Title: LCLS Undulator Systems Beam Loss Monitor
1LCLS Undulator SystemsBeam Loss Monitor
- William Berg ANL/APS Diagnostics Group
2Introduction
- Physics Requirements Document Heinz-Dieter Nuhn
9-28-07 - (prd 1.4-005-r0 undulator beam loss monitor).
- Scope Reduction diagnostic to mps detector.
- Purpose and Requirements.
- ANL Budget MS (325k detector, ctls interface
box 100k). - Detector Schedule (design nov-dec,drawings
dec-feb,pro/fab/assy feb-jun,del july, inst
aug-sep). - Organization 4 groups, Group Definition
(controls, detector, simulation, test
calibration). - Design Highlights and System Overview (detectors
dynamic 33, static 2, rd fiber1). - Detector design details and focus topics.
- Funds are limited and efforts need to be focused
to minimize costs (h-dn).
3BLM Purpose h-dn
- The BLM will be used for Two Purposes
- A Inhibit bunches following an above-threshold
radiation event. - B Keep track of the accumulated exposure of the
magnets in each undulator. - Purpose A is of highest priority. BLM will be
integrated into the Machine Protection System
(MPS) and requires only limited dynamic range
from the detectors. - Purpose B is also desirable for understanding
long-term magnet damage in combination with the
undulator exchange program but requires a large
dynamic range for the radiation detector (order
of 106 ) and much more sophisticated diagnostics
hard and software.
4BLM requirements pk
- Primary function of the BLM is to indicate to the
MPS if losses exceed preset thresholds. - MPS processor will rate limit the beam according
to which threshold was exceeded and what the
current beam rate is.Beam Current threshold
determination? - The thresholds will be empirically determined by
inserting a thin obstruction upstream of the
undulator. - Simulation of losses and damage in the undulator
will proceed in parallel with the present effort.
5ANL Draft BLM Budget
- 425k MS Total
- 325k Detector Development
- detectors
- mounting and slide systems
- cables and fiber
- 100k Controls Interface Box
6Draft schedule
7 LCLS MPS Beam Loss Monitor System
Engineer W. Berg Cost Account Manager G.
Pile Technical Manager D. Walters
Scientific advisor P. Krejcik FEL
Physics H. Nuhn Scientific advisor B. Yang
FEL Physics P. Emma
Controls/MPS Group Lead (ctls) J.
Stein Lead (mps) A. Alacron
Detector Group Lead W. Berg
Simulations and analysis Group Lead J. Dooling
Testing and Calibration Group
Lead B. Yang
W. Berg J. Bailey J. Dooling L. Moog
L. Emery M. Santana J. Vollaire B. Yang
A. Brill L. Erwin R. Keithley J. Morgan
M. Brown R. Diviero J. Dusatko S. Norum A.
Pietryla
Slac employee
8 MPS Beam Loss Monitor Group Functions
- Controls Group J Stein, A. Alacron
- Develop BLM control and mps system
- Interface Box and Control.
- PMT Signal Conditioning.
- Control and MPS Integration and User Displays.
- Detector Group W. Berg
- Develop Detector and Machine Integration.
- Simulations and Analysis Group J. Dooling
- Provide collaborative blm simulation support and
test analysis. - Test and Calibration Group B. Yang
- Provide beam based hardware testing programs and
calibration plan.
9System Design Highlights
- 33 distributed detectors (one preceding each
undulator segment), two static units (up and
downstream of undulator hall). One additional
channel reserved for rd fiber based system. - MPS threshold detection and beam rate limiting.
- Single pulse detection and mps action up to max
120Hz beam rep rate via dedicated mps link. - Monitoring of real time shot to shot signal
levels and record integrated values up to one
second. - Heart beat led pulser for system validation
before each pulse up to full rep rate (pseudo
calibration). - Remote sensitivity adjust (dynamic range) by
epics controlled PMT dc power supply (600-1200V). - Calibrated using upstream reference foil (initial
use cal will be determined from simulation
studies).
10Detector Design Highlights
- Cerenkov Radiation Based (x-ray beam noise
immunity). - Employs PMT for high sensitivity to beam losses.
