Title: THE STEPBY STEPS: as posted on the FTP site
1THE STEP-BY STEPS as posted on the FTP site
2Cross-section of Eroded Bank
3sand bed stream Longitudinal Peaked Stone Toe
Protection (LPSTP) Upper bank sloped and
vegetated
4- sand bed stream - LPSTP Upper bank sloped and
vegetated
Longitudinal Peaked Stone Toe Protection (LPSTP)
with side slopes at the angle of repose
- LOCKED LOG locked under LPSTP (for aquatic
habitat)
5- sand bed stream - LPSTP Upper bank sloped and
vegetated
The stream will adjust to the LPSTP, the LPSTP
will self-adjust to armor the resulting scour hole
6- sand bed stream - LPSTP Upper bank sloped and
vegetated
The LPSTP has self-adjusted
7- sand bed stream - LPSTP Upper bank sloped and
vegetated
Install Live Siltation
8- sand bed stream - LPSTP Upper bank sloped and
vegetated
Install gravel-cobble granular filter
9- sand bed stream - LPSTP Upper bank sloped and
vegetated
Slope bank (balanced cut/fill)
CUT
FILL
10- sand bed stream - LPSTP Upper bank sloped and
vegetated
Sloped bank
11- sand bed stream - LPSTP Upper bank sloped and
vegetated
To install Brush Layering, remove soil
12- sand bed stream - LPSTP Upper bank sloped and
vegetated
Install plant material as Brush Layering
13- sand bed stream - LPSTP Upper bank sloped and
vegetated
Backfill and install second layer of Brush
Layering, etc.
14- sand bed stream - LPSTP Upper bank sloped and
vegetated
Install rooted-stock plants
15- sand bed stream - LPSTP Upper bank sloped and
vegetated
Soil-choke LPSTP
16- sand bed stream - LPSTP Upper bank sloped and
vegetated
Hydroseed all disturbed areas
17DONE
18QUESTIONS???
19ONONDAGA CREEK _at_ NICHOL ROAD BRIDGE,
LAFAYETTE, NY
20Blue lines denote waters edge at base flow
bar
Nichol Road Bridge
Onondaga Creek _at_ Nichol Road Bridge-Sketch from
Mark Schaub
21Top layer of stone will be removed from red
areas. The US section of the left bank will then
be sloped all areas planted.
22Removed stone will be then placed in the brown
areas using the trenchfill technology to provide
a funnel effect to prevent the stream from
flanking the existing project.
23100 Black Willow, 2,000 Streamco Willow, 500 Red
Osier Dogwood 100 Sycamore were planted using
the Slit Trench Brush Layering
bioengineering methods. 40 RPM container plants
(7 species of trees shrubs) were planted in the
green oval areas. Black Willow Sycamore
Extreme Instant Shade shown by the orange lines.
Note Plantings form a grid
24TWO-STAGE SLIT TRENCH TECHNIQUE
Spoil
Dig the trench down into the capillary (vadose)
zone moist area above the permanent water table
Sketches by Derrick
Mini-Case study 1 of 8
25TWO-STAGE SLIT TRENCH TECHNIQUE
Water table
Mini-Case study 2 of 8
26TWO-STAGE SLIT TRENCH TECHNIQUE
Vadose zone moist area is shown in pink
Water table
Mini-Case study 3 of 8
27TWO-STAGE SLIT TRENCH TECHNIQUE
Take the last scoop of soil dug from the trench
place it back into the trench.
Mini-Case study 4 of 8
28TWO-STAGE SLIT TRENCH TECHNIQUE
Place willows other water-loving species into
loose soil at bottom of trench. They are then
less likely to fall over when trench is
backfilled.
Mini-Case study 5 of 8
29TWO-STAGE SLIT TRENCH TECHNIQUE
Partially backfill the trench.
Mini-Case study 6 of 8
30TWO-STAGE SLIT TRENCH TECHNIQUE
Plant other species that require less water than
the willow. In this case Sycamore Red Osier
Dogwood
Mini-Case study 7 of 8
31TWO-STAGE SLIT TRENCH TECHNIQUE
DONE
Backfill water plants in
Mini-Case study 8 of 8
32ONONDAGA CREEK SITE 5-D Diamond-Oriented
Traffic Control Stones with Single Stone
Bendway Weirs
33Diamond-Oriented Traffic Control Stones with
Single Stone Bendway Weirs
Key
TCS
TCS
TCS
Key
TCS
TCS
SSBW
TCS
TCS
TCS
SSBW
Key
TCS
SSBW
Square stones (3 ft by 3 ft by 3 ft) placed with
a sharp edge facing upstream, designed to kick
flow off the bank, must be keyed into the bed
bank, spaced 6 to 8 ft apart, every 4th one
should be keyed into the bank. Every 4th stone
has a Single Stone Bendway Weir.
