Title: Project Management
1Project Management
- Contracts and Procurement
2Outline
- Introduction
- Procurement
- Requirement Cycle
- Requisition Cycle
- Solicitation Cycle
- Award Cycle
3Outline
- Types of Contracts
- Incentive Contracts
- Contract Type versus Risk
- Contract Administration Cycle
- Using a Checklist
- Proposal-Contractual Interaction
4Procurement Strategies
- Corporate procurement strategy the relationship
of specific procurement actions to the corporate
strategy - Project procurement strategy the relationship
of specific procurement actions to the operating
environment of the project
5Procurement Objectives
- Procure all goods/services from a single source.
- Procure all goods/services from multiple sources.
- Procure only a small portion of the goods/
services. - Procure none of the goods/services.
6Procurement Management
- Requirement cycle definition of the boundaries
of the project - Requisition cycle analysis of sources
- Solicitation cycle the bidding process
- Award cycle contractor selection and contract
award - Contract administration cycle managing the
subcontractor until completion of the contract
7Requirement Cycle
- Defining the need for the project
- Development of the statement of work,
specifications, and work breakdown structure - Performing a make or buy analysis
- Laying out the major milestones and the
timing/schedule - Cost estimating, including life-cycle costing
- Obtaining authorization and approval to proceed
8Specifications
- Specifications are written, pictorial, or graphic
information that describe, define, or specify the
services or items to be procured. There are
three types of specifications
9Types of Specifications
- Design specifications These detail what is to
be done in terms of physical characteristics.
The risk of performance is on the buyer. - Performance specifications These specify
measurable capabilities the end product must
achieve in terms of operational characteristics.
The risk of performance is on the contractor.
10Types of Specifications (Continued)
- Functional specifications This is when the
seller describes the end use of the item to
stimulate competition among commercial items, at
a lower overall cost. This is a subset of the
performance specification, and the risk of
performance is on the contractor.
11The Make Decision
- Less costly (but not always!!)
- Easy integration of operations
- Utilize existing capacity that is idle
- Maintain direct control
- Maintain design/production secrecy
- Avoid unreliable supplier base
- Stabilize existing workforce
12The Buy Decision
- Less costly (but not always!!)
- Utilize skills of suppliers
- Small volume requirement (not cost effective to
produce) - Having limited capacity or capability
- Augment existing labor force
- Maintain multiple sources (qualified vendor list)
- Indirect control
13Requisition Cycle
- Evaluating/confirming specifications (are they
current?) - Confirming sources
- Reviewing past performance of sources
- Producing solicitation package
14Solicitation Package
- Bid documents (usually standardized)
- Listing of qualified vendors (expected to bid)
- Proposal evaluation criteria
- Bidder conferences
- How change requests will be managed
- Supplier payment plan
15Solicitation Cycle
- Advertising
- Negotiation
- Small purchases (i.e., office supplies)
16Negotiation Processes
- Request for information (RFI)
- Request for quotation (RFQ)
- Request for proposal (RFP)
17Negotiation Factors
- Compromise ability
- Adaptability
- Good faith
18Negotiation Planning
- Develop objectives (i.e., min-max positions)
- Evaluate your opponent
- Define your strategy and tactics
- Gather the facts
- Perform a complete price/cost analysis
- Arrange hygiene factors
19Negotiation Objective-Setting
Buyer
Min
Objective
Max
Seller
Min
Objective
Max
Price
20Award Cycle
- Conclusion The objective of the award cycle is
to negotiate a contract type and price that will
result in reasonable contractor risk and provide
the contractor with the greatest incentive for
efficient and economic performance.
21Contracting Elements
- Mutual agreement
- Consideration
- Contract capability
- Legal purpose
- Form provided by law
22Contract Forms
- Completion contract
- Term contract
23Contract Selection Criteria
- Overall degree of cost and schedule risk
- Type and complexity of requirement (technical
risk) - Extent of price competition
- Cost/price analysis
- Urgency of the requirements
- Performance period
- Contractors responsibility (and risk)
24Contract Selection Criteria (Continued)
- Contractors accounting system (is it capable of
earned value reporting?) - Concurrent contracts (will my contract take a
back seat to existing work?) - Extent of subcontracting (how much work will the
contractor outsource?)
