CPETECET 470 Technology Project Management - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

CPETECET 470 Technology Project Management

Description:

Are you overrun or underrun? Earned value - actuals = cost ... Are you overrun or underrun? Earned value divided by the actuals equals the cost performance ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 33
Provided by: bryanbo
Category:

less

Transcript and Presenter's Notes

Title: CPETECET 470 Technology Project Management


1
CPET/ECET 470Technology Project Management
  • Class 4 - Budget Control

2
Course Topics
  • Focus
  • Understanding project planning and control
  • Specific Topics
  • Planning
  • Definition of Work
  • Scheduling
  • Budgets
  • Measuring Progress/Controlling Cost
  • Easy to do
  • Your role in the process
  • Risk Management
  • Risk Evaluation
  • Risk Mitigation

3
Stages of Planning
Define Ultimate Goal
Construct Statement of Work
Define Work Breakdown Structure
Create Summary Level Schedule
Create Detailed Schedule
Define Budgets
4
Budget
  • Setting the budget is the last stage of planning
  • If project funding exceeds the resources defined
    in the baseline plan, the difference is held as
    reserve funding
  • Budget constraints sometimes conflict with the
    desired efforts
  • Management will issue challenges to improve
    efficiencies to reduce anticipated project
    expenses
  • Management will constrain efforts to hold reserve
    funding wherever possible
  • Remember the objectives Meet contractual
    requirements, keep the customer happy and make
    money for your company

5
EVM Teaching Objectives
  • Provide Basic Understanding of Earned Value
    Management (EVM)
  • Learn basic EVM terminology
  • Understand the practicality of using EVM

6
Earned Value
  • An Objective Measure of How Much Work
  • Has Been Accomplished Based on the Planned
    Value.....

What We Got for What We Spent!
7
Management Systems Without EVM
8
What Is Earned Value Management?
  • Earned Value Management (EVM) is a process for
    measuring actual performance against a plan to
    identify and correct problem areas before control
    is lost

Plan
Execute (each month)
Measure (each month)
Evaluate
Respond
All the steps work together as an integral part
of program performance
9
Why Does a Company Use EVM?
  • Provides timely feedback to allow cost account
    managers to control cost, schedule and technical
    performance
  • Provides summarization to allow management and
    customers to manage cost, schedule and technical
    objectives
  • Integrates Work Scope, Schedule and Cost
    Objectives Into a Baseline Plan Against Which
    Accomplishments Can Be Measured
  • Indicates Work Progress
  • Relates Cost, Schedule and Technical Performance
  • Objectively Assess Accomplishments at the
    Performance Level
  • Is Valid, Timely, and Auditable
  • Analyzes Significant Variances From the Plan and
    Forecast Impacts
  • Supplies Managers With a Practical Level of
    Summarization

10
Why Should You Use EVM?
  • EVM Enhances the Overall Opportunity of an
    Activity to Succeed
  • Allows you to objectively evaluate if your
    efforts are on schedule
  • Allows you to objectively evaluate if your
    efficiency meets your plan
  • Helps you identify holes in the plan
  • Provides you an opportunity to understand/correct
    problems before they are a concern to your
    management/customer

11
EVM Dependence on Teamwork
  • EVM Requires Task Level Management
  • Involves the whole team
  • Not just the Program Manager and Project Engineer
    monitoring progress
  • EVM Effort Crosses Departmental Lines
  • Engineers
  • Program Managers
  • Business Managers
  • Subcontractors
  • Etc.
  • Objective EVM Requires Open, Honest Communication

12
EVM Terminology
13
Earned Value Myth
Ive spent 400 hours, so Ive accomplished 400
hours of work. Right?
  • Actual cost is not an indication of work progress
  • It is only an indicator of hours/money spent

14
General Terms
  • Work Package (WP)
  • Detailed, short-span tasks required to accomplish
    project objectives
  • Has clear, measurable start and finish criteria
  • WPs are summed into Cost Accounts
  • Cost Account (CA)
  • Sometimes referred to as a Control Account
  • A single chargeable account
  • Has clear, measurable start and finish criteria
  • Amounts to a finite piece of the program

15
General Terms
  • Cost Account Manager (CAM)
  • Person assigned to manage, control and report on
    the activity within a particular CA
  • Work Authorization Document (WAD)
  • Contract between the CAM and the Program Office
    to accomplish a clearly defined scope of work
    within a clearly defined schedule and budget
  • Basis of Estimate (BoE)
  • Description of why a task requires the defined
    resource hours

16
General Terms
  • Work Breakdown Structure (WBS)
  • Organizes and defines the elements of work to be
    performed on a contract
  • WBS Dictionary
  • A document, organized as defined by the WBS, that
    provides product oriented descriptions for each
    element of the WBS
  • Resource/Function Codes
  • Business Management coding for each type of labor
    category

17
Planning Terms
  • Budgeted Cost of Work Scheduled (BCWS)
  • The plan for what will be spent and when it will
    be spent
  • Planned on fiscal month intervals
  • Program Baseline
  • Frozen BCWS after completion of planning
  • Ideally, freezing occurs within 30 days of
    contract award
  • Baseline at Completion (BAC)
  • BWCS value at the end of the program as frozen in
    the program baseline

18
Planning Terms
  • Budgeted Cost of Work Performed (BCWP)
  • The value of work accomplished relative to the
    plan
  • Progress relative to the plan
  • This term is the Earned Value (EV)
  • If I am 50 done with a task worth 1,000 then I
    get 500 of earned value in BCWP
  • Actual Cost of Work Performed (ACWP)
  • Costs incurred monthly
  • What was spent
  • Actuals

