LCLS Undulator Systems Beam Loss Monitor - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

LCLS Undulator Systems Beam Loss Monitor

Description:

... be used for Two Purposes: ... time shot to shot signal levels and record integrated values up ... Cerenkov medium coupled to a high gain photomultiplier tube ... – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 58
Provided by: Berg53
Category:

less

Transcript and Presenter's Notes

Title: LCLS Undulator Systems Beam Loss Monitor


1
LCLS Undulator SystemsBeam Loss Monitor
  • William Berg ANL/APS Diagnostics Group

2
Introduction
  • Physics Requirements Document Heinz-Dieter Nuhn
    9-28-07
  • (prd 1.4-005-r0 undulator beam loss monitor).
  • Scope Reduction diagnostic to mps detector.
  • Purpose and Requirements.
  • ANL Budget MS (325k detector, ctls interface
    box 100k).
  • Detector Schedule (design nov-dec,drawings
    dec-feb,pro/fab/assy feb-jun,del july, inst
    aug-sep).
  • Organization 4 groups, Group Definition
    (controls, detector, simulation, test
    calibration).
  • Design Highlights and System Overview (detectors
    dynamic 33, static 2, rd fiber1).
  • Detector design details and focus topics.
  • Funds are limited and efforts need to be focused
    to minimize costs (h-dn).

3
BLM Purpose h-dn
  • The BLM will be used for Two Purposes
  • A Inhibit bunches following an above-threshold
    radiation event.
  • B Keep track of the accumulated exposure of the
    magnets in each undulator.
  • Purpose A is of highest priority. BLM will be
    integrated into the Machine Protection System
    (MPS) and requires only limited dynamic range
    from the detectors.
  • Purpose B is also desirable for understanding
    long-term magnet damage in combination with the
    undulator exchange program but requires a large
    dynamic range for the radiation detector (order
    of 106 ) and much more sophisticated diagnostics
    hard and software.

4
BLM requirements pk
  • Primary function of the BLM is to indicate to the
    MPS if losses exceed preset thresholds.
  • MPS processor will rate limit the beam according
    to which threshold was exceeded and what the
    current beam rate is.Beam Current threshold
    determination?
  • The thresholds will be empirically determined by
    inserting a thin obstruction upstream of the
    undulator.
  • Simulation of losses and damage in the undulator
    will proceed in parallel with the present effort.

5
ANL Draft BLM Budget
  • 425k MS Total
  • 325k Detector Development
  • detectors
  • mounting and slide systems
  • cables and fiber
  • 100k Controls Interface Box

6
Draft schedule
7
LCLS MPS Beam Loss Monitor System
Engineer W. Berg Cost Account Manager G.
Pile Technical Manager D. Walters
Scientific advisor P. Krejcik FEL
Physics H. Nuhn Scientific advisor B. Yang
FEL Physics P. Emma
Controls/MPS Group Lead (ctls) J.
Stein Lead (mps) A. Alacron
Detector Group Lead W. Berg
Simulations and analysis Group Lead J. Dooling
Testing and Calibration Group
Lead B. Yang
W. Berg J. Bailey J. Dooling L. Moog
L. Emery M. Santana J. Vollaire B. Yang
A. Brill L. Erwin R. Keithley J. Morgan
M. Brown R. Diviero J. Dusatko S. Norum A.
Pietryla
Slac employee
8
MPS Beam Loss Monitor Group Functions
  • Controls Group J Stein, A. Alacron
  • Develop BLM control and mps system
  • Interface Box and Control.
  • PMT Signal Conditioning.
  • Control and MPS Integration and User Displays.
  • Detector Group W. Berg
  • Develop Detector and Machine Integration.
  • Simulations and Analysis Group J. Dooling
  • Provide collaborative blm simulation support and
    test analysis.
  • Test and Calibration Group B. Yang
  • Provide beam based hardware testing programs and
    calibration plan.

9
System Design Highlights
  • 33 distributed detectors (one preceding each
    undulator segment), two static units (up and
    downstream of undulator hall). One additional
    channel reserved for rd fiber based system.
  • MPS threshold detection and beam rate limiting.
  • Single pulse detection and mps action up to max
    120Hz beam rep rate via dedicated mps link.
  • Monitoring of real time shot to shot signal
    levels and record integrated values up to one
    second.
  • Heart beat led pulser for system validation
    before each pulse up to full rep rate (pseudo
    calibration).
  • Remote sensitivity adjust (dynamic range) by
    epics controlled PMT dc power supply (600-1200V).
  • Calibrated using upstream reference foil (initial
    use cal will be determined from simulation
    studies).

