Title: GAIARVS External Interfaces Review
1GAIA-RVS External Interfaces Review
2Agenda
- 1) Introduction MSC
- 2) External interfaces definition overview MSC
- 3) Optical DK/FC
- 4) Mechanical BW
- 5) Thermal BW
- 6) Electrical BKH
- 7) Data structures MSC
- 8) Summary MSC
- 9) Opportunity for presentations by SLTADS
representatives and PDHE contract representative - 10) Discussion on open/non-conformance issues
ALL
3Attendees
- MSSL/UCL
- Mark Cropper
- Berend Winter
- Barry Hancock
- John Coker
- Tony Dibbens
- GEPI/ObsPM
- David Katz
- Fanny Chemla
- Pascal Vola
- Philippe Laporte
- SRC/Leicester
- Tony Abbey
ESA ESTEC Torgeir Paulsen Astrium
Toulouse Frédéric Safa Francois
Chassat Alcatel Bruno Napierala Claude
Israbian Astrium GmbH Christoph Schaefer
4Review Aims
- The aims of the review are
- 1) To identify the external interfaces for RVS
- 2) To provide a specification of these interfaces
wherever this is possible - 3) To identify problematic interfaces and a route
for resolving them - 4) To agree a coherent set of interfaces with
both SLTADS teams.
5Interfaces Overview
6Spectro Hierarchical Diagram
Telescope
RVS
PDHU(VPUsandPDHE)
MBPand MBP Starmapper
Spectro
7RVS Hierarchical Diagram with principal interfaces
8Payload and Service Module thermal
ColdWarmerWarm
2
RVS starmapperproximity electronics
Service Module290K
RVS Starmapper
External harness?
structure
camera
RVS proximity electronics
spectrograph optics
RVS Pre-ProcessingUnit (RPPU)
Mechanism?
structure
structure
Payload Module 160K
radiator
radiator
9Payload and Service Module thermal alternative
RVS starmapperproximity electronics
ColdWarmerWarm
RVS Starmapper
structure
camera
RVS proximity electronics
spectrograph optics
RVS Pre-ProcessingUnit (RPPU)
Mechanism?
structure
Payload Module 160K
radiator
radiator
10MBP and RVS Starmapper Issues
- MBP may have a mechanical and thermal interface
to RVS - RVS Starmapper may have a mechanical and
electronic interface to MBP - RVS Starmapper functionality similar to MBP
functionality - 3 main options
baseline
11Primary Scientific Requirements
- Primary scientific requirement is to obtain
radial velocities for stars in the Galaxy to a
limiting magnitude - Astrophysical information will be obtained for
brighter stars - Wavelength range and resolving power specified
- Spatial resolution requirement is to address
crowding
12RVS Baseline
- We work from Astrium design in System Level
Reassessment Study (July 2002) as in SoW this is
the current baseline - We understand recommendations made by GAIA
Science Team regarding scientific performance at
the faint limits ? we permit the consideration
of a mechanism to correct for the scan law
(mostly internal interface) - We understand that SLTADS teams will have made
substantial progress since December 2002 and some
concepts have changed which will require some
reassessment of external interfaces and
harmonisation between Astrium and Alenia concepts
13Interface review Scanning Law Optics
- F. Chemla and D. Katz (GEPI)
14Scanning law
- Spin motion (6 h)
- Precession motion (70 days)
- Revolution around the sun (1 year)
- Model L. Lindegren (SAG-LL-30)
- Earth orbit eccentricity yes
- motion around L2 no
15Motion in the RVS FoV
- Along scan 60 arcsec/s
- Across scan periodic motion (locally sine P
6h) - average half amplitude 0.168 arcsec/s
velocity drift
16Transverse motion half amplitude
- Maximum half amplitude 0.174 arcsec/s (T0)
- Minimum half amplitude 0.163 arcsec/s (T0 6
months) - Absolute rate error along scan (TBD) First
derivative (TBD) - Absolute rate error across scan (TBD) First
derivative (TBD)
Maximum velocity drift
17Optical Interface telescope focal plane
- Astrium Alenia/Alcatel
- entrance pupil 0.50.5 m2 0.50.5 m2
- exit pupil quasi infin. quasi infin.
- focal length 2.1 m 2.1 m
- FP along scan 74 mm 74 mm
- RVSM along scan 35 mm (TBC) 20 mm
- FP across scan 177 mm (TBC) 180 mm
- (RVS MBP)
- Full 3D allocated volume ? Telescope design ?
