Title: NPDES Permit Compliance Action Plan
1NPDES Permit Compliance Action Plan
- Presentation to the
- Galt City Council
- January 24, 2006
2This presentation is structured to outline our
recommended course of action for NPDES compliance.
- Background - Describe the 4 remaining NPDES
compliance options that received further study
under this phase of the project. - Recommendations - Present our recommended
compliance option and describe the factors that
support this recommendation. - Implementation - Recommended next steps, near
term and long-term. - Plan Adoption or Modification - Obtain City
Councils views and input.
3Four discharge/reuse alternatives for NPDES
compliance were evaluated under this phase of the
project.
- Option A Laguna Creek Seasonal Discharge with
Continued Reclamation - Option B Laguna Creek Year-Round Discharge
- Option C Sacramento River Discharge
- Option D Zero Discharge with Full Reclamation
4Option A is a Laguna Creek seasonal discharge
alternative.
5(No Transcript)
6TREATMENT WETLANDS
FILTERS
WWTP PROCESS SCHEMATIC FOR OPTION A (WINTER
OPERATION)
7Option B involves discharging to Laguna Creek on
a year-round basis.
8TREATMENT WETLANDS
FILTERS
NEED FOR/ADEQUACY OF WETLANDS IS DEPENDENT UPON
OUTCOME OF WATER QUALITY STUDIES, DILUTION
CREDIT, PILOT TESTING
WWTP PROCESS SCHEMATIC FOR OPTION B
9Option C is a Sacramento River discharge option
requiring construction of a 12 mile long pipeline
and river outfall facilities.
10Option D would eliminate effluent discharge
altogether through reuse and storage.
11Estimated capital costs and OM costs for each
option at 3 mgd
These costs are based on existing information and
assumptions, and are subject to change.
12Comparison of Capital Costs 3 mgd and 6 mgd
13Major Conclusions and Recommendations
- Option D, zero discharge with full reclamation,
is no longer considered a viable alternative. - Highest cost alternative
- Acquisition of property in the vicinity of the
WWTP - For 3 mgd, competing land interests complicate
acquisition - Beyond 3 mgd, remote sites are necessary,
substantially increasing costs - Current market value of reclaimed water is low
- Development of properties, and management/operatio
n of the system will be difficult and complex
Recommendation Eliminate Option D from the list
of alternatives.
14Key Decisions
- Option C Retain until NPDES permit is received
vs. Abandon in favor of Option A/B - Option A Retain until benefits of dilution are
known vs. Abandon in favor of Option B - Option B Pursue now and abandon Options A C
vs. Retain as the fallback option
15Major Conclusions and Recommendations
- Laguna Creek discharge (Options A and B) and
Sacramento River discharge (Option C) are
competitive, feasible alternatives. - Continuation of a Laguna Creek discharge is our
recommended implementation approach. - Despite distinct risks, the potential benefits
associated with a Sacramento River discharge are
attractive. - Council may want to consider preserving this
option while additional information is developed.
16The Laguna Creek option is preferred, in part,
because of the potential risks associated with
the Sacramento River discharge option.
- Permit requirements for a Sacramento River
discharge can only been estimated. The actual
requirements, and therefore the viability of this
option, are unknown until an NPDES permit is
obtained. - Public opposition to a new Sacramento River
discharge may surface during the CEQA process. - Potential future regulatory changes may
eventually nullify the key benefits of this
option. - Dilution is a critical element of this option.
Continuation of current policies regarding
dilution credits/mixing zones is not guaranteed
in the long run. - Possible future mass-based effluent limits (e.g.,
for mercury) are independent of dilution - Compliance with other possible future effluent
limits (e.g., pharmaceuticals) cannot be
predicted at this time.
17The Laguna Creek discharge option offers
distinct benefits that make this the preferred
alternative.
- There is very little risk that constructed
improvements will be throwaway if regulations
change. - This option provides flexibility to move from
Option A to Option B to create cost-effective
solutions as the project develops over time. - The ability to phase construction of improvements
allows costs to be effectively managed over time.
- Safety considerations favor this option.
- Discontinued use of chlorine disinfection.
- Eliminates safety concerns related to pipeline
maintenance.
18Major Conclusions and Recommendations
- There are potential risks/disadvantages
associated with a Laguna Creek discharge. - Requires significant additional treatment
processes over Option C (e.g., filtration, UV
disinfection) - Possible future effluent limits (e.g., salinity)
may be difficult to meet without advanced
treatment processes - Wetlands performance needs to be confirmed
through pilot testing additional or alternative
advanced treatment processes may ultimately be
needed - Dilution benefit decreases as effluent flow
increases
19Major Conclusions and Recommendations
- Council may wish to preserve the Sacramento River
discharge option - Lower cost for 6 mgd and beyond (given the
assumptions of this analysis) - Reduced risk of needing advanced treatment
processes (e.g., MF/RO) in the event of future
stringent water quality regulations - Impractical to delay implementation until the
Laguna Creek option proves unfavorable
20Key Decisions (revisited)
- Option C Retain until NPDES permit is received
vs. Abandon in favor of Option A/B - Option A Retain until benefits of dilution are
known vs. Abandon in favor of Option B - Option B Pursue now and abandon Options A C
vs. Retain as the fallback option
Recommendation Pursue Option A/B consider
preserving Option C until NPDES permit is
received
21Major Conclusions and Recommendations
- Irrespective of the selected option, an
integrated approach optimizes your ability to
achieve NPDES permit compliance.
Refine/Expand Effluent Water Quality Analyses
Pursue Dilution Credit, Negotiate NPDES Permit
Requirements
WWTP Improvements
Define Implement Wellhead Treatment for Arsenic
OR
Conduct Receiving Water Analyses
Submit RWD/NDPES Permit Application
Export Pipeline
Identify Implement Other Cost-Effective Source
Control Measures
Refine List of Problem Constituents
It will be imperative to coordinate with the
Regional Board on all of the activities listed
above.
22RECOMMENDED ACTION PLAN
23Recommended Action PlanImmediate Action Items
(2006-2008)
- Take action on Option C (if Council decides it is
warranted). - Conduct flow and water quality analyses for
Laguna Creek. - Begin pilot test of filtration system.
- Construct and test a pilot-scale treatment
wetlands to confirm performance. - Begin preliminary design of selected improvements
(filtration, UV disinfection) and final design of
solids processing improvements. - Use an integrated approach.
- Continue source control efforts.
- Refine sampling techniques and analytical
testing. - Develop water quality and flow analyses to
support NPDES permit negotiations.
24(No Transcript)
25If the Sacramento River option is preserved,
additional costs would be incurred to advance
this alternative.
26Recommended schedule for near-term projects
related to Options A and B.
27Recommended Action Plan Schedule
28(No Transcript)