QPL vs Specification requirements. - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

QPL vs Specification requirements.

Description:

Any repair work done after the erection will be difficult, costly, risky and unsafe. ... Erection during hot weather conditions may pose more challenges ... – PowerPoint PPT presentation

Number of Views:80
Avg rating:3.0/5.0
Slides: 21
Provided by: cn984
Category:

less

Transcript and Presenter's Notes

Title: QPL vs Specification requirements.


1
Critical Construction IssuesBy Rafiq Darji
  • QPL v/s Specification requirements.
  • Steel Girder Erection issues.
  • Picket Railing on Bridges.
  • Concrete Field Technician Level II
    requirements.

2
QPL v/s Specification Requirements
  • Selecting a product from the QPL does not by
    itself constitute final acceptance of that
    product.
  • Final acceptance of a product is granted only
    when it is in full compliance with applicable
    specifications, which may require that the
    product be manufactured by a producer who is
    qualified by the Department and is on the State
    Materials Office (SMO) list of Producers with
    Acceptable QC Programs .
  • The list can be obtained at the following
    website
  • http//www.dot.state.fl.us/statematerialsoffice/qu
    ality/programs/qualitycontrol/materialslistings/po
    stjuly2002.htm


3
  • Currently SMO website has 15 lists depending on
    the category of product. The following is a
    summary of those items on the QPL by category
    that are required to be on an approved producer
    list of the SMO website.
  • Precast Temporary Barrier Wall (Specification
    521), Sound Barrier Panels (Specification 534),
    Retaining Wall Panels (Specification 548) and
    Concrete Strain Poles (Specification 641) SMO
    List Concrete Sources Precast Incidental,
    Drainage and Pipe
  • Galvanizers for Guardrail (Specification 536)
    Roadway Sign Supports (Specification 700-2.3) and
    Light Poles (992-2.1) SMO List Coatings
    Sources
  • Steel Strain Poles, Steel Mast Arms and Monotube
    Assemblies (Specification 649) and Steel and
    Aluminum Light Poles (992-2) SMO List - Metal
    Fabricators
  • Aluminum Pedestrian-Bicycle Railing (Index 860)
    and Aluminum Pipe Guiderail (870) SMO List
    Metal Fabricators


4
  • If the component is not manufactured by a
    producer on the SMO list then even if it appears
    on the QPL, it may not be accepted for use on a
    Department project.
  •  
  • Where required, the product must be stamped by
    the producer which signifies that the product has
    been manufactured in full compliance with the
    producer's QC Plan and the applicable
    specifications and the required certifications.


5
  • Here is an example of typical specification
    requirements.
  • For Prestressed Concrete Poles, the Section 641-1
    says, Obtain precast, prestressed concrete
    poles from a manufacturing plant that is
    currently on the Departments list of qualified
    precast, prestressed concrete plants and listed
    on the Departments Qualified Products List
    (QPL).
  • Look out for a DCE memo that will be issued very
    shortly emphasizing this issue.


6
Steel Girder Erection Issues
  • There has been more than one incident where beams
    did not fit between the end bents or beam seats
    after they were fabricated and erected. Hence,
    the beam ends had to be cut in the field and
    jacking was performed to accommodate the as-built
    conditions.
  • Do your homework prior to erecting the girders
    Verify the as-built locations of the piers and
    beam seats with respect to the plans
    dimensions. If there are any differences, fix
    them in the shop prior to shipping or on the
    ground prior to erecting. Any repair work done
    after the erection will be difficult, costly,
    risky and unsafe.
  • Verify backwall plumbness. Out of plumbness of
    the backwall combined with geometry and
    temperature effects on the girder will pose
    serious fitting issues.


7
  • If any jacking is required to correct the miss
    alignment after the erection, place jacks at the
    plans specified locations. Placing jacks at
    different locations may damage the pier caps
    and/or girders. Communication between the
    Contractor and CEI is very critical in achieving
    the success. Have a meeting prior to jacking
    operations.
  • Erection during hot weather conditions may pose
    more challenges especially for those girders
    where high skew, steep superelevations and tight
    horizontal curvatures exist. Watch out for
    length variations due to temperature rise/fall.
  • If possible, erect girders at fix bearing first.
    Adjustments and fit up at the expansion bearing
    can easily be accommodated due to the presence
    of slotted holes, sliding surfaces, etc.


