Title: CPETECET 470 Technology Project Management
1CPET/ECET 470Technology Project Management
- Class 5 Variances Estimate to Complete
2Decoding Variance
- Negative Variances Are Always Unfavorable
- Behind Schedule
- Overrun
- Positive Variances Are Better
- Ahead of Schedule
- Underrun
- NO VARIANCE IS BEST!
- All Variances Which Exceed Threshold Must Be
Explained, Whether Favorable or Unfavorable
3Variance Analysis Questions
- Behind Schedule
- How Critical Is Schedule?
- Can I Afford to Work Overtime to Recover?
- Can I Do Tasks Concurrently?
- Are There Technical Innovations Which Could Speed
up the Process? - Am I Driving to Over Spec?
- Over Cost
- Can I Reschedule Tasks? (Timephasing)
- Is There a Less Costly Facility I Can Use?
- Are There Tasks Which Can Be Deleted?
4Variance Analysis Check List
- CAUSE Answer the question WHY?
- Did I discuss CV and SV separately?
- Did I clearly identify the reason?
- Did I isolate significant labor rate variances?
- Did I place emphasis on the Quantitative?
- Did I place emphasis on the Specific?
- IMPACT Answer the question WHAT?
- Did I describe impact on the cost account, other
cost accounts, and/or the project? - Did I address intermediate schedules?
- Did I address Predecessors Successors?
- Did I assess the need to revise the EAC?
- Did I place emphasis on the Specific?
5Variance Analysis Check List
- CORRECTIVE ACTION Answer the question HOW?
- Did I describe the specific actions taken or
being taken? - Did I include the individual or organization
responsible for the action? - Did I include schedules and get well dates?
- Did I include results of previous corrective
action plans? - If no corrective action is possible, did I
explain why
6When To Do an ETC
- Full Bottom-Up ETC is Generated for the Program
Semi-Annually - Basic rule-of-thumb Generate an ETC for a Cost
Account When Either of the Following Conditions
Are Met - BCWP 50 of BAC
- ACWP 90 of EAC
7CAM Responsibilities
Cost Account Managers Dont Just Monitor
Status, They Manage the Work !!!
8CAM Notebook
- Should Contain at a Minimum
- Work Authorization Document (WAD)
- Original Baseline Schedule (Gantt or PERT)
- Original Baseline Task Usage Report
- Original Baseline Resource Usage Report
- Original Budget Baseline Report
- Latest Cumulative Earned Value Report
- Latest Actuals Report
- Most Recent Variance Analysis Report
- All Completed Budget Change Requests
- Latest Budget Baseline Report
9CAM Notebook
- Suggest the Following Be Included
- Labor Transfer Sheets
- Last Few Months of Data
- BCRs in Process
- Special Shop Orders
- Any Special Reports the CAM Generates for His/Her
Own Use In - Determining BCWP
- Supporting Budget Data
- Explaining Variances
- Subcontract Status Reports
- CSSR CFSR
- Tracking to MPM system
Maintain the Notebook as a TOOL
10WAD Purpose
- A WAD is a contract between the CAM and the
Program Office for the scope of work, including
budget, completion dates and technical
performance - For efforts outside of the scope of work, the CAM
must request additional authorization PRIOR to
executing work - A WAD should include the following at a minimum
- Definition of work to be performed
- Assumptions for performing work
- Deliverable products resulting from effort
- Exit Criteria for completion of effort
- A WAD may include the following additional
information - Associated work that is EXCLUDED from this SOW
- Representative functional efforts contained
within this effort (I.e. design, supervision, QA,
touch labor, test, equipment, etc.)
11Earned Value Methods
- Discrete Effort - Specific End Product or Result
- Milestone method
- Start/Finish method 0/100, 25/75, 50/50, 75/25,
etc. - Percent complete method
- Apportioned Effort
- Factored effort directly related to discrete
tasks (ie-inspection) - Dependent on other work ( of BCWP of another
task) - Level of Effort
- No final product or result (ie - program
management) - Measure performance with the passage of time
- Each month BCWP is set to equal BCWS
12EV Method - Level of Effort
- Activities Which Are Time-Based Rather Than
Task-Based - Program Management
- Scheduling / Cost Management
- Security
- Contract Administration
- Project Engineering
- Generally Continue for the Life of the Project,
But Have No Measurable Outputs - Work Performed Is Assumed to Always Equal to Work
Scheduled - Therefore There Is Never a Schedule Variance
13Discrete EV Method Selection
- Milestone Method
- Used for CAs where there is limited visibility
into the specific tasks being performed, but
discrete items that will be completed as the work
is performed - Good for
- CDRLs
- PWB layouts
- etc.
- Percent Complete Method
- Least objective of the three choices
- Define an equation that you will use to remove
subjectiveness - Least preferred most time consuming method
14Discrete EV Method Selection
- Start/Finish Method
- Most common method - works for all tasks that
have clear completion criteria - What percentages are best?
- Depends on the task resource loading and
management preference - Each method has some error for an in-process task
- Example Task - Software Coding
- Preferred method 50/50
- Why? Software coding is most likely a level
resource task with clear exit criteria (software
module is ready for test)
15WAD Task Description Content
- Most Important Element in a WAD
- Provides
- Entry (Start) Criteria - Predecessor Activities
- Completion (Exit) Criteria
- Scope of Work
- Basis of Estimate
- Major Risk Identification
- Earned Value Method for All Tasks in the Cost
Account
16How to Write a Task Description
- As the CAM - Know the Task
- If you arent the expert on the task, then get
input - Dont just gloss over detail because you dont
know it - Learn it - Ask Yourself
- When Can the task start?
- What is the task?
- How is the task to be accomplished?
- How do we know when the task is accomplished?
- Why do we think the task will require the defined
resources? - Manpower?
- Schedule?
- Material?
- What are the risks?
- If These Are Answered, The Task Description is
Complete
17EVM Summary
18Elements of EVM
Now
Contract Value
Contract Complete
Contract Start
19EVM Formulas
- Variance
- SV BCWP - BCWS
- CV BCWP - ACWP
- VAC BAC - EAC
- Estimates At Completion
- EAC ACWP ETC
- LRE ACWP ETC
- EAC LRE
- Other
- MR Contract Value - BAC
- Performance Indices
- CPI BCWP / ACWP
- SPI BCWP / BCWS
- TCPI (BAC - BCWP) / (EAC - ACWP)
- (EAC BAC at program start)
20EV Advantages
- Objective Project Status Information
- Capability to Trace the Source of Problems
- Progress Measured Against an Agreed Upon Baseline
- Integrated Cost and Schedule Approach
- Early Identification of Potential Problems
21Rules of Thumb
- You Dont need ACTUALS to take Earned Value (EV)
- You Dont need ACTUALS to complete an ETC
- You Cant earn more than 100!
- Cost Variance (CV) and Schedule Variance (SV)
ALWAYS measured against Budget (BCWS) not ETC - Cost Account tasks (detail schedules) must be
planned to support overall program milestones
22Final Word on Project Control
If you cant measure it, You cant manage it !
- Daniel S. Goldin Former Administrator, NASA