34Diamond-Oriented Traffic Control Stones with
Single Stone Bendway Weirs
Thalweg is dug and that bedload material is
placed between the Traffic Control Stones to form
a bench at the same height as the TCS.
35Diamond-Oriented Traffic Control Stones with
Single Stone Bendway Weirs
Plants, root mass, and soil was pulled down from
the vertical outer bank to provide streamside
vegetation. The mid upper bank was sloped and
seeded.
36Stabilizing a low bank with good top bank veg
Step 1 Good veg good root mat, but eroding
bank
Step 2 Undercut root mat without disturbing
roots
Step 4 Turn bucket collapse bank. Add
minimal stone toe
Utilizing the existing dense root mat
37Large sand bed river Launchable LPSTP weighted
toe with paved (riprap) midbank area Upper
bank sloped and vegetated
38Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
- Locked Logs placed on bed of river and locked
under the LPSTP (for improved aquatic habitat
energy dissipation)
39Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Locked Logs should be angled downstream approx.
45 degrees so as to shed debris
40Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
LPSTP (with riverside slope at the angle of
repose) in a weighted toe configuration
Crestwidth
41Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
All of the purple stone can self-adjust (launch)
and the LPSTP will still be at the original
height of protection
42Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
The stream will adjust to the LPSTP, and the
LPSTP will self-adjust to armor the resulting
scour hole
Scour hole
43Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
The LPSTP has self-adjusted
Scour hole
44Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Grade the bank to the appropriate angle
45Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Install gravel-cobble granular filter
46Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Install willow poles (to be used as the Bent
Willow Pole Method)
47Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Start to install riprap
48Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
More riprap
Bent Willow Pole Method (underlying willow bent
up, then next stone placed)
49Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Bent Willow Pole Method
50Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
More riprap
51Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Bent Willow Pole Method
52POSSIBLE VARIATION
Plant some rooted-stock trees shrubs within
riprap area (in addition to the Bent Willow Poles)
53Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Install Brush Layering
54Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Install rooted-stock plants
55Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Soil-choke riprap
56Large sand bed river LPSTP weighted toe with
paved midbank Upper bank sloped vegetated
Hydroseed all disturbed areas
57DONE
58QUESTIONS???
59A MID PROJECT KEYWAY DETAIL
60Detail for key
Cross-section for keyway
Flow
61Detail for key
Flow
Place granular filter
62Detail for key
Place Willow Poles against US side of trench
Flow
63Detail for key
Place stone in trench
Flow
64Detail for key
Choke stone with gravel (white areas) water in
Flow
65Detail for key
Backfill and overfill with native soils, then
compact (some settling will still occur)
Flow
66Detail for key
Seed
Flow
DONE
67WIDE KEYWAY DETAIL
68DETAIL FOR KEYWAY THAT WILL ALSO BE USED
FOR EQUIPMENT ACCESS AS A HAUL ROAD
69Detail for key
In addition to keyway functions, it will be used
as equipment access as a haul road
Excavate wide trench
16 ft
70Detail for key
Place granular filter
71Detail for key
Place riprap stone in trench
72Detail for key
Choke stone with gravel surge stone (white
areas)
73Detail for key
Backfill overfill to allow for settling with
native soil
74Detail for key
Plant hydro seed as appropriate
DONE
75TRENCHFILL REVETMENT DETAILanother way to do it
76Place granular filter
77Place willow poles other adventitious rooting
plants on DS side of trench
78Place self-adjusting stone in trench
79Choke stone with gravel cobble (white areas)
80Backfill overfill to allow for settling with
native soil
81Plant hydro seed as appropriate
DONE
82STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
83STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Flow
84STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Key trench
Footer trench
Flow
Key trench
Dig key footer trenches
85STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Footer trench
Flow
Key trench
Important note In some cases the US key trench
is dug all the way across the stream
86STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Flow
Place granular filter (gravel) in all trenches.
Note granular filter not needed in gravel-cobble
bed streams
87STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Pole plantings
Flow
Dig a hole, plant a pole says John McCullah
88STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Flow
Place key stones and downstream footer stones
89STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Place granular filter on footprint of ERR.
90STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Place a set of stones (in compression) just
upstream of the footer stones
91A STONE ENGINEERED ROCKED RIFFLE WITH
WEIGHTED TOE
Stones on crest, the downstream face, toe all
set in compression
FLOW
Weighted toe can be designed to help stop the
headward migration of a DS knickpoint headcut
92STONE ENGINEERED ROCKED RIFFLE FOR GRADE
CONTROL HEADCUT STABILIZATION
Place all stones in compression from downstream
to upstream including crest stones.
93STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Place glide stones
Flow will keep glide stones in compression
94STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Place appropriate sediment or spawning gravel
over glide stones
95STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Bank protection riprap
Pool will form here
Place bank protection riprap stones on both banks
96STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Pool will form here
Adventitious rooting poles planted next to bank
protection riprap
97STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
DONE
Pool will form here
98STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Profile view
20
Flow
1
Granular filter
99STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Profile view
Force
All stones in compression from force of water,
energy transferred into ground
100 ENGINEERED ROCKED RIFFLE - MODIFIED FOR
VENSAL CREEK APPLICATION
Existing concrete slab
Profile view
Existing ground
All stones in compression from force of water,
energy transferred into ground
101 ENGINEERED ROCKED RIFFLES FOR VENSAL CREEK
APPLICATION, TULSA, OK. USA
Arkansas River
This ERR for stability, DS pool formation, will
also be sloped specifically for use as a boat
launch
This ERR designed to resist future instability
and headcutting from the Arkansas River, and to
provide a tailwater for the US boat launch ERR.
102- Engineered Rocked Riffles (ERR) in series used to
mitigate the vertical drop over a concrete dam.
Could be utilized on the Highland Park Dam on
Swan Creek - Constructed pool-riffle-pool configuration
Water surface elevation
All top stones in compression
DAM
Stone dug in
103INTEGRATING A FISH LADDER ON THE DOWNSTREAM
FACE OF AN ENGINEERED ROCKED RIFFLE (ALL
STONES IN COMPRESSION)
104AN ENGINEERED ROCKED RIFFLE WITH INTEGRATED
FISH LADDER
At least two layers of stones are set in
compression to form pools on the DS face of the
ERR
Water surface elevation
Backwater from DS ERR
105AN ENGINEERED ROCKED RIFFLE WITH INTEGRATED
FISH LADDER
Mini resting pool for fish passage
106AN ENGINEERED ROCKED RIFFLE WITH INTEGRATED
FISH LADDER
Compression forces (white arrows) are transferred
into the ground
Flow
107AN ENGINEERED ROCKED RIFFLE WITH INTEGRATED
FISH LADDER
An overall slope of 20 to 1 can still be
maintained
20
1
108SPECIAL CASE - STONE ERR WITH MAXIMUM HEADCUT
STABILIZATION WEIGHTED TOE BUILT IN
Similar to previous ERR but a large underground
weighted stone toe at a 10 to 1 slope would be
constructed DS of the present ERR . It would be
constructed first, with all stones in compression
Entire area excavated, with a granular filter
placed on bed
109SPECIAL CASE - STONE ERR WITH MAXIMUM HEADCUT
STABILIZATION WEIGHTED TOE BUILT IN
Amount of weighted toe stone will be designed to
halt the upstream movement of a specific height
of headcut
Stones placed in compression on granular filter
110SPECIAL CASE - STONE ERR WITH MAXIMUM HEADCUT
STABILIZATION WEIGHTED TOE BUILT IN
Riprap stones placed for bank protection
111STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Flow
20
1
10
1
Profile view
112STONE ENGINEERED ROCKED RIFFLE FOR GRADE
HEADCUT STABILIZATION
Amount of weighted toe stone will be designed to
halt the upstream movement of a specific height
of headcut
Flow
Profile view
113Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
114 Gravel-Cobble Bed Stream Install Minimal
Height Riprap - Upper Bank Undisturbed -
115Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Install Live Siltation
116Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
- Pre-dig and overdig pool (let the stream
determine final pool depth)
117Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Part of the dug area will be the toe-down area
for the stone revetment
118Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
If good gravel-cobble, use dug pool material as a
granular filter
119Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Install willow poles (to be used as the Bent
Willow Pole Method)
120Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Install riprap
121Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Install Locked Logs
122Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Install more riprap to hold down Locked Logs
Locked Log
123Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Bent Willow Pole Method (underlying willow bent
up, then next stone placed)
124Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
More riprap
Bent Willow Pole Method
125Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
More riprap
Bent Willow Pole Method
126Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Last of the riprap
Bent Willow Pole Method
127Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Soil-choke riprap
128Gravel-Cobble Bed Stream Install Minimal Height
Riprap Upper Bank Undisturbed -
Hydroseed all disturbed areas
129DONE
130QUESTIONS???
