Title: CPETECET 470 Technology Project Management
1CPET/ECET 470Technology Project Management
2Course Topics
- Focus
- Understanding project planning and control
- Specific Topics
- Planning
- Definition of Work
- Scheduling
- Budgets
- Measuring Progress/Controlling Cost
- Easy to do
- Your role in the process
- Risk Management
- Risk Evaluation
- Risk Mitigation
3Stages of Planning
Define Ultimate Goal
Construct Statement of Work
Define Work Breakdown Structure
Create Summary Level Schedule
Create Detailed Schedule
Define Budgets
4Budget
- Setting the budget is the last stage of planning
- If project funding exceeds the resources defined
in the baseline plan, the difference is held as
reserve funding - Budget constraints sometimes conflict with the
desired efforts - Management will issue challenges to improve
efficiencies to reduce anticipated project
expenses - Management will constrain efforts to hold reserve
funding wherever possible - Remember the objectives Meet contractual
requirements, keep the customer happy and make
money for your company
5EVM Teaching Objectives
- Provide Basic Understanding of Earned Value
Management (EVM) - Learn basic EVM terminology
- Understand the practicality of using EVM
6Earned Value
- An Objective Measure of How Much Work
- Has Been Accomplished Based on the Planned
Value.....
What We Got for What We Spent!
7Management Systems Without EVM
8What Is Earned Value Management?
- Earned Value Management (EVM) is a process for
measuring actual performance against a plan to
identify and correct problem areas before control
is lost
Plan
Execute (each month)
Measure (each month)
Evaluate
Respond
All the steps work together as an integral part
of program performance
9Why Does a Company Use EVM?
- Provides timely feedback to allow cost account
managers to control cost, schedule and technical
performance - Provides summarization to allow management and
customers to manage cost, schedule and technical
objectives - Integrates Work Scope, Schedule and Cost
Objectives Into a Baseline Plan Against Which
Accomplishments Can Be Measured - Indicates Work Progress
- Relates Cost, Schedule and Technical Performance
- Objectively Assess Accomplishments at the
Performance Level - Is Valid, Timely, and Auditable
- Analyzes Significant Variances From the Plan and
Forecast Impacts - Supplies Managers With a Practical Level of
Summarization
10Why Should You Use EVM?
- EVM Enhances the Overall Opportunity of an
Activity to Succeed - Allows you to objectively evaluate if your
efforts are on schedule - Allows you to objectively evaluate if your
efficiency meets your plan - Helps you identify holes in the plan
- Provides you an opportunity to understand/correct
problems before they are a concern to your
management/customer
11EVM Dependence on Teamwork
- EVM Requires Task Level Management
- Involves the whole team
- Not just the Program Manager and Project Engineer
monitoring progress - EVM Effort Crosses Departmental Lines
- Engineers
- Program Managers
- Business Managers
- Subcontractors
- Etc.
- Objective EVM Requires Open, Honest Communication
12EVM Terminology
13Earned Value Myth
Ive spent 400 hours, so Ive accomplished 400
hours of work. Right?
- Actual cost is not an indication of work progress
- It is only an indicator of hours/money spent
14General Terms
- Work Package (WP)
- Detailed, short-span tasks required to accomplish
project objectives - Has clear, measurable start and finish criteria
- WPs are summed into Cost Accounts
- Cost Account (CA)
- Sometimes referred to as a Control Account
- A single chargeable account
- Has clear, measurable start and finish criteria
- Amounts to a finite piece of the program
15General Terms
- Cost Account Manager (CAM)
- Person assigned to manage, control and report on
the activity within a particular CA - Work Authorization Document (WAD)
- Contract between the CAM and the Program Office
to accomplish a clearly defined scope of work
within a clearly defined schedule and budget - Basis of Estimate (BoE)
- Description of why a task requires the defined
resource hours
16General Terms
- Work Breakdown Structure (WBS)
- Organizes and defines the elements of work to be
performed on a contract - WBS Dictionary
- A document, organized as defined by the WBS, that
provides product oriented descriptions for each
element of the WBS - Resource/Function Codes
- Business Management coding for each type of labor
category
17Planning Terms
- Budgeted Cost of Work Scheduled (BCWS)
- The plan for what will be spent and when it will
be spent - Planned on fiscal month intervals
- Program Baseline
- Frozen BCWS after completion of planning
- Ideally, freezing occurs within 30 days of
contract award - Baseline at Completion (BAC)
- BWCS value at the end of the program as frozen in
the program baseline
18Planning Terms
- Budgeted Cost of Work Performed (BCWP)
- The value of work accomplished relative to the
plan - Progress relative to the plan
- This term is the Earned Value (EV)
- If I am 50 done with a task worth 1,000 then I
get 500 of earned value in BCWP - Actual Cost of Work Performed (ACWP)
- Costs incurred monthly
- What was spent
- Actuals
19Planning Terms
- Management Reserve (MR)
- Contract funding held for management control
purposes - Only allocable to fund unanticipated scope
- Earned Value Method
- The objective criteria for claiming earned value
within a WP or CA - Planning Package
- Future CA that is not detail planned into work
packages - Planning Packages are converted to CAs and WPs
four (4) to six (6) months prior to the start of
the work
20Earned Value Myth
My budget for this task is exhausted. Can I
have some Management Reserve to cover my overrun?
