Title: Laserwire at the ATF extraction line
1Laser-wire at the ATF extraction line
- Laser Based Beam Diagnostic
- (Laser-wire UK collaboration)
- Chafik Driouichi
- Royal Holloway University of London
- 19th April 2005
http//www.pp.rhul.ac.uk/lbbd/meetings/meeting10/
index.html
2Outline
- Whats already there and shouldnt worry about.
- Issues to worry about when designing the Optics
Transport. - Relay optics, is it needed?
- Laser beam diameter its implication on the
optics (2 or 3). - Laser power too high. Do we need all that power?
- - Coatings
- - Safety devices
- Lens tolerances system alignment
- Scanning range
- Optics table (what should be there?)
- Define responsibilities
- Plan for next trip
- Summary discussion
3Whats already there?
- Laser
- P 1 GW, tpulse 200 - 300 ps, rep.rate 6.25
Hz, Ø6 mm. - Part of the beam transport (from laser hut to the
tunnel) - Control signal system is partly there easy to
integrate in our DAQ - Wire scanner (should be repaired by now!)
4Issues to worry about (1)
Relay Optics
Risk ? Relay optics might spark the air due to
the laser power.
Laser hut
missing
Ext. Line
Divergence is small ? No need for a relay !!!
5Issues to worry about (2)
Beam diameter implication on the optics
Focusing lens incl. 3 elements
Beam diameter 6 mm
f 60 mm ? 532 nm ?f 1 ?m
To achieve ?f 1 ?m, one needs ?L 10 mm
Can a 2 optics accommodate the beam ? Certainly
not! ? 3 optics _at_45
incidence
6Issues to worry about (3)
Laser Damage Threshold (LDT)
E 300 - 400 mJoules Pulse length 200 - 300
ps Beam diameter 2.R 6 mm
Power density
1.4 Joules/cm2
CVI Coating ? 5 Joules/cm2 _at_ 532 nm for a pulse
duration of 8 ns.
LDT (8 ns) 1.4 Joules/cm2 .
? 9 Joules/cm2
? CVI coating is not enough !
7Issues to worry about (4)
CVI Technical Optics claims coating with LDT 20
Joules/cm2
Best candidate so far !
However
Dust or grease ? highly absorbing areas Laser
cavity instability ? random hot spots
- Environment conditions critical, but can be
taken care of (enclosed system). - Laser best
performance needs to be identified and controlled
(laser parameters needs to be measured at the
beginning of each run)
Shintake ? We dont need to use the full power of
the laser.
8Optics (Breadboard in tunnel)
The breadboard should contain
- High power Beam Shutters one in the laser hut,
the second just at the entrance of the optics
breadboard (interlocked). - Coarse alignment system (global alignment of the
setup) done when putting the system together for
first time by using apertures, red light, PSDs. - Waist monitor measure the waist at the entrance
of the focusing system (will be done by dumping
most of the beam and sending the remaining
fraction to a CCD camera). - An adjustable Beam Expander 2 lenses, one fixed,
the other one is on a translation stage in order
to fully collimate the beam - Fine alignment system 2 steering mirrors
combined with 2 PSDs. - Scanner PI S330 ? ? 2 mrad, f1KHz, high
repeatability - Attenuators, beam dumps, ND filters,.
- Powermeter Molectron or Ophir.
- A fast photodiode for time measurement.
9Alignment
A coarse alignment will be done at first when
installing the system by using a red light,
apertures, PSDs along the beam path.
PSD2
- Fine alignment will be done using
- - 2 steering mirrors MS1 MS2
- ? will have a 2 axis rotations
- - 2 PSDs
- ? will be finely aligned with respect to
the focusing lens) in order to bring the beam
within the tolerance of the focusing lens
(off-axis lt1 mm tilt lt5 mrad).
? tilt
PSD1
A setup is being developed at RHUL.
10Screenshot from ZEMAX of the alignment setup
11Scanning range
- If we suppose that
- s e-beam size
- N number of sigma scans
- ? N x s /f
Example f 60 mm N 5
? (?m) 1 6 ? (mrad) 0.08 0.5
Scanner PI S330 ? 2.5 mrad, f1KHz, good
repeatability.
Other options (A.O E.O) are being investigated.
12ZEMAX screenshot of the beam path
e-beam
x
200
z
Scanning platform
700
300
500
Beam Telescope
MS2
400
100
MS1
800
400
100
13ZEMAX Simulation
14Responsibilities
KEK
Laser hut access Support for the Breadboard,
enclosure for the system (pipes, box
) Wire-scanner
RHUL/OXFORD/UCL (all what will be on the
breadboard)
Breadboard (1.5m x 1m or 2m x 1m) Optics
mirrors, focusing lens, Scanner, diagnostics
tools (beam profilers), photodiode, PSDs, beam
dumps, beam shutters, energy meter, .
15Plan for next KEK trip
Laser Optics Transport
- Get familiar running the laser, and measure its
beam properties - (triggering, jitter, energy, )
- Agree with ATF on safety issues related to Optics
Transport.
e-beam optics
- Validate the e-beam optics (profile measurement
with wire scanner) - Get familiar with the ATF control system
(dispersion corrections, - Wire-scanner, BPMs,)
- APD v.s. PMT
- Get some collision even with the e-Compton setup.
16Summary
Optics Transport
- No Relay optics
- Safety devices Beam shutters will be placed in
both HUT - entrance of Breadboard (Spiricon)
- Coating still a confusion, but will be sorted
out in a couple of days - Reduce the laser power to several 10s MW.
- Optics will be 2 before Beam Expander, and 3
mirrors post-BE. - System alignment is being developed at RHUL
- Scanning PI S330 (other technologies are being
investigated) - Zemax simulation ? meetings our goals.
Companies/Providers identification has already
started
KEK Trip
Critical to meet all goals mentioned earlier.