10
Detector Design Highlights
  • Cerenkov Radiation Based (x-ray beam noise
    immunity).
  • Employs PMT for high sensitivity to beam losses.
  • Dynamic detector (tracks with undulator) 100mm
    stroke. Undulator position (in/out) detection
    will be used to set the corresponding mps
    threshold levels.
  • Manual static insertion option via detachable arm
    for special calibration and monitoring.
  • Large area sensor (coverage of the full
    horizontal width of the top and bottom magnet
    blocks).
  • Fiber Out for low gain upgrade (full integration
    and dyn range diagnostic), control system
    expandable to 80 channels.
  • Radiation hard components (materials and
    electronics).

11
BLM Interconnect Diagram m. brown
12
Interface Box Location
13
Plan View of Short Drift
14
BFW Pump Out Port Relocation
15
Removable Pin for Manual Insertion
16
Undulator Inserted Position
17
Undulator Retracted Position
18
Pin Function
19
Detector Pin Detail
20
Rendering of Detector
21
  • Cross Section of BLM Detector

22
Cerenkov Radiator
23
Magnet Block Sensor Coverage
24
Proposed PMT Device -04 (420nm)
25
Vendor List
  • Radiator Substrate water jet and final polish
    (lap and flame) (quartz)- VA Optical
  • Radiator AlSi coating Eddy Company
  • Radiator Material - Corning
  • PMT and Magnetic Shield - Hamamatsu
  • Connectors
  • SMA Fiber Feed through) -Thor Labs
  • High Voltage Feed through - Kings
  • SMB Signal Fed through - AMP
  • Fiber Optic Cable (heartbeat) Fiber (fused
    silica) - Stocker Yale
  • Fiber Optics Cable, UV Grade Coastal
    Connections
  • Signal Cable Belden
  • Body Fabrication- M1, High Tech, AJR Industries
  • Miscellaneous Hardware (fasteners, o-rings, flex
    coupling, spanner wrench) McMaster-Carr
  • Linear Bearing Assembly IKO International
  • Spherical Bearing Aurora Bearing

26
UV Grade Fiber
27
Fused Silica Radiator
28
BLM System Support Focus Topics
  • Funding of beam based prototyping and test
    program.
  • Implementation of upstream calibration foil (alt.
    profile monitor/halo).
  • BFW prototype tolerance verification (system
    tolerance in LTT)

29
BLM Summary
  • Undulator magnets protection is critical for
    machine commissioning period.
  • BLM system is now defined as a component of the
    mps (descope) with an upgrade path to a
    diagnostic (low gain detector).
  • Calibration plan and hardware is vital to proper
    system operation (threshold detection will use
    empirically derived levels).
  • Schedule for development of the blm program is
    very aggressive and funding is limited.

30
Detector Summary
  • Building a detector based on cerenkov radiation
    and PMT detection.
  • 36 distributed channels (2 static devices)
    capable of single pulse detection (up to full rep
    rate) with rate limiting reaction.
  • Detectors dynamically track with undulator
    position with manual detach option to remain in a
    fully inserted static position.
  • Adjustable PMT sensitivity with remotely
    controlled high voltage power supply.
  • Keep alive system test (led pulser) before each
    beam pulse.
  • All Vendors have been identified, Quotes in
    progress, Drawing set being reviewed.
  • Installation does not require access into the
    vacuum system or removal of other components.

31
  • End of Presentation

32
(No Transcript)
33
Parts Animation
34
Undulator System
35
BLM System Support Focus Topics
  • 1. Assignment of Eric Norum to controls design
    oversight and testing.
  • 2. Funding of beam based prototyping and test
    program.
  • 3. Group Leaders to significantly step up direct
    involvement in system oversight,
    program implementation, and schedule tracking
    (controls n. arnold, diag g. decker, lcls g.
    pile, ops/analysis m. borland).
  • Active participation in simulations and
    simulation priority from slac.
  • Implementation of upstream profile monitor (halo
    or at min. cal foil).
  • Adequate analysis and shielding of upstream beam
    dump.
  • Develop long term collaboration plan for the
    pursuit of determining magnet damage mechanisms
    and thresholds via empirical methods.
  • Determine need and priority of BLM signal
    integration (diagnostic).
  • BFW prototype verification (system tolerance LTT)