18Baseline RVS optical design (SLTRS)
19Quick optimisation
- A quick optimisation has been done
- Distortion slightly better (-20)
- Image quality equivalent
- Dispersion variability is higher
- It appears that an increase of the overall volume
leads to significantly better results in terms
of - Distortion
- Image quality
- Optimisation flexibility
Distortion along scan has not yet been checked
20Mechanism interfaces
- A mechanism might be implemented in order to
cancel the apparent sky motion on the detector
plane due to the GAIA scanning law - Three main options are available for this
mechanism - Rotation mechanism on the CCD
- Rotation mechanism on the grism
- Rotation mechanism on the two reflecting mirrors
of the RVS
21Mechanism possible positions
22Volume issue
- It is very important to know the allocated volume
for the RVS or better, the proximity environment
in order to - Know whether some distances can be increased to
gain optimisation flexibility - Know what folding arrangements are required
23Optics low T qualification
- Development plan
- Identify sensible elements (coatings? Grating?)
- Make a Zemax simulation in order to check
whether - The change in the refracting index is
tolerable - The expansion coefficients is compatible with
the mechanics ones -
- Interfaces
- Cooling velocity TBA
- Refocalisation envisaged TBC
24Optics radiation tolerance (later phases)
- Development plan
- Bibliographic study to gather information on
glasses behaviour under radiation
(manufacturers data, books) - Transmission modification under radiation
- optical index modification under radiation
- Dispersion variation under radiation
- If the two precedent points do not provide
sufficient information ? Tests
- Interfaces
- Radiation intensity 12krad (TBC)
- Radiation type solar protons
- Tolerable darkening, fluorescence and
scintillation TBA
25Mechanical - Thermal - Interface
- John Coker
- Berend Winter
- Mullard Space Science Laboratory
26Contents
- Description of RVS
- Mass
- Stiffness
- Interface
- Mechanism
- Mechanical environment
- Thermal interface
- How to move forward from here?
27Description
- RVS (Radial Velocity Spectrometer)
- A Spectro-telescope is to be fitted below the
main optical bench (torus). The focal plane of
the optical chain M1-M2-M3 is in front of the
entrance aperture of RVS. The optical chain
inside RVS will map the focal plane on one inside
the RVS instrument via a grism. The grism breaks
the beam into a spectrum on the RVS focal plain. - MBP (Medium Band Photometer)
- The location of the MBP (medium band photometer)
is at the aperture of RVS - Starmapper
- The star mapper is also located at the entrance
aperture of the RVS instrument.
28Description - block diagram
Telescope
RVS
PDHU(VPUsandPDHE)
MBPand MBP Starmapper
Spectro
29Description - configurations Astrium envelope
30Description - configurations Alenia/Alcatel
envelope
31Description - configurations
32Description - Lens Mount
33Interface
- We dont have a specified interface yet
- We assume a volume available of about 1.3 x 0.3 x
0.3 m3 (Astrium) and 1.3 x 1.0 x 0.3 m3
(Alenia/Astrium) around the torus - Need to identify mounting fixation points
- Type of fasteners
- Thermal interface definition
- Interface with radiator
- Interface with payload module
- Need a common definition
- We have some hardcopies with overall dimensions
of different configuration for you
34Mass - roadmap
- Design maturity will be reflected in the mass
estimates - Conceptual design 20 uncertainty
- More detailed design for use in trade-offs 10
uncertainty. - Detailed design 5 uncertainty.
- Final detailed design 2 uncertainty or less
- Measured weights less than 1 uncertainty for
units with a mass exceeding 100 gr. Otherwise
accuracy within 1 gram. - On delivery the measured mass will be reported
within measurement accuracy but at least within
1 accurate. During the life of the project the
mass budget will be reported taking into account
the design maturity of the individual components
that make up the overall mass. - During the life of the project the mass budget
will be reported taking into account the design
maturity of the individual components that make
up the overall mass.