19
Planning Terms
  • Management Reserve (MR)
  • Contract funding held for management control
    purposes
  • Only allocable to fund unanticipated scope
  • Earned Value Method
  • The objective criteria for claiming earned value
    within a WP or CA
  • Planning Package
  • Future CA that is not detail planned into work
    packages
  • Planning Packages are converted to CAs and WPs
    four (4) to six (6) months prior to the start of
    the work

20
Earned Value Myth
My budget for this task is exhausted. Can I
have some Management Reserve to cover my overrun?
  • Management Reserve Cannot be used to cover
  • Budget Overruns

21
Performance Terms
  • Schedule Variance (SV)
  • Difference between the earned value and the plan
  • Are you ahead or behind schedule?
  • Earned value - plan schedule variance
  • BCWP - BCWS SV
  • Cost Variance (CV)
  • Difference between the earned value and actuals
  • Are you overrun or underrun?
  • Earned value - actuals cost variance
  • BCWP - ACWP CV

22
Performance Terms
  • Cost Performance Index (CPI)
  • Provides a single number that defines the
    efficiency of use for a Cost Accounts budget
  • Are you overrun or underrun?
  • Earned value divided by the actuals equals the
    cost performance
  • BCWP / ACWP CPI
  • Why not just use CV?
  • As a manager, what do I know quantitatively from
    an CV -1,000?
  • Answer Not much - because the CV shows no
    insight to the amount spent
  • If the ACWP 4,000 then there is a really large
    problem
  • If the ACWP 100,000 then there isnt much of a
    problem
  • What is the CPI in both these cases?

23
Performance Terms
  • Schedule Performance Index (SPI)
  • Provides a single number that defines the
    relative health of a Cost Accounts schedule
  • Are you ahead or behind schedule?
  • Earned value divided by the plan equals the
    schedule performance
  • BCWP / BCWS SPI
  • Why not just use SV?
  • As a manager, what do I know quantitatively from
    an SV -1,000?
  • Answer Not much - because the SV provides no
    insight to the size of the account
  • If the BCWS 2,000 then there is a really large
    problem
  • If the BCWS 50,000 then there isnt much of a
    problem
  • What is the SPI in both these cases?

24
Updating Terms
  • Estimate to Complete (ETC)
  • A bottoms-up cost estimate of the remaining work
  • Estimate At Completion (EAC)
  • Cost of the work performed plus the ETC
  • ACWP ETC EAC
  • Identical to Latest Revised Estimate
  • Latest Revised Estimate (LRE)
  • Cost of the work performed plus the ETC
  • ACWP ETC LRE
  • Identical to EAC
  • EAC LRE

25
Updating Terms
  • Variance At Completion (VAC)
  • The difference between your budget and your
    projected final cost
  • BAC - EAC VAC

26
Elements of EVM
Now
Contract Value
Contract Complete
Contract Start
27
Variance Terms
  • Variance Analysis Report (VAR)
  • Form that the CAM completes to describe a
    variance and projected future state of a cost
    account
  • Program Thresholds
  • Trigger levels where particular items, such as
    VARs or ETCs are required for a particular
    program
  • Scope Growth
  • Work required in a cost account beyond the scope
    defined in the WAD for that account
  • Work defined for a program beyond the scope of
    any cost account

28
Variance Terms
  • Baseline Change Request (BCR)
  • Form used by a CAM to request modification of a
    cost account contract
  • BCRs are used for
  • Defining a change in the scope of a cost account
  • Defining a change in the schedule for performance
    of activity within a cost account
  • Defining a change in the cost for performance of
    activity within a cost account
  • BCRs are used prior to the start of work in a
    cost account
  • Exception When changes are driven by program
    level contract changes, A BCR can occur after the
    start of effort in a cost account

29
To Complete Performance Index (TCPI)
  • The CPI required for the performance of remaining
    work to meet the budget
  • The remaining work divided by the estimate to
    complete equals the To Complete Performance Index
  • (BAC - BCWP) / (EAC - ACWP) TCPI
  • How Is TCPI Calculated at Program Start (Prior to
    Performance of an ETC)?
  • EAC BAC at program start
  • TCPI, compared to current CPI, will indicate
    the realism of an EAC

30
TCPI Example 1
  • A cost account has the following present
    characteristics
  • BAC 10K BCWS 5K BCWP 4K ACWP
    4.5K
  • So, CPI 0.89
  • The remaining work (BAC - BCWP) 6K
  • And, the remaining budget (BAC - ACWP) 5.5K
  • Making TCPI 6000 / 5500 1.09

31
TCPI Example 2
  • Upon completion of your analysis of example 1,
    you recognize there is a problem and perform an
    ETC
  • Two months later you have the following
    information on the same cost account
  • EAC 12K BCWS 10K BCWP 9K ACWP
    9.5K
  • What is the TCPI now?
  • What can you conclude about the state of the
    account?
  • Do you think the CAM adjusted the process at all?

32
Class 4 Assignment
  • Answer questions 12-5, 12-6, 12-13 through 12-16,
    15-15 and 15-17
  • Due Monday
  • Use Microsoft Project to assist you in providing
    answers if you want (good practice to learn the
    software)
  • Read paragraphs 15.4 15.5
Write a Comment
User Comments (0)
About PowerShow.com