CPETECET 470 Technology Project Management - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

CPETECET 470 Technology Project Management

Description:

CPET/ECET 470 - Spring 2005. CPET/ECET 470. Technology Project Management ... Define an equation that you will use to remove subjectiveness ... – PowerPoint PPT presentation

Number of Views:37
Avg rating:3.0/5.0
Slides: 23
Provided by: bryanbo
Category:

less

Transcript and Presenter's Notes

Title: CPETECET 470 Technology Project Management


1
CPET/ECET 470Technology Project Management
  • Class 5 Variances Estimate to Complete

2
Decoding Variance
  • Negative Variances Are Always Unfavorable
  • Behind Schedule
  • Overrun
  • Positive Variances Are Better
  • Ahead of Schedule
  • Underrun
  • NO VARIANCE IS BEST!
  • All Variances Which Exceed Threshold Must Be
    Explained, Whether Favorable or Unfavorable

3
Variance Analysis Questions
  • Behind Schedule
  • How Critical Is Schedule?
  • Can I Afford to Work Overtime to Recover?
  • Can I Do Tasks Concurrently?
  • Are There Technical Innovations Which Could Speed
    up the Process?
  • Am I Driving to Over Spec?
  • Over Cost
  • Can I Reschedule Tasks? (Timephasing)
  • Is There a Less Costly Facility I Can Use?
  • Are There Tasks Which Can Be Deleted?

4
Variance Analysis Check List
  • CAUSE Answer the question WHY?
  • Did I discuss CV and SV separately?
  • Did I clearly identify the reason?
  • Did I isolate significant labor rate variances?
  • Did I place emphasis on the Quantitative?
  • Did I place emphasis on the Specific?
  • IMPACT Answer the question WHAT?
  • Did I describe impact on the cost account, other
    cost accounts, and/or the project?
  • Did I address intermediate schedules?
  • Did I address Predecessors Successors?
  • Did I assess the need to revise the EAC?
  • Did I place emphasis on the Specific?

5
Variance Analysis Check List
  • CORRECTIVE ACTION Answer the question HOW?
  • Did I describe the specific actions taken or
    being taken?
  • Did I include the individual or organization
    responsible for the action?
  • Did I include schedules and get well dates?
  • Did I include results of previous corrective
    action plans?
  • If no corrective action is possible, did I
    explain why

6
When To Do an ETC
  • Full Bottom-Up ETC is Generated for the Program
    Semi-Annually
  • Basic rule-of-thumb Generate an ETC for a Cost
    Account When Either of the Following Conditions
    Are Met
  • BCWP 50 of BAC
  • ACWP 90 of EAC

7
CAM Responsibilities
Cost Account Managers Dont Just Monitor
Status, They Manage the Work !!!
8
CAM Notebook
  • Should Contain at a Minimum
  • Work Authorization Document (WAD)
  • Original Baseline Schedule (Gantt or PERT)
  • Original Baseline Task Usage Report
  • Original Baseline Resource Usage Report
  • Original Budget Baseline Report
  • Latest Cumulative Earned Value Report
  • Latest Actuals Report
  • Most Recent Variance Analysis Report
  • All Completed Budget Change Requests
  • Latest Budget Baseline Report

9
CAM Notebook
  • Suggest the Following Be Included
  • Labor Transfer Sheets
  • Last Few Months of Data
  • BCRs in Process
  • Special Shop Orders
  • Any Special Reports the CAM Generates for His/Her
    Own Use In
  • Determining BCWP
  • Supporting Budget Data
  • Explaining Variances
  • Subcontract Status Reports
  • CSSR CFSR
  • Tracking to MPM system

Maintain the Notebook as a TOOL
10
WAD Purpose
  • A WAD is a contract between the CAM and the
    Program Office for the scope of work, including
    budget, completion dates and technical
    performance
  • For efforts outside of the scope of work, the CAM
    must request additional authorization PRIOR to
    executing work
  • A WAD should include the following at a minimum
  • Definition of work to be performed
  • Assumptions for performing work
  • Deliverable products resulting from effort
  • Exit Criteria for completion of effort
  • A WAD may include the following additional
    information
  • Associated work that is EXCLUDED from this SOW
  • Representative functional efforts contained
    within this effort (I.e. design, supervision, QA,
    touch labor, test, equipment, etc.)