36
Summary
  • Undulator magnets protection is critical for
    machine commissioning period.
  • Schedule for development of the blm program is
    very aggressive and funding is limited.
  • System design and fabrication must go in parallel
    with simulation and testing program.
  • Consider Minimum requirements for first level
    implementation. Taking advantage of existing
    mps infrastructure.
  • BLM system is now defined as a component of the
    mps with an upgrade path to a diagnostic (low
    gain detector).
  • 36 distributed channels (2 static devices)
    capable of single pulse detection and rate
    limiting reaction.
  • Detectors track with undulator position with
    detach option for manual operation.
  • Calibration plan and hardware is vital to proper
    system operation (threshold detection will use
    empirically derived levels).
  • Quotes in progress
  • Drawing set being reviewed

37
BLM Controls Architecture pk
  • The BLM PMT interfaces to the MPS link node
    chassis.
  • The IO board of the MPS link node chassis
    provides the ADC DAC for the PMT.
  • A detector interface box (pmt, led pulser, sig
    con?) is the treaty point between the MPS and the
    undulator BLM.
  • There are 5 link node chasses serving up to 8
    BLMs along the undulator (expandable from 8 to16
    channels).

38
Undulator Hardware
39
Beam Loss Monitors with Link Nodes
  • Use Link Node to
  • support analog I/O IndustryPack modules
  • provide analog readouts to control system
  • set threshold levels
  • control HV power supplies
  • control LED Pulser

40
Segment Design Layout m. brown
41
Locking Pin Detail
(moves with undulator)
Flex Joint
Spherical Bearing
42
Beam Loss Monitors using Link Nodes
43
Beam Loss Monitor - Undulator Hardware (m. brown)
In Undulator Hall
Long Haul Cables
44
Proposed PIC / BLM Timing
45
Link Node Block Diagram
46
(No Transcript)
47
(No Transcript)
48
Undulator Protection Requirements
  • Inputs to inhibit the e-beam
  • Primary protection from a number of Beam Loss
    Monitors (BLMs) along the undulator
  • Secondary protection from control system
    monitoring of
  • BPM orbit
  • Magnet power supply status
  • Magnet mover status
  • Long-term monitoring of the radiation dose
  • Dosimeters attached to the magnets

49
BLM Rolls Out with Undulator Magnet
  • The BLM is mounted to tightly surround the vacuum
    pipe near the beam finder wire
  • It is on a linear slide so that it can be moved
    off the beam when the undulator magnet is rolled
    out
  • An detachable arm makes the BLM and magnet roll
    out together
  • The BLM will automatically be less sensitive to
    beam loss when the undulator is in the out
    position
  • The BLM can be manually inserted on the beam pipe
    for special calibration procedures

50
BLM Specification
  • A single BLM will be placed in each of the gaps
    between undulator modules.
  • Design is to maximize the sensitivity of the
    monitor
  • Located as close as possible to the beam axis as
    the vacuum chamber allows
  • Choose a sensitive Cerenkov medium coupled to a
    high gain photomultiplier tube
  • The detector will not be segmented to provide
    transverse position information of the losses

51
BLM reliability and self test
  • Each loss monitor is equipped with a LED that
    flashes between beam pulses.
  • Provides a pre-beam test of the BLM system before
    beam is sent through the undulator
  • Provides a stay-alive signal for the control
    system to monitor the BLM system during operation

52
BLM dynamic range
  • For simplicity and cost the BLM will be optimized
    for maximum sensitivity
  • And allowed to saturate the signal if a large
    loss occurs
  • The trip threshold is still exceeded if the
    device saturates so the MPS will still trip and
    protect the undulator
  • Monitoring of the loss signal to integrate the
    dose received by the undulator will not be valid
    if the device saturates
  • However, if large losses are anticipated such as
    when the beam finder wires are inserted, the gain
    of the PMT will be reduced to prevent saturation.

53
BLM Signal Monitoring
  • The BLM has a fast, dedicated link to the MPS to
    shutoff the beam within 1 pulse
  • The local MPS link node chassis also has a slow
    network connection to the control system via
    channel access
  • Allows monitoring of the BLM level at any time
  • Reads back and controls the PMT voltage
  • Controls the LED test pulse
  • Controls the threshold set point for MPS trips

54
BLM Controls Architecture
  • The BLM PMT interfaces to the MPS link node
    chassis
  • The IO board of the MPS link node chassis
    provides the ADC DAC for the PMT
  • A cable interface box is the treaty point between
    the MPS and the undulator BLM
  • There are 5 (? verify this number) link node
    chasses serving up to 8 BLMs along the undulator
    (a diagram would help here)

55
Future expansion
  • The link node chassis can handle more than the
    present number of installed BLMs
  • During commissioning a long fiber BLM will also
    be tested
  • It is compatible with the link node chassis
    controls

56
MPS Overview (m. brown)
57
System Roll
Write a Comment
User Comments (0)
About PowerShow.com