Title: Programmatic Audit and Review PA
1(No Transcript)
2Module II - Knowledge
- Make Decision to Audit
- Conduct Program Discovery
- Understand Baseline SMA Requirements
3PAR Knowledge Steps
Module II
In this module, we will discuss the PAR Steps
that Initiate the PAR Process Develop Knowledge
of Program SMA Requirements
Remember this chart from the Introduction which
shows the Principal Steps of the PAR Process.
4Details of the PAR Process
Module II
- This module provides a detailed discussion of the
principal knowledge steps. The steps will be
depicted in a simplified flowchart as shown
below.
Decide
Discovery
Flow-down
Capability
Compliance
Understand Requirements
Feedback
Operational Readiness
Additionally, the step being discussed will be
highlighted, e.g., Flow-down.
5 P1 - Decide Make Decision to Audit
Module II
The Decide Process Step is the kick-off of the
PAR Process select what programs/ projects to
audit/review/assess, determine who should lead
the audit and define the initial scope of the
PAR.
- Program/Project Selection
- Select program/project for PAR
- By Risk-based Selection Logic
- By Request
- By Direction
- Determine if PAR will be led by Headquarters or
a Center - PAR Planning Workgroup
- PAR Initiation
- Designate PAR Audit/Review Lead
- Establish PAR Team
- Initiate contact with the program or project.
- Define preliminary scope and schedule.
- Draft PAR Initiation Letter for signature and
distribution.
6Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Risk/ Rule- Based Filter
MSD Filter
Preliminary Selection and Scoping
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- The above flowchart depicts the PAR Program
Selection for both Headquarters-led (upper flow)
and Center-led (lower flow) PARs. - The HQ-led PAR process will be discussed in
detail in the following slides. - NASA Centers have their own internal processes
for selection that may be - similar to the NASA HQ process.
- The PAR selection process for both HQ and
Centers comes together at the PAR - Planning Work Group
7Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Preliminary Selection and Scoping
Risk/ Rule- Based Filter
MSD Filter
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- The PAR Process begins with the collection and
analysis of program or project information from
Agency sources. - The step continues with the development of the
initial list of candidates for HQ-led PARs using
broad-based filters, reviews of previous audit
activities, and the OSMA insight into
programs/projects. The various filters are listed
on the next slide.
8Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Preliminary Selection and Scoping
Risk/ Rule- Based Filter
MSD Filter
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- Risk/Rule-Based Filter
- Human Safety
- Nuclear Safety
- Multi-Center
- Multi-National
- High Cost
- Center
- Mission Directorate
- Mishaps/Audits/Reviews
- Lifecycle phase
- MSD Filter
- Program/Project Insight
- Contacts with program/project SMA management
- Contacts with Center SMA management
- Contacts with Mission Directorate management
- RAD Filter
- Previous RAD audit activities
- Other independent audit/review activities
9Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Preliminary Selection and Scoping
Risk/ Rule- Based Filter
MSD Filter
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- Using a standard template, each center and HQ
develop and revise, as appropriate, their PAR
activities. - Selection and schedule primarily based on the
PAR risk-informed analysis/ranking. - Additional candidates may be identified by
request from an entity within NASA (e.g., NASA
Administrator, Mission Directorate AA, Chief,
SMA, etc.) or by direction from a higher
authority external to NASA (e.g., GAO, Congress,
etc.).
10Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Preliminary Selection and Scoping
Risk/ Rule- Based Filter
MSD Filter
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- The PAR Planning Workgroup (PWG) is chartered to
plan, coordinate, and fully integrate Agency-wide
PAR activities. The current status of the PAR
activities is presented at the annual PWG
meeting. - The RAD PAR Manager formally develops/presents a
list of potential HQ-led PAR candidates. - Each PWG Center Representative identifies current
or planned PARs for their respective Center.
These lists contain justification for performing
the PAR, preliminary scoping, and the name of
the proposed PAR Lead. - HQ and Center PAR candidates are discussed as to
their merit for inclusion/deletion/ combination
into the proposed integrated list.
11Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Preliminary Selection and Scoping
Risk/ Rule- Based Filter
MSD Filter
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- Candidate List Presented to Chief, SMA
- The proposed lists of programs and projects
developed by the PWG are presented to the Chief,
SMA for approval (Headquarters-led PAR) and
information (Center-led PAR). - A rough order of magnitude (ROM) estimate of the
resources (and their source) to perform the PAR
is also provided. - Once approved, the integrated schedule is made
available via the web-based PBMA-KMS for agency
wide access.
