Title: February 21, 2006
1Orleans Parish School Board Accounting, Human
Resources and Financial Management Plan and
Status Report 14
February 21, 2006
2Table of Contents
- Section Page
-
- Working Group Updates
- Financial Management Accounting 2
- Human Resources 5
- Procurement 8
- Information Technology 11
- Facilities Maintenance 16
- Dispute Analysis and Forensics 19
- Appendix A Detailed Workplans
- Schedule A - Financial Management
Accounting 24 - Schedule B - Human Resources
25 - Schedule C - Procurement 28
- Schedule D - Information Technology
29 - Schedule E Facilities Maintenance
30
3Financial Management Accounting
- Post Katrina Key Accomplishments
- Coordinated with insurance carriers to collect
claims for hurricane damages. To date, 28.5M has
been collected. - Community Disaster Loan application was approved
with potential monies of approximately 20M. - Monitored daily cash receipts and disbursement
transactions in each of the Districts bank
accounts. - Developed preliminary projections of school and
other operating expenses as well as anticipated
revenue streams from federal, state and local
governments. Revised pro-forma budget deficit
estimated at approximately 43.3M. - Modified weekly cash flow forecasts for material
changes caused by the post-hurricane environment.
These cash flow forecasts indicate that, based
on current assumptions, the District will run out
of cash in March. - Obtained bond counsel opinion supporting the use
of existing capital project funds to fund
liquidity needs for the school building repair
efforts. - Segregated pre-Katrina payables from post-Katrina
liabilities for go-forward accounting purposes. - Supported payroll team in processing pre-Katrina
payroll in an off-line system as a result of the
damage to the District information systems as
well as continued implementation of interim
payroll processing solution with ADP.
4Financial Management Accounting (cont.)
- Post Katrina Key Accomplishments (cont.)
- Payroll
- Completed and transmitted over 10,000 Form W2s.
- Completed and transmitted approximately 600 Form
1099s. - Updated over 7,000 employee addresses.
- Addressed over 4,000 calls to our call center,
with issues ranging from multiple address
changes, benefits and retirement questions, to
payroll issues. - Developed and implemented a system of metrics to
use in identifying root causes and action items
for use with our call center operations. - Developing the ability to manage the payroll tax
function within the payroll department rather
than in the finance department. - Developing core competency within the payroll
department to handle retirement reporting. This
function is typically handled by the
retirement/benefits department. - Assisted the finance/accounting department in
closing long standing, open, and un-reconciled
issues. - Beginning the transition from ADP to the Munis
payroll system. - Developing, and constantly revising payroll
department quality and internal controls. - Prepared, and are constantly updating the
upcoming vacation/sick payout process. The
payment and distribution process is settled and
ready to go. - With the assistance of the LLA, we have
identified approximately 300 employees with
questionable stipend and assault pay issues,
which amounts will be offset against the
vacation/sick payouts. - Developing processes to go after potential
payroll, stipend, and assault pay overpayments.
5Financial Management Accounting (cont.)
- Key Deliverables to be Accomplished
- Design, implement and permanently staff a
scalable accounting/ finance department for a
reconstituted OPSB system by December 2006. - Design a Treasury/Cash Management system that
incorporates necessary controls to provide
timely and reliable reporting capabilities. - Create a Special Revenue department with
capabilities to develop, budget and timely
process reimbursement claims while complying with
all federal and state regulations. - Complete the termination process for all former
employees including process final payout of
sick/ vacation pay, prepare final W-2s and
reconcile all associated withholdings. - Identify and record all unrecorded liabilities,
compile and validate a complete accounts payable
listing and process all valid claims for payment. - Design and implement Tyler/ MUNIS as a scalable
and reliable financial reporting systems. -
- Develop alternatives to move toward a more
optimal debt structure for the District,
including potential refinancing/refunding options
on 250M of existing indebtedness. Conclude a
successful refinancing of all outstanding bond
obligations. - Obtain/recover all available funds from insurance
policies, Community Disaster Loan and other
Federal Assistance. Complete validation and
subsequent repayment of all outstanding
pre-Katrina liabilities, including
employee-related and vendor claims.
