shall be manufactured in the US.
27Potholing Requirements(GC 5.25 and SC 1-40)
- The Contractor shall pothole
- All utilities where crossings, interferences, or
connections to the new pipelines or other
facilities are marked by the utility companies or
indicated by surface signs or other surface
markers or indications. - All utilities parallel to and within 15 ft of the
pipeline. Parallel utilities shall be potholed at
sufficient intervals to verify the location of
the utility relative to the pipeline or structure
being constructed. - All utilities adjacent to and within 5 ft of all
buried structures. The number of potholes shall
be sufficientto determine plan location and
direction and depth of all said utilities.
28Potholing Requirements(GC 5.25 and SC 1-40)
- If a utility that is required to be potholed as
described above is not found at the expected
depth, the Contractor must continue to pothole
deeper until either the utility is located or
the pothole reaches 1 ft below the elevation of
thebottom of the planned pipeline or structure
without encountering the utility. - Additional potholing requirements in Sections
02315 and 02320 for trenchless crossings.
29Tunneling Requirements(Sections 02315 and 02320)
- Five trenchless crossings are required on this
project. - Contractor may select auger boring (Section
02315) or pipe ramming (Section 02320) for each
trenchless crossing. - Both methods require a pilot tube to be used for
increased accuracy.
30Construction for Port Hueneme and Oxnard (SC 1-07)
- Port Hueneme Sewer Relocation
- Contractor shall install the relocated sewer with
the existing sewer line in service. - Tie-ins between the relocated sewer and the
existing sewer shall only be performed Mon-Fri
between 7am and 4pm. - 7 Working Day notice to Owner required.
- Oxnard Water Line Relocation
- 5 Calendar Day shutdown allowed for relocation of
existing water line. - 5 Working Day notice to Owner required.
31Southern California Edison/Verizon Coordination
- SCE Coordination Electrical service connection
design from SCE is included in Appendix F. The
Contractor shall notify the Owner, in writing, 40
Calendar Days in advance of requiring the
services of SCE to perform electrical service
work. (SC 1-37) - Verizon Service Connection and Coordination
Communication service connection shall be
obtained by the Owner. Construction of any
Verizon facility shall be performed in accordance
with Verizon standards and requirements and the
requirements of the Contract Documents. The
Contractor shall notify the Owner, in writing, 40
Calendar Days in advance of requiring the
services of Verizon to perform communications
work. (SC 1-38)
32Permits(Appendix C)
- Oxnard/Port Hueneme/County Encroachment
- VCWPD Encroachment
- Railroad Encroachment
- Stormwater NOI
- Dewatering Discharge
- Hydrostatic Discharge
- Oxnard Coastal Development Permit
- Port Hueneme Coastal Development Permit
- CalOSHA Tunnel Classification
Additional information provided on subsequent
slides.
33Stormwater NOI(Appendix C and Section 02970)
- Implement all measures necessary to comply with
construction stormwater runoff requirements in
SWRCB Order No. 99-08-DWQ, NPDES General Permit
No. CAS000002. - Prepare a SWPPP which complies with the
requirements of the General Permit. - SWPPP must be prepared, submitted, and accepted
prior to any construction work, including
potholing. - Amend the SWPPP as required by the General
Permit. - Furnish, install, and maintain all erosion and
sediment control measures described in the
approved SWPPP. - Implement monitoring programs, record keeping,
maintenance, inspection, repair, training, and
sampling as required in the General Permit.
34Dewatering Discharge(Appendix C and Section
02140)
- Design, furnish, install, operate, monitor,
maintain and remove a temporary dewatering system
as required to lower and control water levels
below subgrades of excavations to permit
construction in the dry. - Collect and properly dispose of all discharge
water from the dewatering system in accordance
with California RWQCB NPDES Permit No. CAG994004,
CI-9469. - Allowable discharge points are shown on the
Drawings.Contractor may discharge into sotrm
drains that connect to these discharge points.
35Dewatering Discharge(Appendix C and Section
02140)
- Contractor shall submit to the Owner, within the
first 5 days of the month, the total volume of
water discharged during each day of the previous
month. - The Owner will take the samples required by
Permit No. CAG994004, CI-9469 and submit the
required reports to the RWQCB. The Owner will
notify the Contractor if his discharge fails to
comply with the permit requirements. - The Contractor shall take daily samples of the
discharge and analyze them in the field each day
for turbidity. Dewatering and treatment system
must maintain an average turbidity below 50 NTU.
36Additional Information Available
- Record Pipeline Information Appendix J contains
CD of record drawings and record pipeline layout
drawings for the portion of the 48 PVC to be
connected to and design drawings for the 30 WSP
be connected to. This information is provided as
a convenience to the Contractor only, and all
information contained therein shall be field
verified prior to pipe fabrication (SC 1-23). - Geotechnical Information Geotechnical reports
are available at www.calleguas.com/planholders.htm
, but are not a part of the Contract Documents
(SC 1-17).
37Mitigation Measures
- Mitigation monitoring plan can be found in
Appendix E. - Specific mitigation measures of interest include
- Archaeologist Orientation/Training (SC-28)
- Flat Blade Bucket Excavation (Section 02220)
- Noise and Vibration Control and Monitoring
(Section 01560)
38Buy American Provision(SC 1-42)
- When possible, the Contractor shall provide, use,
and install only iron, steel, and manufactured
goods produced in the United States in the Work.
