Title: QPL vs Specification requirements.
1Critical Construction IssuesBy Rafiq Darji
- QPL v/s Specification requirements.
- Steel Girder Erection issues.
- Picket Railing on Bridges.
- Concrete Field Technician Level II
requirements.
2QPL v/s Specification Requirements
- Selecting a product from the QPL does not by
itself constitute final acceptance of that
product. - Final acceptance of a product is granted only
when it is in full compliance with applicable
specifications, which may require that the
product be manufactured by a producer who is
qualified by the Department and is on the State
Materials Office (SMO) list of Producers with
Acceptable QC Programs . - The list can be obtained at the following
website - http//www.dot.state.fl.us/statematerialsoffice/qu
ality/programs/qualitycontrol/materialslistings/po
stjuly2002.htm
3- Currently SMO website has 15 lists depending on
the category of product. The following is a
summary of those items on the QPL by category
that are required to be on an approved producer
list of the SMO website. - Precast Temporary Barrier Wall (Specification
521), Sound Barrier Panels (Specification 534),
Retaining Wall Panels (Specification 548) and
Concrete Strain Poles (Specification 641) SMO
List Concrete Sources Precast Incidental,
Drainage and Pipe - Galvanizers for Guardrail (Specification 536)
Roadway Sign Supports (Specification 700-2.3) and
Light Poles (992-2.1) SMO List Coatings
Sources - Steel Strain Poles, Steel Mast Arms and Monotube
Assemblies (Specification 649) and Steel and
Aluminum Light Poles (992-2) SMO List - Metal
Fabricators - Aluminum Pedestrian-Bicycle Railing (Index 860)
and Aluminum Pipe Guiderail (870) SMO List
Metal Fabricators
4- If the component is not manufactured by a
producer on the SMO list then even if it appears
on the QPL, it may not be accepted for use on a
Department project. -
- Where required, the product must be stamped by
the producer which signifies that the product has
been manufactured in full compliance with the
producer's QC Plan and the applicable
specifications and the required certifications.
5- Here is an example of typical specification
requirements. - For Prestressed Concrete Poles, the Section 641-1
says, Obtain precast, prestressed concrete
poles from a manufacturing plant that is
currently on the Departments list of qualified
precast, prestressed concrete plants and listed
on the Departments Qualified Products List
(QPL). - Look out for a DCE memo that will be issued very
shortly emphasizing this issue.
6Steel Girder Erection Issues
- There has been more than one incident where beams
did not fit between the end bents or beam seats
after they were fabricated and erected. Hence,
the beam ends had to be cut in the field and
jacking was performed to accommodate the as-built
conditions. - Do your homework prior to erecting the girders
Verify the as-built locations of the piers and
beam seats with respect to the plans
dimensions. If there are any differences, fix
them in the shop prior to shipping or on the
ground prior to erecting. Any repair work done
after the erection will be difficult, costly,
risky and unsafe. - Verify backwall plumbness. Out of plumbness of
the backwall combined with geometry and
temperature effects on the girder will pose
serious fitting issues.
7- If any jacking is required to correct the miss
alignment after the erection, place jacks at the
plans specified locations. Placing jacks at
different locations may damage the pier caps
and/or girders. Communication between the
Contractor and CEI is very critical in achieving
the success. Have a meeting prior to jacking
operations. - Erection during hot weather conditions may pose
more challenges especially for those girders
where high skew, steep superelevations and tight
horizontal curvatures exist. Watch out for
length variations due to temperature rise/fall. - If possible, erect girders at fix bearing first.
Adjustments and fit up at the expansion bearing
can easily be accommodated due to the presence
of slotted holes, sliding surfaces, etc.
8- Do not apply lateral or longitudinal forces on
to the girder system without releasing all the
restrains. Otherwise, you may introduce torsional
moments into the girder system. - Do not force the girders to fit in to the anchor
bolt holes. Otherwise, this may introduce
locked-in forces into the girder system. - Verify that the anchor bolt block-out locations
are in compliance with the plan details prior to
concrete placement. - Make sure that the anchor bolt block-out formwork
is secured and stable during concrete placement
operations. if it is displaced, new holes needs
to be cored into the cap, which may damage the
existing cap steel and may affect the design. An
Engineers approval will be required prior to any
coring.