131Gravel-Cobble Bed Stream Install Minimal
Height Riprap PLUS Engineered Floodplain Bench
PLUS Upper Bank Sloped Veged
132Cross-section of Eroded Bank
133Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Floodplain Bench
Cut floodplain bench and slope upper bank (you
will have soil left over). Or build the
floodplain bench out into the stream
134Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Floodplain Bench
Dig Slit Trenches BOTH parallel and perpendicular
to flow install adventitious rooting plants
135Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Install upper bank rooted-stock plants
136Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Install Live Siltation against bank
137Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
- Pre-dig and overdig pool, let the stream
determine the final pool depth
138Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
- Part of the dug area will also be the toe-down
area for the stone revetment -
139Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
If good gravel-cobble, use dug pool material as a
granular filter
140Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Install toed-down Riprap
141Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Install Locked Logs for aquatic habitat
improvement energy dissipation
142Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Lock Locked Logs in place with more Riprap
Locked Log
143Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Install willows for Bent Willow Pole Method
144Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Add Riprap
145Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Bent Willow Pole Method (underlying willow bent
up, then next stone placed)
146Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
More Riprap
Bent Willow Pole Method
147Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Bent Willow Pole Method
148Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
More Riprap
Bent Willow Pole Method
149Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Bent Willow Pole Method
150Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Last of the Riprap
Bent Willow Pole Method
151POSSIBLE VARIATION
In addition to the Bent Willow Pole Method, some
rooted stock plants could be placed within the
interstices of the riprap
152Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Choke riprap with soil
153Gravel-Cobble Bed Stream Install Minimal Height
Riprap Engineered Floodplain Bench Upper Bank
Sloped Vegetated
Hydroseed all disturbed areas
154Done Basically riprap that could stand alone,
but enjoys many other functions
155QUESTIONS???
156(No Transcript)
157QUESTIONS???
158CONTRACTION STONES DESIGNED TO PROVIDE POOL
HABITAT
159Contraction Stones designed to provide pool
habitat
WELL VEGETATED
Overwidened riffle-run with no pools
Flow
WELL VEGETATED
160Toe down large stones (partially key into bank)
opposite each other to constrict channel. Crests
of stones should not be higher than adjacent bank
areas
8-10 ft
Reduce width according to model results
10-15 ft
10-15 ft
Contraction Stones designed to provide pool
habitat
161Contraction Stones designed to provide pool
habitat
Pre-dig and over-dig pool areas.
162Contraction Stones designed to provide pool
habitat
DONE
Stream will set pool depths and widths over time
163QUESTIONS???
164Transverse Bar with Stone Angle Slam
165Transverse Bar with Stone Angle Slam
Predig overdig pool
166Transverse Bar with Stone Angle Slam
Angle Slam stones
Place stones, backfill with soil (choke), and
vegetate.
167DONE
Transverse Bar with Stone Angle Slam
Transplant overhanging shrub-small tree
vegetation.
168QUESTIONS???
169Transverse Bar with Wood Board LUNKER
170Transverse Bar with Wood Board LUNKERS
Pre-dig overdig pool area where LUNKERS will
be placed
Pre-dig and overdig pool LUNKER areas
171Transverse Bar with Wood Board LUNKERS
LUNKER
LUNKER
LUNKER
Place and anchor LUNKERS.
172DONE
Transverse Bar with Wood Board LUNKERS
LUNKER
LUNKER
LUNKER
Transplant large shrubs/small trees.
173QUESTIONS???
174Transverse Bar with Log LUNKER
175Transverse Bar with Log LUNKER
Footer log
Footer log
Key section of log
Dig place footer logs, downstream log keys
behind US log .
176Transverse Bar with Log LUNKER
Roof log
Roof log
Roof log
Place and anchor roof logs .
177Transverse Bar with Log LUNKER
DONE
Transplant shrub/tree vegetation .
178QUESTIONS???
179VORTEX WEIR FOR POOL CREATION
180Vortex Weir for Pool Creation
Key
Key
Key
Lower elevation
Key
Key
Vortex weir is a semi-circle flow concentrator,
lower in the center of the Weir, plunge pool
immediately downstream. Key stones will be
choked with soil and vegetated.
181Vortex Weir for Pool Creation
Predig overdig pool
Predig overdig pool
182Vortex Weir for Pool Creation
Plant vegetation
Plant vegetation
Plant vegetation, can be combos of, Live
Siltation, Live Stakes, Slit Trench, rooted stock
or mechanically transplanted vegetation.
183Vortex Weir for Pool Creation
DONE
Transplant large vegetation
Plant mechanically transplanted large shrub
vegetation.
184QUESTIONS???
185QUESTIONS???
186QUESTIONS???
187QUESTIONS ???ANSWERS ???
188(No Transcript)
189(No Transcript)