- Dynamic detector (tracks with undulator) 100mm
stroke. Undulator position (in/out) detection
will be used to set the corresponding mps
threshold levels. - Manual static insertion option via detachable arm
for special calibration and monitoring. - Large area sensor (coverage of the full
horizontal width of the top and bottom magnet
blocks). - Fiber Out for low gain upgrade (full integration
and dyn range diagnostic), control system
expandable to 80 channels. - Radiation hard components (materials and
electronics).
11BLM Interconnect Diagram m. brown
12Interface Box Location
13Plan View of Short Drift
14BFW Pump Out Port Relocation
15Removable Pin for Manual Insertion
16Undulator Inserted Position
17Undulator Retracted Position
18Pin Function
19Detector Pin Detail
20Rendering of Detector
21- Cross Section of BLM Detector
22Cerenkov Radiator
23Magnet Block Sensor Coverage
24Proposed PMT Device -04 (420nm)
25Vendor List
- Radiator Substrate water jet and final polish
(lap and flame) (quartz)- VA Optical - Radiator AlSi coating Eddy Company
- Radiator Material - Corning
- PMT and Magnetic Shield - Hamamatsu
- Connectors
- SMA Fiber Feed through) -Thor Labs
- High Voltage Feed through - Kings
- SMB Signal Fed through - AMP
- Fiber Optic Cable (heartbeat) Fiber (fused
silica) - Stocker Yale - Fiber Optics Cable, UV Grade Coastal
Connections - Signal Cable Belden
- Body Fabrication- M1, High Tech, AJR Industries
- Miscellaneous Hardware (fasteners, o-rings, flex
coupling, spanner wrench) McMaster-Carr - Linear Bearing Assembly IKO International
- Spherical Bearing Aurora Bearing
26UV Grade Fiber
27Fused Silica Radiator
28BLM System Support Focus Topics
- Funding of beam based prototyping and test
program. - Implementation of upstream calibration foil (alt.
profile monitor/halo). - BFW prototype tolerance verification (system
tolerance in LTT)
29BLM Summary
- Undulator magnets protection is critical for
machine commissioning period. - BLM system is now defined as a component of the
mps (descope) with an upgrade path to a
diagnostic (low gain detector). - Calibration plan and hardware is vital to proper
system operation (threshold detection will use
empirically derived levels). - Schedule for development of the blm program is
very aggressive and funding is limited.
30Detector Summary
- Building a detector based on cerenkov radiation
and PMT detection. - 36 distributed channels (2 static devices)
capable of single pulse detection (up to full rep
rate) with rate limiting reaction. - Detectors dynamically track with undulator
position with manual detach option to remain in a
fully inserted static position. - Adjustable PMT sensitivity with remotely
controlled high voltage power supply. - Keep alive system test (led pulser) before each
beam pulse. - All Vendors have been identified, Quotes in
progress, Drawing set being reviewed. - Installation does not require access into the
vacuum system or removal of other components.
31 32(No Transcript)
33Parts Animation
34Undulator System
35BLM System Support Focus Topics
- 1. Assignment of Eric Norum to controls design
oversight and testing. - 2. Funding of beam based prototyping and test
program. - 3. Group Leaders to significantly step up direct
involvement in system oversight,
program implementation, and schedule tracking
(controls n. arnold, diag g. decker, lcls g.
pile, ops/analysis m. borland). - Active participation in simulations and
simulation priority from slac. - Implementation of upstream profile monitor (halo
or at min. cal foil). - Adequate analysis and shielding of upstream beam
dump. - Develop long term collaboration plan for the
pursuit of determining magnet damage mechanisms
and thresholds via empirical methods. - Determine need and priority of BLM signal
integration (diagnostic). - BFW prototype verification (system tolerance LTT)
36Summary
- Undulator magnets protection is critical for
machine commissioning period. - Schedule for development of the blm program is
very aggressive and funding is limited. - System design and fabrication must go in parallel
with simulation and testing program. - Consider Minimum requirements for first level
implementation. Taking advantage of existing
mps infrastructure. - BLM system is now defined as a component of the
mps with an upgrade path to a diagnostic (low
gain detector). - 36 distributed channels (2 static devices)
capable of single pulse detection and rate
limiting reaction. - Detectors track with undulator position with
detach option for manual operation. - Calibration plan and hardware is vital to proper
system operation (threshold detection will use
empirically derived levels). - Quotes in progress
- Drawing set being reviewed
37BLM Controls Architecture pk
- The BLM PMT interfaces to the MPS link node
chassis. - The IO board of the MPS link node chassis
provides the ADC DAC for the PMT. - A detector interface box (pmt, led pulser, sig
con?) is the treaty point between the MPS and the
undulator BLM. - There are 5 link node chasses serving up to 8
BLMs along the undulator (expandable from 8 to16
channels).