6Human Resources
- Post Katrina Key Accomplishments
- General Employee Communications and HR Operations
- Relocated Call Center to Ashe facility. Continue
to manage Call Center and HR related content on
the NOPS Website to include updating call center
scripts, FAQs, and responding to employees
questions and requests. - Responded to walk-ins and processed employment
verification requests, resignations, retirements,
mortgage/auto loan requests, payroll questions,
student records requests, benefits requests, etc.
- Preparation for Reduction-in-Force for all OPSB
staff on Disaster Leave. - Drafted revised termination notice per OPSB RIF
policy Judges orders - Updated and finalized audit of vacation sick
balances - Finalized offset to vacation sick balances
(i.e., past over payments) - Updated and removed all retirements, voluntary
resignations, Charter School Active OPSB
employees from termination list - Finalized and compiled updated staff addresses
for distributions - Formatted and sent termination list to 3rd-party
vendor for mail outs - Prepared audited files for ADP to process sick
and/or vacation payments to retirees and
employees who voluntary resigned. - Continue to support finance cash flow forecasts
(i.e., payroll costs, benefit expenses,
unemployment benefit projections, workers
compensation costs, sick/vacation balances). - Continue to approve/disapprove and process
administrative employees brought back from
disaster leave. Compile and maintain list of
all employees/salaries (administration
school-based). - Updated preliminary organization charts and OPSB
employee roll-off dates (See Attachment). - Contacted and hired temporary at will employees
as required. - Supporting staffing of Bethune Elementary and
other OPSB schools as required. - At the Boards request, developed a parent
satisfaction survey to be administered to a cross
section of parents at all OPSB schools. - Continue to collect, communicate, and pursue
organizations and individuals who have offered
donations to OPSB to include securing an
undetermined number of computers from the Best
Buy Company.
7Human Resources (cont.)
- Post Katrina Key Accomplishments
- Retirement/Benefits
- Prepared and testified before Senate Committee
for Insurance regarding Retiree Healthcare to
include the development of various analyses (See
Attachments). Followed-up with a Senator
Duplissess to evaluate potential options for OPSB
Retirees. - Worked with Coventry to implement the
Self-Insured health plan. Had documents approved
to fund the claims administration account. - Participated in healthcare mediation between
Coventry and OPSB facilitated by Louisiana
Department of Insurance, resulting in a refund of
the December 2005 increase in retiree premiums.
Testified before the Legislative Audit Advisory
Committee regarding the districts healthcare
costs and was challenged to work with the state
to craft a cost effective solution, particularly
as it relates to retirees. - Approved one year extension for the Hammerman
Gainer Workers Compensation TPA agreement. - Received quotes from two COBRA administrators, as
previous provider we were negotiating with
withdrew once TRO was filed. Provided census
data to provider utilized by Hammerman Gainer
to access viability of their services. Reviewed
quote from FBMC for COBRA and retiree
billing/collection services to determine if an
agreement should be reached or if historical
administration issues should be resolved/closed. - Converted Assault Pay claimants to Workers
Compensation, as appropriate. Working with
outside and plaintiffs counsel to settle claims
and/or receive necessary medical information to
support the continuation of TTD payments. Still
working to finalized the collection process to
recover Unemployment Insurance benefits that were
received by Workers Compensation claimants while
they were eligible or receiving indemnity
payments. - Recommended Workers Compensation firm (Willis of
Louisiana) to conduct actuarial study to
re-establish accrual rates for workers
compensation liabilities. - Communicated with state agencies regarding
employees who were scheduled to be terminated
effective January 31, 2006 and discussed the
impact the TRO would have on retirement plan
participation and benefit processing.
8Human Resources (cont.)