12Program Selection
Module II
HQ-led List
Chief, SMA Approval
HQ-led Plan
Analysis
PAR Planning Workgroup
Preliminary Selection and Scoping
Risk/ Rule- Based Filter
MSD Filter
RAD Filter
Program/ Project Information Sources
Center-led List
Chief, SMA Info
Integrated Schedule
START
Center-led Plans
Center SMA Planning
- By coordinating and maintaining an annual,
integrated risk-informed PAR schedule - Programs and centers can improve resource
planning - Overlapping and redundant efforts can be
reduced - PAR impact on program/project schedules is
minimized
13PAR Initiation
Module II
Approval
Select PAR Audit/Review Lead
Select PAR Team
Propose PAR Scope and Schedule
Draft PAR Initiation Letter
Distribute
- PAR Manager (for Headquarters-led) or the Center
SMA Director (for Center-led) selects the PAR
Lead, who will have the overall responsibility
for the successful execution of the PAR. - PAR Lead recruits appropriate personnel to serve
on the PAR Team to perform specific PAR
activities, as scoped. Team may consist of both
civil servants and/or support service
contractors.
14PAR Initiation
Module II
Approval
Select PAR Audit/Review Lead
Select PAR Team
Propose PAR Scope and Schedule
Draft PAR Initiation Letter
Distribute
- The PAR Team meets and drafts a plan (scope) for
conducting the PAR. Scoping contains the
following elements - 1st Order Which step or steps will be performed
(e.g., Program Discovery, Understand
Requirements, Requirements Flow-down
Verification, Process Capability Assessment,
On-site Audit) - 2nd Order Organizational level (e.g., program,
project, prime, first-tier subs, second-tier
subs) - 3rd Order Requirement/Process Scope (e.g.,
sample vs. total requirements set, selected
processes) - 4th Order Audit Depth
- Simple analysis yes/no checklist format
- Complex analysis - quality assessment of plan
- The following slides provide a notional scoping
matrix that can be used to formally document the
scoping process and examples of simple vs.
complex.
15Notional Scoping Matrix
Module II
Resource and time constraints require careful
audit/review scope definition to maximize return
on investment.
16Simple vs. Complex Analysis
Module II
17PAR Initiation
Module II
Approval
Select PAR Audit/Review Lead
Select PAR Team
Propose PAR Scope and Schedule
Draft PAR Initiation Letter
Distribute
- The PAR Initiation Letter is the formal
notification to the program or project that the
PAR will be conducted. It contains the PAR
plan, including the preliminary scope and
schedule of the PAR. The letter also identifies
the PAR Lead. - Chief, SMA or Center SMA Director approves scope
and Initiation Letter. - The PAR Initiation Letter is then distributed to
appropriate Program, Project, and SMA personnel.
After the letter is distributed, scoping is
finalized through detailed discussion with the
program or project.
18P2 - Conduct Program Discovery
Module II
The Discovery Process Step has a two-fold
purpose Educate the PAR Team and instill
confidence in the Project/Program of the PAR
team knowledge and the credibility of results.
- Characterize Program
- Provide Context for PAR
- Documentation Review
- Interviews
- Technical Interchange Meetings
- Briefly summarize program or project
(program/projects mission, objectives, goals,
background, and SMA processes) to ensure PAR
Team is prepared - Describe SMA Roles, Responsibilities and
Relationships - Review existing Program/Project developed SMA
process map and matrix, if available - Assist in the development of Map and Matrix
19Characterize Program
Module II
Example using X-37
Data Sources RFP Interviews Proposal Public
Information Program Office Etc.
- PAR Team gathers information from
- Center SMA, Program, Project, and
- Contractor via document review and
- TIMS
- Amount and level of detail of
- information is directly dependent on
- the scope of the PAR and the
- criticality and complexity of program/
- project under review.
Information To Provide Overall Program/Project
Context
Program Selection
By conducting this step, the PAR team gains
knowledge and the program/project gains
confidence in the capability of the PAR team and
credibility of the results of the process.