38Undulator Hardware
39Beam Loss Monitors with Link Nodes
- Use Link Node to
- support analog I/O IndustryPack modules
- provide analog readouts to control system
- set threshold levels
- control HV power supplies
- control LED Pulser
40Segment Design Layout m. brown
41Locking Pin Detail
(moves with undulator)
Flex Joint
Spherical Bearing
42Beam Loss Monitors using Link Nodes
43Beam Loss Monitor - Undulator Hardware (m. brown)
In Undulator Hall
Long Haul Cables
44Proposed PIC / BLM Timing
45Link Node Block Diagram
46(No Transcript)
47(No Transcript)
48Undulator Protection Requirements
- Inputs to inhibit the e-beam
- Primary protection from a number of Beam Loss
Monitors (BLMs) along the undulator - Secondary protection from control system
monitoring of - BPM orbit
- Magnet power supply status
- Magnet mover status
- Long-term monitoring of the radiation dose
- Dosimeters attached to the magnets
49BLM Rolls Out with Undulator Magnet
- The BLM is mounted to tightly surround the vacuum
pipe near the beam finder wire - It is on a linear slide so that it can be moved
off the beam when the undulator magnet is rolled
out - An detachable arm makes the BLM and magnet roll
out together - The BLM will automatically be less sensitive to
beam loss when the undulator is in the out
position - The BLM can be manually inserted on the beam pipe
for special calibration procedures
50BLM Specification
- A single BLM will be placed in each of the gaps
between undulator modules. - Design is to maximize the sensitivity of the
monitor - Located as close as possible to the beam axis as
the vacuum chamber allows - Choose a sensitive Cerenkov medium coupled to a
high gain photomultiplier tube - The detector will not be segmented to provide
transverse position information of the losses
51BLM reliability and self test
- Each loss monitor is equipped with a LED that
flashes between beam pulses. - Provides a pre-beam test of the BLM system before
beam is sent through the undulator - Provides a stay-alive signal for the control
system to monitor the BLM system during operation
52BLM dynamic range
- For simplicity and cost the BLM will be optimized
for maximum sensitivity - And allowed to saturate the signal if a large
loss occurs - The trip threshold is still exceeded if the
device saturates so the MPS will still trip and
protect the undulator - Monitoring of the loss signal to integrate the
dose received by the undulator will not be valid
if the device saturates - However, if large losses are anticipated such as
when the beam finder wires are inserted, the gain
of the PMT will be reduced to prevent saturation.
53BLM Signal Monitoring
- The BLM has a fast, dedicated link to the MPS to
shutoff the beam within 1 pulse - The local MPS link node chassis also has a slow
network connection to the control system via
channel access - Allows monitoring of the BLM level at any time
- Reads back and controls the PMT voltage
- Controls the LED test pulse
- Controls the threshold set point for MPS trips
54BLM Controls Architecture
- The BLM PMT interfaces to the MPS link node
chassis - The IO board of the MPS link node chassis
provides the ADC DAC for the PMT - A cable interface box is the treaty point between
the MPS and the undulator BLM - There are 5 (? verify this number) link node
chasses serving up to 8 BLMs along the undulator
(a diagram would help here)
55Future expansion
- The link node chassis can handle more than the
present number of installed BLMs - During commissioning a long fiber BLM will also
be tested - It is compatible with the link node chassis
controls
56MPS Overview (m. brown)
57System Roll