35Mass - RVS breakdown
Current allocation including MBP is 42 kg
36RVS - Stiffness
- Baseline is to stay away from main spacecraft
modes - Assumed for the time being is the following
- Main structure modes 120 Hz (goal)
- Main sub structure modes 400 Hz (goal)
- This approach will allow us to use the design
loads as a quasi-static design criterion and will
allow straight forward notching on interface
loads
37Mechanism - Allowable Disturbances
- Rotating Components
- Maximum disturbance torque less than 1 micro-Nm
- We assume this requirement to be valid for all
timescales
38Mechanical Environment
- No mechanical environment specified - we assume
for now - Longitudinal 20 g
- Transverse 10 g
- Sine stepped down after 50 Hz (static input) to
10 g above 70 Hz up to 100 Hz - Allowed to notch on interface forces (not to
exceed design loads) - Random 0.05 g2/Hz between 100 and 300 Hz with 3
dB/Oct ramp up between 20 and 100 Hz. And a -12
dB ramp down to 2000 Hz
39RVS - Alignment budget
- External alignment
- Defocus 2.5 microns (TBC)
- Decentre across scan 1.5 mm (TBC)
- Decentre along scan direction 0.13 mm (TBC)
- Tilt about axis corresponding to cross-scan
direction 0.0004 (TBC) - Other tilt 0.0017 (TBC)
- Inside the RVS instrument optics need to be kept
aligned as follows (TBC) - 50 micron lens spacing
- 200 micron tube location
- 5 micron stability
- Need information of temperature influence on CTE
40Thermal
- Maximum allowed heat flow into spacecraft 1 W
- Thermal stability of the heat flow better than
0.1 of the flux - Heat flow towards radiators TBD
- Radiator area TBD
- Currently about 14 W heat is generated inside the
RVS (excluding MBP) (TBC) - Hence the flow will likely be about 1 W into
payload module and about 13 via the radiators
into space.
41How to move forward?
- Mass is the big issue for now
- We need to find areas where mass can be saved
- We need to assess basic structural properties
- Mass distribution in more detail
- Create simple FEA for main structure resonances
- Continue the thermal analysis
- The basic thermal and structural analysis should
allow us to save mass if possible. Since it will
minimize the interface from a structural/thermal
point of view, stiff and strong enough to meet
required frequency and strength but not more than
that. Minimizes the thermal heat flow. - This will be fed back into the design and updated
mass breakdown.
42How to move forward? - continued
- We need to assess the interface with the s/c in
more detail. Need to convey meetings with
potential s/c primes asap - Also we need to know (soon) if we should take
into account the mounting of the MBP. This will
have an impact on the thermal and mechanical
performance. Or alternatively look at the impact
as part of design trades
43Electrical
44Contents
- Overall concept
- VPU interface
- Power interface
- Power allocation
- Survival heaters/spacecraft monitoring
- EMI requirements
- Grounding
- Radiation issues
- Parts qualification issues
45RVS Option 1 PRIME OPTION
46RVS Option 2
47RVS Option 3
48RVS Option 4
49RPPU Functions
- Data volume reduction
- Co-adding CCD frames with fractional pixel
resolution - Application of windows using co-ordinates from
the star mapper - CCD readout control
- Removal of CCD cosmetic blemishes
- Removal of cosmic ray induced data
- Diagnostic functions
- Mechanism control (with data input from the
VPU/PDHE) - Power conversion and control for RVS and RVSM
- Power dissipation control in RVS and RVSM focal
planes and Proximity electronics - HK data acquisition
50Architecture Options Trade Off
51RVS External Interface Summary
52RPPU-VPU interface
- SpaceWire seems an appropriate interface standard
for SPECTRO and GAIA. - Fast 200Mbits/sec.
- Use of bus routers increase flexibility and fault
tolerance. - Conform to ECSS-E-50-12A.
- LVDS drivers and receivers have good EMI
properties. - Power consumption 5mW per Mbps per link
interface (500mW max).
53Power Dissipation Control
- To maintain power dissipation stability it will
be necessary to implement an active management
system. RVS constantly will consume maximum power
consumption, taking into account transient peaks
and end of life projections. The required
stability of each unit is shown below. - Focal Plane 0.01 over 6 hours TBC
- Proximity Electronics 0.01 over 6 hours TBC
- Service module TBD
54Power distribution
- Single primary power interface
- Power conversion in RPPU and secondary power
distributed to subsystems - RVS Subsytems to regulate and filter power.
55Budgets Power Astrium baseline
56RVSRVSM Power Breakdown TBC(6CCDs with optional
Mechanism)
57Survival Heaters
- RVS will require S/C powered survival heaters,
these will need to be powered when RVS is off. - Dual redundant thermostatic control to avoid
short circuit and open circuit failures. - RVS will require TBD S/C powered temperature
sensors situated at strategic positions on the
RVS. Measurement accuracy TBD.
58Grounding EMC Requirements
- RVS will be galvanically isolated from GAIA S/C
- RVS will convert its own secondary power
- Each Spectro instrument will define its own
secondary reference. - All communication links will have differential
interfaces (SpaceWire LVDS is current loop). - All interconnecting harnesses will have an
overall shield connected to the S/C chassis
59Radiation Issues
- Transfer trajectory total dose very low.
- GAIA total dose for 6 year mission assuming 2mm
Al shielding 12Krads silicon. - Dose mainly solar protons.