11
Earned Value Methods
  • Discrete Effort - Specific End Product or Result
  • Milestone method
  • Start/Finish method 0/100, 25/75, 50/50, 75/25,
    etc.
  • Percent complete method
  • Apportioned Effort
  • Factored effort directly related to discrete
    tasks (ie-inspection)
  • Dependent on other work ( of BCWP of another
    task)
  • Level of Effort
  • No final product or result (ie - program
    management)
  • Measure performance with the passage of time
  • Each month BCWP is set to equal BCWS

12
EV Method - Level of Effort
  • Activities Which Are Time-Based Rather Than
    Task-Based
  • Program Management
  • Scheduling / Cost Management
  • Security
  • Contract Administration
  • Project Engineering
  • Generally Continue for the Life of the Project,
    But Have No Measurable Outputs
  • Work Performed Is Assumed to Always Equal to Work
    Scheduled
  • Therefore There Is Never a Schedule Variance

13
Discrete EV Method Selection
  • Milestone Method
  • Used for CAs where there is limited visibility
    into the specific tasks being performed, but
    discrete items that will be completed as the work
    is performed
  • Good for
  • CDRLs
  • PWB layouts
  • etc.
  • Percent Complete Method
  • Least objective of the three choices
  • Define an equation that you will use to remove
    subjectiveness
  • Least preferred most time consuming method

14
Discrete EV Method Selection
  • Start/Finish Method
  • Most common method - works for all tasks that
    have clear completion criteria
  • What percentages are best?
  • Depends on the task resource loading and
    management preference
  • Each method has some error for an in-process task
  • Example Task - Software Coding
  • Preferred method 50/50
  • Why? Software coding is most likely a level
    resource task with clear exit criteria (software
    module is ready for test)

15
WAD Task Description Content
  • Most Important Element in a WAD
  • Provides
  • Entry (Start) Criteria - Predecessor Activities
  • Completion (Exit) Criteria
  • Scope of Work
  • Basis of Estimate
  • Major Risk Identification
  • Earned Value Method for All Tasks in the Cost
    Account

16
How to Write a Task Description
  • As the CAM - Know the Task
  • If you arent the expert on the task, then get
    input
  • Dont just gloss over detail because you dont
    know it - Learn it
  • Ask Yourself
  • When Can the task start?
  • What is the task?
  • How is the task to be accomplished?
  • How do we know when the task is accomplished?
  • Why do we think the task will require the defined
    resources?
  • Manpower?
  • Schedule?
  • Material?
  • What are the risks?
  • If These Are Answered, The Task Description is
    Complete

17
EVM Summary
18
Elements of EVM
Now
Contract Value
Contract Complete
Contract Start
19
EVM Formulas
  • Variance
  • SV BCWP - BCWS
  • CV BCWP - ACWP
  • VAC BAC - EAC
  • Estimates At Completion
  • EAC ACWP ETC
  • LRE ACWP ETC
  • EAC LRE
  • Other
  • MR Contract Value - BAC
  • Performance Indices
  • CPI BCWP / ACWP
  • SPI BCWP / BCWS
  • TCPI (BAC - BCWP) / (EAC - ACWP)
  • (EAC BAC at program start)

20
EV Advantages
  • Objective Project Status Information
  • Capability to Trace the Source of Problems
  • Progress Measured Against an Agreed Upon Baseline
  • Integrated Cost and Schedule Approach
  • Early Identification of Potential Problems

21
Rules of Thumb
  • You Dont need ACTUALS to take Earned Value (EV)
  • You Dont need ACTUALS to complete an ETC
  • You Cant earn more than 100!
  • Cost Variance (CV) and Schedule Variance (SV)
    ALWAYS measured against Budget (BCWS) not ETC
  • Cost Account tasks (detail schedules) must be
    planned to support overall program milestones

22
Final Word on Project Control
If you cant measure it, You cant manage it !
- Daniel S. Goldin Former Administrator, NASA
Write a Comment
User Comments (0)
About PowerShow.com