Title: Interconnecting to the CG


1
Interconnecting to the CGE System
  • PUCO Technical Conference on Interconnection
  • March 9, 2006 - Columbus, OH
  • Jim Lemke

2
Where to find Uniform Interconnection Procedure
in CGEs Tariff
  • Rate DI (Distribution Interconnection)
  • http//www.cinergycge.com/pdfs/ratedi.pdf
  • Includes Application Form Interconnection
    Agreements

3
CGE Has Further Simplified Interconnection
  • No application or study fees
  • One page Agreement for PV lt 10kW
  • Separate utility disconnect switch usually not
    required for residential PV
  • Available to discuss requirements and options for
    specific projects before an application is made

4
CGE Has Further Simplified Interconnection
  • IEEE 1547 Certification
  • CGE accepts inverters with UL 1741 listing as
    meeting the testing section in the Technical
    Requirements for lt 300kW
  • CGE uses IEEE 1547 as the core of its
    interconnection technical requirements for any DR
    lt 10MW

5
Experience(Since Uniform Procedures Adopted)
  • Most applications have been in two categories
  • Small photovoltaic
  • Net metering
  • Smallest 1.3kW Largest 20kW
  • Pass screens for simplified interconnection
  • Recip engine driven synchronous generator
  • Backup with Paralleling Switchgear
  • Smallest 600kW Largest 4MW
  • Do not pass screens for simplified
    interconnection

6
Small PV Interconnection Approval Process Is Very
Simple
  • Application information can be taken over the
    phone
  • Name and address
  • Inverter manufacturer, model number, rating
  • Confirm UL1741 listing
  • On site inspection after installation takes
    less than 15 minutes

7
One Page Agreement for PV lt 10 kW
8
Typical Application for gt 300kW
  • Diesel or natural gas engine
  • Synchronous generator
  • Primarily for emergency or back-up power
  • Paralleling Switchgear to avoid interruption when
    returning load to utility, but includes
    continuous parallel capability for future
    peak-shave option
  • No intention to export power

9
gt300kW Process
  • Most projects do not start with an application
    containing a completed interconnection design
  • Most projects do start well before application
    with phone call seeking information about
    technical requirements

10
gt300kW Process
  • CGE uses IEEE 1547 as the core of its
    interconnection technical requirements for any DR
    lt 10MW
  • To complete a design that is compliant with IEEE
    1547, some exchange of information with the
    utility is necessary
  • Relative size of DR to utility load
  • Transformer winding connections
  • Utility reclosing

11
gt300kW Process
  • Most of the interconnection issues are worked out
    in an informal process with the Customers
    engineering firm before an application is made
  • In most cases so far, no CGE system changes have
    been required to accommodate the DR

12
Impact of IEEE 1547
  • Provides a nationally recognized standard that
    supports CGE requirements
  • In CGEs experience, most pre-IEEE 1547
    interconnection designs were generally consistent
    with IEEE 1547 therefore, no significant
    changes have occurred

13
Who to Contact About Interconnection
  • Mike Koehler
  • 513-287-1984 Direct Number
  • Mike.Koehler_at_cinergy.com
  • Jim Lemke
  • 765-454-6196 Direct Number
  • Jim.Lemke_at_cinergy.com