- Safety factor of 2 required on total dose.
- Necessary to understand EOL conditions to assess
peak power consumption. - Where possible all technology should be latchup
resistant (precautions must be taken. - Sufficient data in the test report to assess SEU
and SEL effects of selected technologies. - CCD radiation study.
60Parts Qualification
- Use of FPGA technology
- SpaceWire implementation
- Top level project requirements
- COTS component usage
- Proximity electronics ADC selection
61Data Handling
62Telemetry SLTRS (Astrium July 2002)
63Data Format
- Data format will be dispersed spectra from CCD
detectors with spatial width 2 pixels and
spectral extension over 690 pixels, set by
resolution requirement and bandpass (see earlier)
- Data windows around objects are typically 690x3
pixels - Most stars are detected at the limits of
visibility
64Telemetry requirement
- No of stars/sq degree (average) 2900
ESA-SCI(2000)4 - Area of each CCD (one of six) 0.463 sq degree
- No of stars per CCD 29000.463 1340
- Area of each star window 666x3 pixels 1998
pixels - Total pixels with stars per CCD 2677320 pixels
- Total bits for stars per CCD 267732016
- Time taken to read 1 CCD 16.5 sec
- Total bits/sec per CCD 267732016/16.5
2596189 - Total bits/sec for 6 CCDs 62596189
15577134 15.6 Mbit/s (cf 0.824) - Fraction of CCD pixels occupied by stars
2677320/(10004000) 67
65Telemetry Requirement (ctd)
- Telemetry data rate for satellite is 3.6 Mbit/s
(SLTRS Table 5.4A)during one 8hr shift ? 1.2
Mbit/s average per day - Total raw data data rate (payload) 4.6 Mbit/s
- Assumed compression (excl. overhead) 4.6/1.2
3.6 - Assumed allocation to RVS 0.824/3.6 Mbit/s
0.25 Mbit/s(if the compression
allocation is held within RVS). - Ratio of average data rate to allocation
15.6/0.25 65 - ? serious under-allocation of telemetry
resources to RVS
66Data Handling Strategies
- In order to reduce telemetry combine
CCDs factor 6 lossless compression factor 2.
5 select reduced window for faint stars
around Ca lines factor 2 Total factor 3
0 Required 65 ? shortfall is still a
factor 2 on average (worse for peak) - Notes that lossy compression is not a feasible
solution - Note also that since on average 67 of the CCD
is covered with source spectra, it makes more
sense for thermal reasons to read entire CCD all
the time and window subsequently
67Data Interface
- RVS Pre-Processing Unit will supply spectra that
are - Coadded
- Windowed
- Cosmetic and cosmic ray preprocessed
- Windowing will select only the regions around the
Ca triplet lines for fainter (V15 TBC) objects
- RVS compression will take place in PDHU
(lossless) - RVS data structures are TBD. Will probably
consist of nominally formatted data areas with
unwanted areas zerod.
68Summary
69Overview
- We have identified the external interfaces for
GAIA-RVS - We have addressed several options for mechanical
and electronic architecture to investigate impact
of these on the external and internal interfaces - We have made a recommendation as to which option
is preferred in each case
70Overview
- Many of the interfaces are still TBD
(particularly attachment locations and
accommodation). - Many of the interfaces will require revision in
the light of developments within other GAIA
studies - External Interfaces Document (MSSL/GAIA-RVS/SP/001
) will be issued shortly with as many revisions
as are available
71Instrument Resource Budgets
- RVS mass, power and telemetry allocations appear
inadequate - Telemetry Considerable effort already expended
in searching for feasible solutions in telemetry
allocation shortfall subsequent options are
available but significantly impact science and
raise instrument coordination issues
(chequerboard sampling of the sky) - Power Power allocations appear also to be
inadequate even if considering only the RVS focal
plane and proximity electronics RPPU saves power
consumption elsewhere and simplifies interfaces - Mass A significant fraction of the mass
allocation is consumed simply by the spectrograph
optical elements (without cells or support
structure) lower mass solutions here are being
investigated to include - thinner lens elements
- fewer lens elements
- alternative optical concepts
72The mass issue example lower mass optical designs
- Off-axis Schmidt Camera in double-pass (RGB)
73MBP Interface
- The RVSMBP interface is a complex one, including
the respective starmappers and thermal interfaces - No investigation yet on MBP resource allocation
requirements (and not sure whether this is
covered in other GAIA contracts) - There may be some advantages in treating the
RVSMBP as a combined Spectro instrument, but
RVSRVSM can also be treated separately