More information on federal Buy American
requirements can be found at http//www.arnet.gov/
far/current/html/Subpart2025_1.htmlwp1118857
39Labor Compliance Program (SC 1-43 and Appendix
I)
- The Work is subject to the requirements of an
LCP. Calleguas has retained the services of a 3rd
party LCP administrator. The Contractor shall
cooperate fully with the administrator in
submitting information and cooperating with site
visits and other required LCP activity. - The Contractor shall post at the Site the contact
information for the administrator. - Calleguas reserves the right to withhold progress
and final payment on this project until all
appropriate certified payroll forms and related
LCP documents are submitted and found to be in
compliance.
40Labor Compliance Program(SC 1-43 and Appendix I)
- The following language is hereby inserted at the
end of Article 6.3.8 of the GCs (3) Any sums it
believe may be necessary in response to failure
to fully comply with LCP requirements for the
Work. - Only individuals who are legally able to work in
the US shall be employed for the Work. - As California prevailing wage statutes and
regulations are also applicable to the Work, the
more restrictive requirements will be applied. - Calleguas requires that certified payrolls be
submitted electronically via LCP Tracker or
similar electronic service designated by
Calleguas.
41Experience and Contractors License Requirements
(N-9)
42Experience and Contractors License Requirements
(N-9)
(a) The experience of a traffic control
subcontractor shall not substitute for or
supplement the Bidders traffic control
experience. The projects shall be those where
either the Contractor self-performed the traffic
control work or managed a subcontractor who
performed the traffic control work.
43Experience and Contractors License Requirements
(N-9)
(b) The experience of the proposed auger boring
or pipe ramming subcontractor (as appropriate)
may be substituted for the Bidders
experience. (c) The experience of the proposed
auger boring or pipe ramming subcontractors
superintendent (as appropriate) may be
substituted for the Bidders Superintendents
experience. (d) The Contractors (or
Subcontractors) experience shall match with the
trenchless installation method(s) he proposes to
use. If the Contractor only plans to use one
trenchless method, then he is only required to
submit experience on that method if he plans to
use both methods, experience on both methods must
be submitted.
44Experience and Contractors License Requirements
(N-9)
- All qualifying experience must have been obtained
in the past 15 years. - All qualifying experience must have been obtained
on projects which have been successfully
completed. - A single project may meet more than one of the
experience requirements. - The Superintendent must have acted as
Superintendent or Foreman on each project from
project start through project completion. - The Project Manager must have acted as Project
Manager on each project from project start
through project completion.
45Bid/Proposal Issues
- Proof of Authority for Signature
- Special Federal Provisions and Specifications
- Manufacturers and Suppliers Experience
Requirements - Information to be Submitted After the Bid
- Insurance Requirements
46Proof of Authority for Signature
- Have bid signed by appropriate signatories
(I-3). - Two signatures are required even if company
policy allows one. - Furnish a resolution or other evidence
demonstrating the authority of the Bidder to
submit the Bid and the authority of each person
executing the Contract, bonds and all other
documents and instruments (I-3). - Provide notarization for forms in bid proposal.
47Special Federal Provisions and Specifications
- Federal funding is being used for this project
- Federally Assisted Construction (N-14)
- Special Federal Provisions and Specifications
- Bid Proposal Forms
- Certification of Bidder Regarding Equal
Employment Opportunity - Certification by Proposed Subcontractor Regarding
Equal Employment Opportunity - Certification regarding Debarment, Suspension and
Other Responsibility matters Drug-free Workplace
Requirements and Lobbying
48Manufacturers and Suppliers Experience
Requirements (N-10)
- Manufacturer of the 48 WSP and fittings must
meet the following minimum requirements - The Pipe Manufacturer shall within the last 5
years have manufactured at least 10,000 feet of
48 or larger mortar lined and mortar coated WSP
in conformance with AWWA C200 and C205 and the
requirements similar to those in Section 02620 of
these Specifications. - All aspects of the pipe fabrication process must
be performed in the US. - Before a Contract is awarded, the Successful
Bidder must demonstrate that the Pipe
Manufacturer employs a CWI, certified in
accordance with AWS QC1, and a NDT technician and
operator qualified to a minimum of NDT Level II
in accordance with ASNT SNT-TC-1A.
49Information to be Submitted After the Bid
- Within 3 Working Days from bid opening, submit
Welded Steel Pipe Manufacturer Experience. - List the name of pipe fabricators and
manufacturers who will provide pipe materials and
fabrication for this project, and indicate their
compliance with requirements as specified in
Section N-10 of the NIB.
50Insurance Requirements
- Insurance documentation does not need to be
submitted with the bid - Workers Compensation and Employers Liability
Insurance Required of the Contractor (I-12) - Liability Insurance Required of the Contractor
(I-13) - Certificates and endorsements shall be submitted
for both the Successful Bidder and the
subcontractor(s) performing trenchless work
(I-10) - Coverage shall include railroads endorsement CG
24 17 or equivalent on the CGL policy (I-13) - Additional insureds listed in SC 1-25
51Questions
- For bidding RFI/RFC
- Use form in Appendix B and submit by June 23,
2009 at 5 pm - Send to
- Perliter IngalsbeAttention Rean David
Kunitake, P.E.Fax (626) 398-9115 - For planholders lists, geotech reports, this
presentation, bid results, etc. visit
http//www.calleguas.com/planholders.htm