- Management Reserve Cannot be used to cover
- Budget Overruns
21Performance Terms
- Schedule Variance (SV)
- Difference between the earned value and the plan
- Are you ahead or behind schedule?
- Earned value - plan schedule variance
- BCWP - BCWS SV
- Cost Variance (CV)
- Difference between the earned value and actuals
- Are you overrun or underrun?
- Earned value - actuals cost variance
- BCWP - ACWP CV
22Performance Terms
- Cost Performance Index (CPI)
- Provides a single number that defines the
efficiency of use for a Cost Accounts budget - Are you overrun or underrun?
- Earned value divided by the actuals equals the
cost performance - BCWP / ACWP CPI
- Why not just use CV?
- As a manager, what do I know quantitatively from
an CV -1,000? - Answer Not much - because the CV shows no
insight to the amount spent - If the ACWP 4,000 then there is a really large
problem - If the ACWP 100,000 then there isnt much of a
problem - What is the CPI in both these cases?
23Performance Terms
- Schedule Performance Index (SPI)
- Provides a single number that defines the
relative health of a Cost Accounts schedule - Are you ahead or behind schedule?
- Earned value divided by the plan equals the
schedule performance - BCWP / BCWS SPI
- Why not just use SV?
- As a manager, what do I know quantitatively from
an SV -1,000? - Answer Not much - because the SV provides no
insight to the size of the account - If the BCWS 2,000 then there is a really large
problem - If the BCWS 50,000 then there isnt much of a
problem - What is the SPI in both these cases?
24Updating Terms
- Estimate to Complete (ETC)
- A bottoms-up cost estimate of the remaining work
- Estimate At Completion (EAC)
- Cost of the work performed plus the ETC
- ACWP ETC EAC
- Identical to Latest Revised Estimate
- Latest Revised Estimate (LRE)
- Cost of the work performed plus the ETC
- ACWP ETC LRE
- Identical to EAC
- EAC LRE
25Updating Terms
- Variance At Completion (VAC)
- The difference between your budget and your
projected final cost - BAC - EAC VAC
26Elements of EVM
Now
Contract Value
Contract Complete
Contract Start
27Variance Terms
- Variance Analysis Report (VAR)
- Form that the CAM completes to describe a
variance and projected future state of a cost
account - Program Thresholds
- Trigger levels where particular items, such as
VARs or ETCs are required for a particular
program - Scope Growth
- Work required in a cost account beyond the scope
defined in the WAD for that account - Work defined for a program beyond the scope of
any cost account
28Variance Terms
- Baseline Change Request (BCR)
- Form used by a CAM to request modification of a
cost account contract - BCRs are used for
- Defining a change in the scope of a cost account
- Defining a change in the schedule for performance
of activity within a cost account - Defining a change in the cost for performance of
activity within a cost account - BCRs are used prior to the start of work in a
cost account - Exception When changes are driven by program
level contract changes, A BCR can occur after the
start of effort in a cost account
29To Complete Performance Index (TCPI)
- The CPI required for the performance of remaining
work to meet the budget - The remaining work divided by the estimate to
complete equals the To Complete Performance Index - (BAC - BCWP) / (EAC - ACWP) TCPI
- How Is TCPI Calculated at Program Start (Prior to
Performance of an ETC)? - EAC BAC at program start
- TCPI, compared to current CPI, will indicate
the realism of an EAC
30TCPI Example 1
- A cost account has the following present
characteristics - BAC 10K BCWS 5K BCWP 4K ACWP
4.5K - So, CPI 0.89
- The remaining work (BAC - BCWP) 6K
- And, the remaining budget (BAC - ACWP) 5.5K
- Making TCPI 6000 / 5500 1.09
31TCPI Example 2
- Upon completion of your analysis of example 1,
you recognize there is a problem and perform an
ETC - Two months later you have the following
information on the same cost account - EAC 12K BCWS 10K BCWP 9K ACWP
9.5K - What is the TCPI now?
- What can you conclude about the state of the
account? - Do you think the CAM adjusted the process at all?
32Class 4 Assignment
- Answer questions 12-5, 12-6, 12-13 through 12-16,
15-15 and 15-17 - Due Monday
- Use Microsoft Project to assist you in providing
answers if you want (good practice to learn the
software) - Read paragraphs 15.4 15.5