20Describe SMA Roles, Responsibilities and
Relationships
Module II
- Ideally, program/projects have already developed
SMA process maps and matrices as required by NPR
7120.5D and NPR 8705.6 and have provided this key
source of information as part of the
Characterization step. However, if the
map/matrix has not been developed, the PAR team
may require and assist in their development. - SMA Process Analysis results in an SMA process
map and matrix that provide a concise graphical
and narrative representation of the safety and
mission assurance roles, responsibilities, and
relationships for assurance agents supporting
safety and risk management within a given program
or project. - The creation and maintenance of the SMA Process
Map and Matrix is the responsibility of the
program or project. Because this is a new tool,
OSMA RAD will support program or project SMA in
creating the document. - The following slides show an example of an SMA
process map and matrix. For more detailed
information on the SMA Process Analysis please
refer to the AP Map Survival Kit found on PBMA at
- http//pbma.nasa.gov/apmaps_main_cid_568
21Describe SMA Roles, Responsibilities and
Relationships
Module II
SMA Process Map
- The program or project develops a baseline SMA
Process Map using SMA organizational charts,
program organizational charts, and other
information gained through technical interchange
meetings and interviews with Center and program
SMA organizations, coupled with any other
relevant information discovered during the
Characterize Program step.
22Describe SMA Roles, Responsibilities and
Relationships
Module II
This is a representative page of an SMA Process
Matrix
23Describe SMA Roles, Responsibilities and
Relationships
Module II
Ideally, the SMA Process Map and Matrix should
be developed early in the program/project and
used as a management tool The SMA
Process Map and Matrix should be updated
throughout the program/project lifecycle
The Map and Matrix are required inputs to the
Safety and Mission Success Review (SMSR)
Identify Accountable Organizations
Notional Mission Assurance Process Map
Identify Organization Roles and Points of Contact
Notional Mission Assurance Process Matrix
24 P3 - Understand Baseline SMA
Requirements
Module II
A meaningful review, assessment, or audit of a
program or project requires a thorough
understanding of the BRS.
- Analyze Baseline Requirements Set (BRS)
- Principal purpose of this step is to simply
document the existing BRS for the project/program
to be used throughout the PAR process. - As appropriate, perform a requirements gap
analysis of the programs BRS, all applicable
Agency SMA requirements, and accepted best
practices. Document gaps and assess/document
residual risks
25 Analyze Baseline Requirements
Set (BRS)
Module II
The PAR Team works with program/project SMA and
the Office of the Chief Engineer (OCE), OSMA
Mission Support Division and Safety and Assurance
Requirements Division (or the Center equivalent
organization for a Center-led PAR) to develop a
complete list of the Agency-level SMA
requirements documents that are imposed on the
program or project (the BRS) and SMA requirements
that should be on the program or project. The
PAR Team also uses Agency knowledge management
resources to assemble a list of best practices
and lessons learned that are relevant to the
program or project.
26 Analyze Baseline Requirements
Set (BRS)
Module II
If deemed appropriate, a Gap Analysis can be
performed as a series of traceability
assessments. The initial traceability
assessment compares the program-applicable Agency
SMA requirements set to the contractual
requirements set. This analysis identifies those
program-specific Agency requirements not
traceable to the program/project contractual
requirements (e.g., those requirements
negotiated-out or subject to subsequent Agency
SMA requirements revisions, additions, or
deletions). Additionally, the PAR Team can
perform a requirements gap analysis between the
existing set of program contractual SMA
requirements, any program-applicable Agency SMA
requirements, and a set of accepted engineering
best practices.
27 Analyze Baseline Requirements
Set (BRS)
Module II
The untraceable requirements from the Gap
Analysis represent a delta requirements set.
Requirements in the delta requirements set are
then prioritized by their potential increased
risk to safety and mission success. The output
of the traceability assessments is a SMA
requirements risk assessment that is used to
inform the PAR Team as the PAR Process proceeds
and to provide the Program, Project, Center,
Mission Directorate, Chief, SMA and the Chief
Engineer with feedback as to the
program/projects SMA requirements status
28 Analyze Baseline Requirements
Set (BRS)
Module II
- In summary, the gap analysis identifies missing,
redundant, or new/revised requirements resulting
in - Feedback to MSD (process step P7) or equivalent
Center organization for inclusion of missing - requirements based on negotiation with
Program Management - Feedback to SARD (process step P7) suggesting
improvements to be included in Agency - SMA Requirements Set
- Identification of any residual risks related to
gaps