8
  • Do not apply lateral or longitudinal forces on
    to the girder system without releasing all the
    restrains. Otherwise, you may introduce torsional
    moments into the girder system.
  • Do not force the girders to fit in to the anchor
    bolt holes. Otherwise, this may introduce
    locked-in forces into the girder system.
  • Verify that the anchor bolt block-out locations
    are in compliance with the plan details prior to
    concrete placement.
  • Make sure that the anchor bolt block-out formwork
    is secured and stable during concrete placement
    operations. if it is displaced, new holes needs
    to be cored into the cap, which may damage the
    existing cap steel and may affect the design. An
    Engineers approval will be required prior to any
    coring.


9
Aluminum Pedestrian /Bicycle Picket Railing on
Bridges
  • Due to some recent failures in the welded
    connections of picket railings, the Department
    has modified the Standard Index No. 860 (2008
    version) to allow non-welded connection at the
    top.
  • Previous Index details require welding at both
    top and bottom picket connections.
  • Now, on Bridges only, the index requires
    non-welded connection between the picket and top
    rail and welding connection between the picket
    and bottom rail.
  • Non welded connection is optional for other
    locations such as for roadway applications.


10
Here are some photographs of failed picket rails

11

12

13

14
I encourage incorporating this detail in all
ongoing bridge projects, If this is possible.

Index 860 Non welded Picket and Top Rail
Connection Detail
15
Concrete Field Technician Level II requirements
  • The Specification Section 105-5.7.2 requires a
    level II technician must be present on the
    jobsite during all concrete placements on major
    bridge projects. Prior to the placement of
    concrete, the technician will inspect the element
    to be cast to ensure compliance with Contract
    Documents.
  • The following questions have been raised many
    times on the above requirements,
  • Is this indented to apply only to placements that
    are structural elements of the major bridge as
    opposed to all placements of structural concrete
    anywhere on a project that includes major bridge,
    e.g. inlet tops, etc.?
  • Is the reference to inspection prior to casting
    intended to require that only a level II
    inspector is qualified to do a pre-placement
    inspection or that a level II technician
    supervise the process as with testing plastic
    properties?


16
  • Here are clarifications to those questions
  • The level II requirement applies only to placing
    components of a major bridge and not to all
    placements on a project which includes a major
    bridge. The Specification 105-5.7.2, is intend to
    apply to structural components of major bridges
    including decks, caps, footings, columns, crash
    walls, abutments, barrier walls etc.   The type
    of structures that are considered to be MAJOR are
    defined in Specification
  • 5-1.4.1(e).
  • The Level II Technician must personally inspect
    form work (bracing, alignment, dimensions, etc.),
    rebar placement (positioning, size and quantity),
    screed operation, preparation for curing and
    inclement weather and evaporation rate monitoring
    to name some of the items to be checked, prior to
    the actual placement of concrete.
  • During the actual concrete placement process
    (delivery, sampling, testing, record keeping,
    concrete placement, vibration, screeding,
    finishing, evaporation monitoring, curing, etc.)
    the Level II Technician should be present at the
    site of work in progress.


17
Having said that, one may ask, why is level II
technician not required for minor bridges? Is
this because the quality on minor bridges is not
as important as on major bridges ? There is no
doubt, quality on minor bridges is as important
as on major bridges. But, due to the scarcity of
Level II Technicians, the Contractors would have
a very hard time to find and supply Level II
Technicians for all bridge projects. Hence, the
Department in conjunction with the Contractors
had decided to have this requirement only for
major bridges.

18
Departments Future Direction on the Level II
Requirements
In order to be a Level II qualified, the
Construction Training and Qualification Manual
(CTQM) requires an ACI CTCI certification. This
course is difficult and covers topics other than
bridges, which has been a problem for
Contractors. In order to address this issue, at
present, the ACI is at the final stage of
developing a new course concentrating on roads
and bridges. After the course is finalized and
accepted by the Department (i.e. TRT), the course
will be offered to the public. Once this is
done, a year after this date, the Department will
require Level II technicians for Contractors in
all bridge projects regardless of it being a
minor or a major bridge project. The one year
time is allowed so that the Contractors have
sufficient time to train their personnel and take
the required course.

19
REMINDER
  • Due to variety of quality problems on Category 2
    (C2) construction projects, few years ago, a memo
    (No.17-05) was issued to clarify the role of
    State Construction Structures Engineer (SCSE) on
    C2 bridge construction projects .
  • Require notification and consultation with the
    SCSE by the CEI staff on technical matters such
    as any proposed deviation from the plans and
    specifications Contractor means and methods that
    might adversely impact the performance or
    durability of the finished bridge and Contractor
    proposed corrections of damaged or defective
    structural components.


20
Write a Comment
User Comments (0)
About PowerShow.com