- Key Deliverables to be Accomplished / Next two
weeks - General Employee Communications and HR Operations
- Continue to oversee OPSB in-house call center
website to include updating call center scripts
and website FAQs and responding to researching
employees questions and requests. - Continue to respond to walk-ins and process OPSB
employment verification requests, resignations,
retirements, mortgage/auto loan requests, payroll
questions, student records requests, benefits
requests, etc. Continue to oversee OPSB in-house
call center website to include updating call
center scripts and website FAQs and responding to
researching employees questions and requests. - Continue to respond to walk-ins and process OPSB
employment verification requests, resignations,
retirements, mortgage/auto loan requests, payroll
questions, student records requests, benefits
requests, etc. - Redraft and mail out termination notices as a
result of TRO. - Finalize 2006-2007 organizational charts and the
plan for the estimated release dates for OPSB
employees. - Continue to approved/disapprove and process
employees brought back from disaster leave. - Begin to draft new HR policies and practices
(i.e., stipends, hiring, terminations, leaves,
etc.). - Provide finance with HR expenses to include
health insurance claims paid for last two years,
a SAS 70 report on the internal controls of the
TPA, and preparing a schedule of all employer
retirement contributions by month for all plans. - Prepare HR reports for financial Audit.
- Administer parent satisfaction survey.
- Continue to provide staffing support and
employment processing to schools and central
administration. - Continue to coordinate donor relation activities
and distribution of donated items. - Retirement/Benefits
- Create an RFP for a fully-insured healthcare
provider and work with the State to develop
viable options for continued healthcare,
particularly for retirees. Finalize arrangements
with COBRA administrator and distribute
appropriate notifications to participants.
Schedule meeting with UTNO to discuss the benefit
changes. - Complete critical retirement processing and
submit documentation to TRSL including employer
and employee contributions since September.
Process retirements and submit documentation to
LaSERS and LSERS including employer and employee
contributions since August. - Begin calculating Unemployment Insurance payments
collected by workers compensation and/or assault
pay claimants to determine the amount such
claimants must reimburse OPSB . - Finalize contract arrangements with Temple
Resource Management (UI).
9Procurement
- Post Katrina Key Accomplishments
- Arranged/Coordinated tours of the Council for the
Great City Schools at various school
facility/properties. - Worked with Facilities to properly procure
emergency repairs on nearly all NOPS schools. - Developed and maintained an interim, manual,
non-Oracle based Requisition and Purchasing
process. - Drafted, distributed, received and awarded RFPs
related to the following services - General Contracting Parsons
- Environmental Parsons
- HVAC Johnson Controls
- Custodial and Grounds Sodexho
- Assisted the IT department in the recovery of IT
assets from 3510 General DeGualle. - Assisted in the drafting and distribution of RFPs
for Transportation Services. - Assisted in the drafting and distribution of RFPs
for Food Services. - Assisted in the drafting and distribution of an
RFP for Security Services. - Assisted in the drafting and distribution of a
bid package for the sale of land. - Assisted in the drafting and distribution of an
RFP for an E-rate Service Provider - Discussed proposals related to waste/trash
removal and pest control with a few vendors. - Maintained interim contract management system.
10Procurement (cont.)
- Post Katrina Key Accomplishments (cont.)
- Worked with Real Estate group to procure services
and coordinate moves from Henderson Elementary to
McDonogh 7, then from McDonogh 7 to Arthur Ashe
Elementary. - Work with OPSB General Counsel to terminate
copier/printer leases with Xerox. Replaced with
Imagistics copier/printer leases to support NOPS
sites (Franklin Elementary, McMain H.S., McDonogh
35, Ashe, Bauduit) pursuant to state contract
rates. Agreement runs through June 30, 2006 at
which point it will be up to OPSB discretion to
renew or put out to public bid. - Installed agreement with Allied Waste to provide
waste removal services at current NOPS sites
(Franklin Elementary, McMain H.S., McDonogh 35,
Ashe, Bauduit). Agreement runs through end of
March, 2006. RFP for waste removal services
advertised and distributed on February 14, 2006. - Released, per Emergency Procurement guidelines,
RFPs for the repair and reconstruction of Bauduit
Elementary, Gaudet Elementary (RSD), Ashe
Elementary. - Released, per States Public Bid Policy, RFP for
the repair and reconstruction of Easton Senior
High School on February 17, 2006. - Preparing bid packages for Hynes Elementary as
well as other schools identified by the RSD to
open in August, 2006.
