1'6 Quality Management Project Preparation Phase - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

1'6 Quality Management Project Preparation Phase

Description:

The purpose of this work package is to provide final verification of all prior ... project team should be scheduled for both level one and level two training. ... – PowerPoint PPT presentation

Number of Views:64
Avg rating:3.0/5.0
Slides: 28
Provided by: pc75278
Category:

less

Transcript and Presenter's Notes

Title: 1'6 Quality Management Project Preparation Phase


1
1.6 Quality Management Project Preparation Phase
2
What is Quality Management Project Preparation
Phase?
  • Its part of Phase 1 Project Preparation
  • The purpose of this phase is to provide initial
    planning and preparation for your SAP project.
    Although each SAP project has its own unique
    objectives, scope and priorities, the steps in
    Phase 1 help identify and plan the primary focus
    areas to be considered.
  • As you prepare for your SAP implementation,
    there are important issues you must address at
    the beginning of the project, including

3
  • Defining your project goals and objectives
  • Clarifying the scope of your implementation
  • Defining your implementation strategy
  • Defining the overall project schedule and
    implementation sequence
  • Establishing the project organization and
    committees
  • Assigning resources
  • By addressing these issues early in your
    implementation, you help ensure that the
    project proceeds efficiently, and that you have
    established a solid foundation for a successful
    SAP implementation.

4
  • Phase 1 consists of the following work packages
  • 1-1 Initial Project Planning
  • 1-2 Project Procedures
  • 1-3 Create Training Plans
  • 1-4 Project Kickoff
  • 1-5 Technical Requirements Planning
  • 1-6 Quality Check Project Preparation Phase

5
(No Transcript)
6
Overview
  • What is Quality Management Project Preparation
    Phase?
  • 1.6.1 Perform Quality Check and Obtain
    Approval
  • 1.6.1.1 Conduct Quality Check
  • 1.6.1.2 Signoff Project Preparation

7
Quality Management Project Preparation Phase
  • Quality Check Project Preparation Phase
  • The purpose of this work package is to provide
    final verification of all prior project planning
    and deliverables from this phase. Its critical
    that regular quality checks be performed
    throughout the phase, as tasks are completed. All
    issues regarding scope, project environment and
    initial technical setup must be addressed.

8
1.6.1 Perform Quality Check and Obtain
Approval The purpose of this activity is to
collect all deliverables and to review them
together for completeness and accuracy. Quality
checks are performed as specific tasks are
completed. However, it is also critical to review
deliverables in total because individual results
from one task can have an adverse impact in
another area of the project. Upon completion of
this quality check, signoff is obtained and the
project proceeds to the next phase.
9
Trigger Phase 1 activities have been
completed Input Phase 1 deliverables Output Comp
leted and formal signoff of Phase
1 Outcome Approval to proceed to Phase 2  
10
1.6.1.1 Conduct Quality Check
  • The purpose of this task is to collect and
    review the status of all deliverables from this
    phase to ensure that all activities, tasks, and
    deliverables are complete.
  • This is an internal quality check carried out
    by the project manager and should not be confused
    with Determine Quality Assurance Standards, which
    addresses external, independent quality checks.

11
Steps
  • Review project charter and verify completeness
  • The project charter needs to address the
    project mission statement, business drivers, and
    business and project measurements.
  • Verify that an implementation strategy has been
    chosen
  • Ensure that the project team room has all
    necessary components
  • If necessary, review the Project Room
    Requirements White Paper.

12
Steps
  • Verify that needed project team roles are filled
  • Review the project plan components for
    completeness
  • The project plan consists of three different
    parts the work plan, the budget plan, and the
    resource plan.
  • Review the organizational change management plan

13
Steps
  • Review the project team training plan
  • At this point, the project team should be
    scheduled for both level one and level two
    training. If possible, it is recommended that
    level two training begins before Business
    Blueprinting. This helps the team visualize their
    business processes using an SAP system.
  • Validate that all project management standards
    and procedures have been created
  • The standards for project communication,
    documentation, issue and scope management, team
    building, project planning and monitoring, and
    quality assurance need to be reviewed. Make sure
    that owners are identified for issue and scope
    management and that procedures are in place for
    addressing issues and changes in scope.

14
Steps
  • Validate that all implementation standards and
    procedures are created
  • Standards for system configuration, end
    user training and documentation, testing,
    post-implementation support, and system
    authorizations need to be reviewed. Also, the
    system problems and errors handling, and the
    system enhancement and modification approval
    process, need to be reviewed.
  • Make sure the project kickoff has occurred, or is
    scheduled
  • Verify that the system landscape strategy is
    agreed
  • The landscape strategy includes the
    number of required systems, client deployment
    strategy, release strategy, and transport system
    strategy.
  • Validate that the initial system is installed and
    remote connection is ordered

15
Result and Tips
  • Result
  • Reviewed Phase 1 deliverables
  • Tips
  • At this time, it is beneficial to use the
    SAP Concept Check Tool to help analyze the
    organization and critical factors in the Project
    Preparation Phase. It covers the following
    topics
  • Project organization
  • SAP system infrastructure
  • Client concept
  • General reporting limits
  • The current analysis focuses on project
    organization and performance-critical factors.
    You perform analyses by completing checklists.
    After completing each checklist, you receive a
    report, which has to be discussed with the
    project management. The report provides important
    information for the project organization.

