Title: SRF Work Packages
1SRF Work Packages
2Accelerating RF Cavity HOM ? BPM
- Naturally narrow band cavity QL 104 , ?? 1
µs - single bunch,
- but not bunch to bunch BPM
Centering accuracy and BPM resolution better
than 50 µm (TTF, 2004)
31) Measurement of cavity alignment in the
cryomodule
- Measuring the Cavity misalignment in Cryomodule
- Experiment performed last week at TTF module 4
(ACC4) - (N. Baboi, J. Frisch, L. Hendrikson, R.
Paparella, et al.) - Accelerating gradients set to zero in all 8
cavities - Reference straight trajectory across the module
set by 2 BPMs on both sides of the module - Modes used TE1116, TE1117, TM1105, TM1106
- PRELIMINARY RESULTS ( problems of reproducibilty
of HOM center reconstruction w.r.t. steering
ranges !! )
41) Monitor cavity alignment in the cryomodule
- PRELIMINARY RESULTS ( problems of reproducibilty
of HOM center reconstruction w.r.t. steering
ranges !! )
52) Inta-cavity Bean Position Monitor
Angular scan resolution and accuracy lt 50 µrad
Relative position resolution 4 µm (cf. M. Ross
and J. Frisch).
63) Trapped modes
- HOM measurements of beam excited trapped mode was
successfully applied to - The detection of the 2.6 GHz dipole mode (Qext
106) - The qualification of superstructures
- It will be necessary if for the qualification of
Low Loss and Reentrant cavity types at SMTF
and STF.
7Two Challenges for HOM-BPM
I) Mode to mode systematics em. centre and
polarisation
Systematic center position offset 100 µm (M.
Dohlus)
last 2 columns reversed !!
Mode center spread 100 µm (TTF measurements,
2004)
8Two Challenges for HOM-BPM
II) Measuring the Pitch of the fondamental
mode The pitch angle between the 1.3 GHz
accelerating mode and the beam trajectory (200
µrad) is the main cause of songle bunch emittance
growth in the linac.
- Can one measure it through the HOM couplers ?
- other monopole modes of the 1st passband through
the 2 ports ?? - systmetics of the dipole mode vs. 1.3 GHz mode
pitchs ??
9HOM-BPM Programme
- Thesis of Rita Paparella (Saclay-DESY) at Orsay
University (Oct. 2003 Sept. 2006) - The 40 cavities of TTF will be equipped with the
SLAC electronics. - Use for the ILC much debatted question 36,
Cost vs. Performance ?
- The association to CARE will allow
- 3-6 months extension of Ritas PhD contract (6
month delay in the thesis program) - Participation of Claire Simon (CARE/SRF temp
stall on WP11/BPM) to the test and commissioning
of the SLAC electronics at SLAC (1 month) and at
DESY - Scientific cross-benefit CARE-ILC to the debate
on HOM monitors
10HOM-BPM Programme
- The 40 cavities of TTF will be equipped with the
SLAC electronics.
Project Cost and Schedule Table 1 TTF VUV-FEL
HOM BPM electronics cost.
The system will be delivered before October 31,
2005. At that time, the group will work at DESY
to commission the system using the TTF beam. The
prototype cycle will be complete July 31, 2005.
11HOM-BPM Programme
- The 40 cavities of TTF will be equipped with the
SLAC electronics.
12New BPM mechanics
- New design of the cavity BPM ( For the cleaning,
12 holes of diameter 5mm have to be added)
- Resonant modes with the new design (simulated
with HFSS)
13Cold Re-entrant BPM
Linearity and Centering Accuracy
New design
Old design
Voltage ?/S a.u
40 µm
Voltage ?/S a.u
Position of the beam (mm)
14SRF/WP1/BPM Planning
- Sept. 05 - Dec. 05 Fabrication of the 1st BPM
cavity (TTF room temperature). - Oct.05 Test and commisioning of the old type
BPM in ACC1 - Oct. 05 - Jan. 06 Fabrication of the 2nd BPM
cavity (TTF cryogenic temperature). - Jan. 06 RF tests with beam at DESY
(installation of the BPM cavity need an
oscilloscope with a bandwidth gt2 GHz). - Feb.06 - Apr. 06 Validation of the RF board
Programming and validation of the digital
electronics. - May 06 - June 06 Tests at DESY (2 weeks) on the
cavity which is at room temperature with its
electronics but without control-command
interface. The tests will be done with
displacement of the beam to know the noise, the
dynamic range and do the calibration of this
system. - Feb. 06 - Sept. 06 Installation and preparation
of the cold BPM cavity. - Oct. 06 Tests of the cold cavity with the beam
and electronics without the control-command
interface. - Nov. 06 - Feb. 07 Programming of the
control-command interface. - March 07 Tests of the cold cavity and its
electronics.