11Procurement (cont.)
- Key Deliverables to be Accomplished
- Continue to exercise joint authority with OPSB,
requiring written concurrence of both parties in
matters of procurement, execution, amendment and
termination of contracts. - Design and develop District procurement policies
and procedures - Ensure consistency with state, local and federal
laws and regulations. - Incorporate best practices from LDE, other
districts, other states. - Codify processes and procedures including a
written code of conduct for employees involved in
purchasing and contracting on behalf of the
District. - Codify areas of authority, delegation and ensure
actions require proper authorization. - Work on all the above in concert with MUNIS
implementation - Design and develop District policies and
procedures involving the bidding process from
informal bids (i.e. price verifications) to
formal Request-for-Proposals. - Design and develop the District Contract
Administration function. - Continued support of Real Estate Group with RFP
process for construction projects.
12 Information Technology (cont.)
- Post Katrina Key Accomplishments
- Oracle Operations
- Delayed the printing and distribution of the
Termination, OPSB and COBRA letters to affected
employees due to Temporary Restraining Order - Delayed the printing and distribution of the
vacation/sick settlement check to 2150 affected
employees due to TRO - Rescheduled the completion of the application of
a technical patch in the Oracle Production
environment to reduce the null values in the
Employee Payroll tables by approximately 50 and
reduction of number of Oracle User IDs (See
financial impact below) - Financial impact is the reduction of the monthly
contract of the Oracle On Demand environment by
an estimated 20 - Continued to manage production related business
requests and issues related to Oracle LINUX
conversion - Continued to revise and execute Oracle shut-down
plan and key milestones, including access to
historical data - Tyler MUNIS Enterprise K-12 Design /
Implementation project - Finalizing NOPS Chart of Accounts and fund
structure - Configured General Ledger, Accounts Payable,
Purchasing and Requisition applications in MUNIS
as well as workflow and security for testing
purposes - Loaded AP vendor master 1099 activity for 2006
in MUNIS - Loaded MUNIS client software and training
materials on key users PCs - Prepared for the cross-walk of General Ledger
budget and actual accounts to MUNIS when the data
is ready for migration - Communicated design framework of the combined AFR
and budget reporting for NOPS, Algiers and the
other charter schools with the LDE LLA and
following up on clarification of NOPS charter
reporting responsibilities
13 Information Technology (cont.)
- Post Katrina Key Accomplishments (cont.)
- Help Desk / PC Support RFP
- Obtained grant commitment from Best Buy for 1500
new PCs - Executed Help Desk / PC support outsourcing
contract - Initiated Help Desk /PC support outsourcing end
user capability - Continue to build NOPS IT customer service
capacity - IT Shared Services capability
- Initiated IT start-up operations for Bethune at
Bauduit - Completed Phase I conversion of IT operations at
Ashe - Continued to meet with each school to finalize IT
costs and budgeting - Continued to support on-going IT operations
- Continued to build NOPS IT business capacity
- Data Center Operations
14 Information Technology (cont.)
- Post Katrina Key Accomplishments (cont.)
- E-Rate Filing and Management
- Completed submission of Year 9 (2006/2007)
