Decision Maths - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Decision Maths

Description:

If fetching the car takes longer then this will hold up driving to the Interview. ... We already know that there is a lot of float involved in fetching the car. ... – PowerPoint PPT presentation

Number of Views:319
Avg rating:3.0/5.0
Slides: 21
Provided by: bengr1
Category:

less

Transcript and Presenter's Notes

Title: Decision Maths


1
Decision Maths
  • Lesson 6 Resource Allocation

2
Notation
  • Activities are represented by arcs.
  • The nodes represent events.
  • They can be specific points (dates) in a project.
  • It is possible to refer to an activity by a
    unique pair of events i and j, ( i , j ).
  • i represents the node (event) before the activity
    and j represents the node (event) after the
    activity.

3
Notation
  • In the example below the activity A can be
    represented by the ordered pair ( 1 , 2 ).
  • B ( 1 , 3 ) C ( 2 , 5 ) etc

4
Resource Allocation
  • When Mr and Mrs Jaffrey go out together they get
    away more quickly than when Mr Jaffrey goes out
    on his own.
  • Here are the activities involved.

5
Resource Allocation
6
Cascade (Gantt) Chart
  • The example just shown illustrates how tasks can
    be made more efficient by careful planning.
  • We have looked at illustrating problems using
    precedence networks.
  • Another way to show the same information is by
    using a Cascade (Gantt) Chart.
  • A Cascade Chart shows the information in the form
    of bars along a time scale.
  • Hopefully you will see that they can be easier to
    interpret when allocating resources.

7
Cascade (Gantt) Chart
  • We are now going to look at constructing a
    Cascade Chart.
  • Through out the rest of this lesson we are going
    to be looking at the example below.
  • A woman has an interview that she is running late
    for, and her two flat mates are going to help her
    get there on time.
  • The table below shows the activities that need to
    be completed, their duration and the immediately
    preceding activities.

8
Cascade (Gantt) Chart
  • The first thing to do is to construct a
    precedence network.
  • Describe how to construct the network for the
    example.

9
Cascade (Gantt) Chart
  • In the first chart the order of the activities is
    given by sorting on the i activity and then on
    the j.
  • You must place the bars as far left as they will
    go.

2
1
Shower
10
Cascade (Gantt) Chart
  • The rest of the activities will now be drawn,
    focusing first on all activities leaving node 1.
    Then Node 2 etc.
  • They should be positioned as far left as possible.

2
1
Shower
0
5
15
20
25
30
35
40
45
10
Minutes
11
Cascade (Gantt) Chart
  • Activity Dry hair cannot begin until Shower
    has finished.
  • Dry hair is positioned as far left as it can go,
    so it starts at 3.
  • A dotted line can be drawn to help show this
    relation between the two activities.

2
1
Shower
0
5
15
20
25
30
35
40
45
10
Minutes
12
Cascade (Gantt) Chart
  • The bar for drying hair cannot be moved past the
    dotted line that joins iron and dress. If Drying
    Hair is delayed then it will affect Dress,
    Make-up
  • The Critical activities are written in bold and
    the bars are shaded.

2
1
Shower
3
1
Iron Clothes
1
4
Fetch Car
Dry Hair
3
4
Dress, Make-up
4
5
Drive to interview
0
5
15
20
25
30
35
40
45
10
Minutes
13
Cascade (Gantt) Chart
  • It is not as clear to see but activity Fetch
    car can be moved around until it reaches the
    activity Drive to interview
  • If fetching the car takes longer then this will
    hold up driving to the Interview.

2
1
Shower
3
1
Iron Clothes
Fetch Car
3
2
Dry Hair
3
4
Dress, Make-up
4
5
Drive to interview
0
5
15
20
25
30
35
40
45
10
Minutes
14
Cascade (Gantt) Chart
  • It is not as clear to see but activity Fetch
    car can be moved around until it reaches the
    activity Drive to interview
  • If fetching the car takes longer then this will
    hold up driving to the Interview.

2
1
Shower
1
3
Iron Clothes
Fetch Car
3
2
Dry Hair
3
Dress, Make-up
Drive to interview
0
5
15
20
25
30
35
40
45
10
Minutes
15
Cascade (Gantt) Chart
  • An alternative way of drawing a Cascade Chart is
    to group all of the critical activities in one
    bar. With the other activities as separate bars.
  • The dotted lines can be drawn to show the float
    available.
  • It is clear to see here that fetching the car has
    a lot of float until it reaches 22 minutes.

A
B
D
E
F
16
Cascade (Gantt) Chart
  • Finally we could draw the chart from the point of
    view of each of the three people involved in the
    activities. Showing their responsibility
    throughout.
  • We already know that there is a lot of float
    involved in fetching the car.
  • We can also see that this activity could in fact
    be done by person 2.
  • Person 3 is surplus to requirements. This is a
    valuable tool when allocating resources.

Person 3
Person 2
Person 1
17
Resource Histogram
  • From the cascade it is a simple matter to draw a
    resource histogram to show the number of people
    required at any given time.

18
Resource Histogram
  • As was shown on a previous slide the activity
    fetch the car can actually be done after person
    2 has ironed the clothes.
  • In this case the resource histogram would look
    like this.

19
Resource Levelling
  • Resource levelling is the process of making your
    project more efficient.
  • There are three main objectives that can be
    looked at.
  • Can you guess three areas that you might like to
    focus on?
  • 1 Minimise total time
  • This is typically the case with maintenance. If
    you have a piece of vital equipment that you
    don't want out of action for too long. An
    aeroplane or a heating system.
  • Using extra resources to reduce completion time
    is known as crashing a network.

20
Resource Levelling
  • 2 Minimise total cost
  • When time is not a factor, you have the luxury of
    minimising cost. For example things that are
    required in the summer can be repaired through
    the winter.
  • 3 Make max use of resources (people and
    equipment)
  • If you need to work with a fixed team of workers,
    or if you want to avoid hiring two cement mixers
    when, with careful planning, one will do, then
    this kind of planning is appropriate.
Write a Comment
User Comments (0)
About PowerShow.com