16
People involved
  • Team SAP Project Manager
  • Description
  • Assist the customer project manager in the
    definition and execution of project deliverables
    and the day-to-day management of the entire
    project. The TeamSAP project manager is the main
    liaison for the TeamSAP members including the
    steering committee, project sponsor, and partner
    management as appropriate.
  • The TeamSAP project manager must be able to
    proactively anticipate project deviations with
    the customer project manager, communicate such
    deviations when appropriate to steering committee
    members, project sponsor, and TeamSAP management
    and facilitate taking immediate corrective
    action.
  • The TeamSAP project manager is responsible
    for the ongoing management of SAP resources
    assigned to the project and for the tracking of
    the SAP consulting budget.

17
  • Customer Project Manager
  • Description

The customer project manager owns the project
deliverables and is responsible for day-to-day
project management. The customer project manager
is the primary liaison with the steering
committee and project sponsor, as well as the SAP
(or partner) consulting team. Most SAP
implementation projects have both an TeamSAP
project manager and a customer project manager
(this should always be the case to assure the
coordination of the customer project team as well
as the communication channels). The
responsibilities outlined below should be split
between the two project managers, based on the
skill sets and experience levels of both
individuals. This division of responsibilities
varies from project to project. The TeamSAP
project manager and the customer project manager
should work in a very close relationship during
the entire project. An open and cooperative way
of working is particularly important for these
two parties.
18
The customer project manager must proactively
anticipate project deviations and be responsible
for taking immediate corrective action. It is
also the customer project managers
responsibility to obtain an understanding of the
overall system business process integration in
the companys environment. The customer project
manager is a member of the steering committee and
must be fully supported by that body. The
customer project manager has (together with the
TeamSAP project manager) the power/right to
decide on all project relevant issues and the
budget. He escalates the strategical issues to
the sponsor for a common decision. The regular
decisions are his domain (empowerment). Depending
on the situation, the customer project manager
may participate as part of a change management
team.
19
  • SAP Reviewer
  • Description
  • The SAP reviewer is responsible for evaluating
    the project at milestone or end of phase dates.
    The review role should be taken by an experienced
    project manager (or higher level individual) from
    outside the project. A SAP (or partner)
    consulting manager is ideal. The reviewer
    conducts periodic project reviews assessing the
    following
  • Adherence to the project implementation
    strategy i.e. the project does not drift away
    from its original goals and business objectives
  • Identify risks which may impact the successsful
    implementation of the solution and propose
    corrective action

20
  • Effective use of the AcceleratedSAP methodology
    and tools
  • Project progress compared to plan milestone
    achievement
  • Deliverables quality, and conformance to the
    documented approval process
  • Project team, steering committee, and any other
    project dynamics for example, assessing the
    Team structure and performance

21
The reviewer provides an objective view of the
project at pre-determined dates. The reviewer
then documents review findings and provides
written communication and recommendations to both
the steering committee and the project team.
Additionally, some companies may require the
project participation of the companys internal
audit department. The internal auditor is
responsible for assessing and evaluating the
System implementations compliance with either
application, data or technical standards,
controls and procedures. The internal auditor
communicates findings and recommendations to the
steering committee and project management.
22
1.6.1.2 Signoff Project Preparation Phase
  • Purpose
  • The purpose of this task is to obtain signoff
    by the project management, confirming that all
    deliverables are complete and accurate. Once
    signoff has occurred, the project proceeds to
    Phase 2.
  • Steps
  • 1. Schedule a meeting for the signoff of
    Phase 1
  • 2. Obtain approval and formal signoff
  • Result
  • Completed, formal signoff of Phase 1
  • Approval to proceed to Phase 2

23
People involved
  • Steering Committee Member
  • Description
  • The steering committee, the primary source
    for the companys long-term goals and vision,
    must set priorities, approve scope, and resolve
    company-wide issues. The steering committee aids
    in promoting the system implementation project
    throughout the organization.
  • The project sponsor, the SAP Consulting
    Manager (and/or the TeamSAP Coach) and the
    company project manager, must be members of the
    steering committee. The Team SAP Project Manager
    should attend the meetings.

24
  • Project Sponsor
  • Description
  • The project sponsor directly communicates the
    companys long-term goals and visions.
  • The project sponsor is a member of the steering
    committee, and must participate in the regular
    steering committee meetings. The project sponsor
    should participate in the feedback meetings for
    Project Reviews.
  • Ha Team SAP Project Manageer
  • Description
  • Assist the customer project manager in the
    definition and execution of project
    deliverables and the day-to-day management of the
    entire project. The TeamSAP project manager is
    the main liaison for the TeamSAP members
    including the steering committee, project
    sponsor, and partner management as appropriate.

25
  • Customer Project Manager
  • Description
  • Business Process Team Lead
  • Description
  • The PTL manages the effort to analyze and
    document the decomposition of the companys
    business processes, and directs and works with
    the business process team members, owners, and
    users to
  • Develop the system process design
  • Configure the system and validate the design
  • Test and document the system implementation
  • Obtain buy-in from both the business process
    owners and end
  • users

26
  • The PTL also manages the execution of system
    unit testing and
  • integration testing, including
  • Working with the project team to identify
    mission critical business
  • process scenarios
  • Identifying transactions and data to be tested
    managing expected
  • results versus actual results, and reasons for
    differences
  • Assigning follow up tasks to reconfigure and
    retest
  • Tracking of error resolution.

27
  • Are there any questions?
  • Thank you for your attention!
Write a Comment
User Comments (0)
About PowerShow.com