request to the SLD - Submitted selective review response letter to the
SLD for Year 8 ( 2005 / 2006) - IT Asset Inventory
- Evaluate potential storage facility for the
transfer of valuable IT assets
15 Information Technology (cont.)
- Key Activities to be Accomplished
- Oracle Operations
- Complete the printing and distribution of the
Termination, OPSB and COBRA letters to affected
employees - Complete the printing and distribution of the
vacation/sick settlement check for 400 Retiree
employees only through ADP - Complete the application of a technical patch in
the Oracle Production environment to reduce the
null values in the Employee Payroll tables by
approximately 50 and reduction of number of
Oracle User IDs (See financial impact below) - Financial impact is the reduction of the monthly
contract of the Oracle On Demand environment by
an estimated 20 - Complete FY 2006 Oracle OnDemand data access and
retention business requirements - Continue to manage production related business
requests and issues related to Oracle LINUX
conversion - Continue to revise and execute Oracle shut-down
plan and key milestones, including access to
historical data - Tyler MUNIS Enterprise K-12 Design /
Implementation project - Finalize NOPS Chart of Accounts fund structure
- Train key users test General Ledger, Accounts
Payable, Purchasing and Requisitions applications
in MUNIS - Configure Budget Grants applications
- Go live with Requisitions, Purchasing, Accounts
Payable General Ledger - Finalize the design framework of the combined AFR
and budget reporting for NOPS, Algiers and the
other charter schools with the LDE LLA - Start the design of the Human Resources and
Payroll applications
16 Information Technology (cont.)
- Key Activities to be Accomplished (cont.)
- Help Desk / PC Support RFP
- Initiate Help Desk / PC support outsourcing end
user capability - Begin to communicate PC Support Help Desk process
to end users - Continue to build NOPS IT customer service
capacity - IT Shared Services capability
- Continue to meet with each school to finalize IT
costs and budgeting - Continue to support on-going IT operations
- Continue to build NOPS IT business capacity
- Data Center Operations
- Continue to implement VOIP telephone capability
at schools along with upgrades to the Cox Centrex
system - Continue to document NOPS data center assets at
Cox facility to support disaster recovery
planning - Implement initial off-site storage rotation with
Iron Mountain - Student Information Systems
- Continue to conduct on-site SASI training and
operations support for all charter and NOPS
schools, including SIS, Master Schedule, and
Grading
17 Facilities Maintenance
- Key Accomplishments
- McMain
- Met with structural engineer to assess damage to
McMain auditorium. Installed tile in the kitchen.
Continuing further repairs in the kitchen area.
Cafeteria area made available to principal and
faculty. Met with Principal Frick and Tulane
resources to discuss volunteer projects. Plan is
to paint hallways and stairwells during
March/April time period. - Capdau
- Met with Principal Verrett and Tulane resources
to discuss volunteer projects. Plan is to
address 5 projects, including paint first floor
Physical Education rooms paint first floor
storage rooms paint second floor balcony
establish garden area in backyard/parking lot
design and establish flower boxes in front of
building repaired refrigerator gaskets,
electrical components. - Banneker
- Began repairs, including flashing on roof, roof
vents, ceiling tiles and cleanout of kitchen
area. Performed FEMA Life Safety walk-through on
February 15th. Performed scope clarification
walk-through with Associates general contractor. - Lusher
- Progressed work on punch list, including
re-hanging white boards, shaving sticky doors
and installing shelving. Proposed tile repair
solution to Principal Reidlinger. Plan to
perform necessary work during Mardi Gras holiday. - Ashe
- Awarded contract and continue to supervise
contractor work. - Bauduit
- Awarded contract. Currently conducting final
preparations for the school opening on Feb. 20. - Fortier
- Completed removal of gym floor. Began preparation
for remediation effort on the 4th and 3rd floors
that included full containment on the 4th floor
and initial efforts on 3rd floor. Covered room
contents on the 4th floor. Initialized the
electricity on one meter. Spoke with Entergy on
multiple occasions over the last 3 weeks. As of
Feb. 16, we are waiting on the second meter to be
energized which should be completed by Feb. 17. - Debris Removal
- Debris removal commenced the week of Feb 13.
- McDonogh 35
- School opened January 17. Ongoing restoration of
the asset continues in a phased
approach. Currently removing asbestos floor tile
throughout to be followed by restoration. Walk-in
refrigerator/freezer removal to commence
immediately. A kitchen consultant will visit the
school on Feb. 17 to scope replacement for
walk-ins and reach-ins. In process of getting a
mechanic to assess/repair inoperable
ovens/steamer. Identified further debris items to
be removed from first floor due to standing water
damage/mold.
