Title: Proposed regulatory alternatives
1Proposed regulatory alternatives
- Class location change
- Other risk control projects
2Pipeline map of class chg area
3Class location change30 main line -L154
4Class location change30 loop line L-254
5Corrosion technology evaluation
- Will closely parallel PRCI initiative but will be
independent of PRCI study - Objective is to carry out a comparative study on
the various techniques available in - identifying coating anomalies
- quantifying corrosivity
- identifying and quantifying metal loss
6Corrosion technology evaluation
- Techniques that will be considered
- close interval survey (on only)
- interrupted close interval survey (fast cycle)
- interrupted close interval study (slow cycle)
- close interval survey with side drain meas.
- direct current voltage gradient (DCVG) survey
- pipeline current mapping
- waveform analysis
- pearson survey
- C-scan and electromagnetic soil resistivity
7Corrosion technology evaluation
- Industry experts in a joint approach will conduct
this evaluation - CSIR North America
- TEPSCO
- If logistics can be worked out, this evaluation
will be conducted in coordination with planned
smartpig runs on lines L-154 and L-254
8Corrosion technology evaluation
- If smartpig results indicates bellhole
inspections are needed to further evaluate
indications, 1-2 of these locations would be used
as a test site to compare information from
techniques being evaluated prior to escavation
9Corrosion technology evaluation
- Project details
- all techniques will be applied according to
standard industry practices and/or manufacturer
specifications - A distinction will be made between close
interval techniques and wide interval
techniques (waveform, PCM, C-scan) - In order to avoid any discrepancies in terms of
positional correlations, all anomalies will be
identified using differential GPS
10Corrosion technology evaluation
- Project details - continued
- DCVG will also be used to provide additional
information on possible shielding effects - The use of elctromagnetic soil resistivity
measurements will be included as a technique
aimed at obtaining information on the possible
corrosivity of the soil environment. These
results will be correlated with the results
obtained from the other techniques listed
11Corrosion technology evaluation
- These tests will be performed on approximately a
3 mile section of pipeline in the proximity of
the proposed class location alternative area near
Church Rock, NM - TW is especially interested in determining if any
of the techniques can provide additional
corrosion control information regarding the
bottom half of large diameter pipe
12Corrosion technology evaluation
- TW will plan to conduct additional surveys on
lines L-154, L-187, and L-176 having known
disbondment with technique(s) identified that
will provide measurable additional information
regarding coating condition
13Evaluation of coating survey techniques
Resistance bond to a foreign pipeline
Holidays at varying locations around the pipe
3 to 5 miles
000
100
200
300
400
600
700
Varying size and shape holidays
High resistance short to ground
Pearson Survey Close Interval Survey (On) Close
Interval Survey (On-Off- Fast Cycle) Close
Interval Survey (On-Off - Slow Cycle) Close
Interval Survey with Side Drains DC Voltage
Gradient Survey (Pipe Camp) Pipeline Current
Mapping Waveform Analysis (TransWave)
14Risk control activities planned for class loc chg
area
- Conduct geometry tool and in-line inspection
(smartpig) - Increase pipeline surveillance from monthly to
twice monthly - Install additional ROW markers with spacing not
to exceed 500 feet where possible and practical - Install new style ROW markers
15Risk control activities planned for class loc chg
area
- Conduct depth of cover survey
- Increased emphasis on meeting with certain
excavation contractors, local and county planning
groups, and utilities operating in the area - Install transwave equipment
- Conduct corrosion technology evaluation
- Conduct CP survey with instrument using results
of corrosion technology evaluation
16Risk control activities planned for line L-154
- Conduct geometry tool and in-line inspection
(smartpig) - Conduct CP survey with instrument using results
of corrosion technology evaluation
17Risk control activities planned for line L-154
- Where any class 2 or 3 areas exist, besides
specific class change area, the following will be
done - Install new style ROW markers with spacing not to
exceed 500 feet where possible and practical - Increased emphasis on meeting with certain
excavation contractors, local and county planning
groups, and utilities operating in the area
18Risk control activities planned for line L-254
- Conduct geometry tool and in-line inspection
(smartpig) - Where any class 2 or 3 areas exist, besides
specific class change area, the following will be
done - Install new style ROW markers with spacing not
to exceed 500 feet where possible and practical - Increased emphasis on meeting with certain
excavation contractors, local and county planning
groups, and utilities in area
19Risk control activities planned for line L-187
- Conduct geometry tool and in-line inspection
(smartpig) - Where any class 2 or 3 areas exist, besides
specific class change area, the following will be
done - Install new style ROW markers with spacing not
to exceed 500 feet where possible and practical - Increased emphasis on meeting with certain
excavation contractors, local and county planning
groups, and utilities in area
20Risk control activities planned for line L-187
- Conduct CP survey with instrument using results
of corrosion technology evaluation - Install subsidence monitoring equipment at
mainline valve assemblies where currently not
present - Increase pipeline surveillance from monthly to
twice monthly
21Risk control activities planned for line L-176
- Conduct geometry tool and in-line inspection
(smartpig) - Where any class 2 or 3 areas exist, besides
specific class change area, the following will be
done - Install new style ROW markers with spacing not
to exceed 500 feet where possible and practical - Increased emphasis on meeting with certain
excavation contractors, local and county planning
groups, and utilities in area
22Risk control activities planned for line L-176
- Conduct CP survey with instrument using results
of corrosion technology evaluation - Install subsidence monitoring equipment at
mainline valve assemblies where currently not
present - Increase pipeline surveillance from monthly to
twice monthly