9Aluminum Pedestrian /Bicycle Picket Railing on
Bridges
- Due to some recent failures in the welded
connections of picket railings, the Department
has modified the Standard Index No. 860 (2008
version) to allow non-welded connection at the
top. - Previous Index details require welding at both
top and bottom picket connections. - Now, on Bridges only, the index requires
non-welded connection between the picket and top
rail and welding connection between the picket
and bottom rail. - Non welded connection is optional for other
locations such as for roadway applications.
10Here are some photographs of failed picket rails
11 12 13 14I encourage incorporating this detail in all
ongoing bridge projects, If this is possible.
Index 860 Non welded Picket and Top Rail
Connection Detail
15Concrete Field Technician Level II requirements
- The Specification Section 105-5.7.2 requires a
level II technician must be present on the
jobsite during all concrete placements on major
bridge projects. Prior to the placement of
concrete, the technician will inspect the element
to be cast to ensure compliance with Contract
Documents. - The following questions have been raised many
times on the above requirements, - Is this indented to apply only to placements that
are structural elements of the major bridge as
opposed to all placements of structural concrete
anywhere on a project that includes major bridge,
e.g. inlet tops, etc.? - Is the reference to inspection prior to casting
intended to require that only a level II
inspector is qualified to do a pre-placement
inspection or that a level II technician
supervise the process as with testing plastic
properties?
16- Here are clarifications to those questions
- The level II requirement applies only to placing
components of a major bridge and not to all
placements on a project which includes a major
bridge. The Specification 105-5.7.2, is intend to
apply to structural components of major bridges
including decks, caps, footings, columns, crash
walls, abutments, barrier walls etc. The type
of structures that are considered to be MAJOR are
defined in Specification - 5-1.4.1(e).
- The Level II Technician must personally inspect
form work (bracing, alignment, dimensions, etc.),
rebar placement (positioning, size and quantity),
screed operation, preparation for curing and
inclement weather and evaporation rate monitoring
to name some of the items to be checked, prior to
the actual placement of concrete. - During the actual concrete placement process
(delivery, sampling, testing, record keeping,
concrete placement, vibration, screeding,
finishing, evaporation monitoring, curing, etc.)
the Level II Technician should be present at the
site of work in progress.
17Having said that, one may ask, why is level II
technician not required for minor bridges? Is
this because the quality on minor bridges is not
as important as on major bridges ? There is no
doubt, quality on minor bridges is as important
as on major bridges. But, due to the scarcity of
Level II Technicians, the Contractors would have
a very hard time to find and supply Level II
Technicians for all bridge projects. Hence, the
Department in conjunction with the Contractors
had decided to have this requirement only for
major bridges.
18Departments Future Direction on the Level II
Requirements
In order to be a Level II qualified, the
Construction Training and Qualification Manual
(CTQM) requires an ACI CTCI certification. This
course is difficult and covers topics other than
bridges, which has been a problem for
Contractors. In order to address this issue, at
present, the ACI is at the final stage of
developing a new course concentrating on roads
and bridges. After the course is finalized and
accepted by the Department (i.e. TRT), the course
will be offered to the public. Once this is
done, a year after this date, the Department will
require Level II technicians for Contractors in
all bridge projects regardless of it being a
minor or a major bridge project. The one year
time is allowed so that the Contractors have
sufficient time to train their personnel and take
the required course.
19REMINDER
- Due to variety of quality problems on Category 2
(C2) construction projects, few years ago, a memo
(No.17-05) was issued to clarify the role of
State Construction Structures Engineer (SCSE) on
C2 bridge construction projects . - Require notification and consultation with the
SCSE by the CEI staff on technical matters such
as any proposed deviation from the plans and
specifications Contractor means and methods that
might adversely impact the performance or
durability of the finished bridge and Contractor
proposed corrections of damaged or defective
structural components. -
20