25Contractors Risks
HIGH
LOW
FFP
CPFF
Risk On Contractor
LEGEND
FFP FIRM FIXED PRICE
CPFF COST PLUS FIXED FEE
26Firm-Fixed-Price Contract (FFP)
- Maximum risk with contractor
- Higher negotiated profit margins
- High likelihood of scope changes
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
27Firm-Fixed-Price With Economic Price Adjustments
(FPE)
- Adjustments for escalation factors
- Adjustments for inflation
- Negotiated adjustment cycle
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
28Incentive Contracts
- Additional profits are possible by lowering cost
- Customer and contractor share cost savings
29Principles of Incentive Contracts
- CUSTOMER PAYS 80 OF OVERRUN
- CONTRACTOR PAY 20 OF OVERRUN
- PROFIT IS 1500 LESS
EXAMPLE
CONTRACTORS 20
TARGET COST 20,000
TARGET FEE 1500
- CUSTOMER KEEPS 80 OF OVERRUN
- CONTRACTOR KEEPS 20 OF OVERRUN
- PROFIT IS 1500 PLUS
SHARING RATIO 80/20
CONTRACTORS 20
NOTE LIMITATIONS MAY BE IMPOSED ON PRICE OR
PROFIT
30Fixed-Price-Incentive-Fee Contract (FPIF)
- Contractor can earn additional profits
- Contract has a ceiling on price (or cost) paid
- Price (or cost) ceiling at point of total
assumption
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
31Cost-Plus-Incentive-Fee Contract (CPIF)
- Contractor can earn additional profits
- All costs are reimbursed (cost run-ups)
- A floor and ceiling exists on profits
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
32Cost-Plus-Award-Fee Contract (CPAF)
- All costs are reimbursed (cost run-ups)
- Negotiated range of possible profits
- Customer determines profit paid at completion
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
33Cost-Plus-Fixed-Fee Contract (CPFF)
- All costs are reimbursed (cost run-ups)
- Fee is fixed (in not ) irrespective of costs
- Contractor is motivated for early completion
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
34Cost-Sharing Contract (CS)
- No profits allowed
- Customer and contractor share costs
- Contractor may retain control of
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
35Cost Contract (C)
- No profits allowed
- Contractor is usually a non-profit organization
- Limitations on costs allowed may be imposed
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
36Cost-Plus-Percentage-Of-Cost Contract (CPPC)
- Costs incurred may be unlimited
- Contractors can maximize profits
- Scope changes may be frequent and unlimited
RISK SHARING METER
100
0
RISK
CONTRACTORS
CUSTOMERS
RISK
RISK
LOCATION
0
100
37Relative Contract Risk
RISK SHARING METER
0
100
FFP
FFE
RISK
RISK
FPIF
CUSTOMERS
CPIF
CONTRACTORS
CPAF
CPPC
CPFF
RISK
CS
LOCATION
C
0
100
38There are several other types of contracts
available. They may be derivatives of these
contracts, combinations, or simply special
contracts for special circumstances.
39Contract Administration Cycle
- Change management
- Specification interpretation
- Adherence to quality
- Warranties
- Subcontractor management
- Production surveillance
- Waivers
- Contract breach
40Contract Administration Cycle (Continued)
- Resolution of disputes
- Project termination
- Payment schedules
- Project closeout
41Order of Precedence
- Specifications (first priority)
- Other instructions (second priority)
- Other documents, such as exhibits, attachments,
appendices, SOW, contract date requirements list
CDRL, etc. (third priority) - Contract clauses (fourth priority)
- The schedule (fifth priority)
42Type of Changes
- Administrative change
- Change order
- Contract modification
- Undefinitized contractual action
- Supplemental agreement
- Constructive change
43Causes of Constructive Changes
- Defective specification with impossibility of
performance - Erroneous interpretation of contract
- Over-inspection of work
- Failure to disclose superior knowledge
- Acceleration of performance
- Late or unsuitable owner or customer furnished
property
44Causes of Constructive Changes
- Failure to cooperate
- Improperly exercised options
- Misusing proprietary data
45Reasons for Termination for Convenience of the
Customer
- Elimination of the requirement
- Technological advances in the state-of-the-art
- Budgetary changes
- Related requirements and/or procurements
- Anticipating profits not allowed
46Reasons for Termination for Default Due to
Contractors Actions
- Contractor fails to make delivery on scheduled
date. - Contractor fails to make progress so as to
endanger performance of the contract and its
terms. - Contractor fails to perform any other provisions
of the contract.
47Contract Administration Rights
- Reject the entire shipment
- Accept the entire shipment (barring latent
defects) - Accept part of the shipment