18 Facilities Maintenance (cont.)
- Key Accomplishments
- Benjamin Franklin High School
- School opened on January 17. Ongoing restoration
of the asset continues in a phased approach.
Drywall, painting, and floor tile continues.
Cafeteria main hall was delivered this week.
Kitchen is not available. Gymnasium flooring
being ordered on Feb. 20. Walk-in
refrigerator/freezer removal to commence
immediately. A kitchen consultant will visit the
school on Feb. 17 to scope replacement for
walk-ins and reach-ins. - Wicker
- Identifying a structural engineer to assess the
exterior wall. Restoration continues at the
school in a phased approach. - Turead
- Awaiting phased completion schedule from
contractor. - Craig
- Awaiting phased completion schedule from
contractor. Performing GC walkthrough on Feb. 16. - Easton
- Performed Detailed Assessment/FEMA walkthrough of
asset. Public notice to occur on Feb. 17. - McDonogh 15
- Completed detailed assessment.
- Gaudet
- Completed detailed assessment and awarding bid to
contractor. - Various
- Preparing Fischer and Rosenwald for April 1
opening. - Began detailed assessment of Sarah T. Reed,
McNair and McDonogh 28 and performed initial
walk-throughs of Haley and Hansberry. - Completed emergency repairs at Lafon, Kennedy,
Hughes, McDonogh 42, Bradley, Lake Area, Martin
Luther King, Bienville, Waters, Cohen, Abramson,
Morial, Lawless, Hardin, New Orleans Center for
the Education of Adults. Verifying the completed
emergency repairs for payment. Reviewed and
updated emergency repair scopes and continued
work confirmation.
19 Facilities Maintenance
Facilities Maintenance (cont.)
- Key Deliverables to be Accomplished
- Perform Real Estate Construction and Repairs -
CM/PM - Complete building assessments for 124 schools
- Create RFPs, review bids, and award the winning
bid - Monitor the progress of GC, Environ, HVAC, and
Janitorial - Work with FEMA and DAF on Scope of Repairs
- Develop a school readiness checklist to be used
for each school - FEMA project work sheets, building assessments,
and cost estimates - OPSB School Openings - FM
- Develop custodial, grounds, and maintenance
contracts - Obtain and maintain all facilities maintenance
programs - NOPS Master Planning Strategic Planning
- Master planning, community Development
- RF AE firms, manage process
- Surplus property transaction program
- Create process program to identify and sell
surplus land
20 Dispute Analysis and Forensics
- Key Accomplishments
- Confirmed property ownership and continued to
obtain supporting documentation - Determined accurate property listing of all NOPS
properties and continued to compile all
supporting documentation for each property from
the Orleans Parish Notorial Archives. - Continued to advance insurance claims and
inventory process - UBS (Insurance Adjusters) has completed 67 of
their inspections. - AAA (Capital Asset Valuation) has completed 36
of their inspections. - Continued to meet with FEMA and provide
documentation to build Project Worksheets. - Confirmed ten additional project worksheets for
reimbursements of approximately 1.8 million.
Eight of the ten project worksheets approved were
related to portable buildings and two covered
temporary repairs. - Worked with building contractors to reconcile
contractor bidding/invoicing with FEMAs
bidding/invoicing requirements to ensure maximum
reimbursement for eligible reconstruction costs. - Compiled, created, and refined school
reconstruction (temporary and permanent repairs
caused by Hurricane Katrina) documentation for
submittal to FEMA. - Continued to manage the vehicle securitization
process - Created a vehicle hotline (504-304-3800) for
former NOPS employees to call and report the
vehicles in their possession or displaced around
the city. - Registered with EBay in order to sell damaged
buses in the coming weeks. - Met with Salvage Sale in Houston to discuss
potential sales of damaged busses.
21 Dispute Analysis and Forensics (cont.)
- Key Deliverables to be Accomplished
- Property
- Investigate ownership of up to 200 properties
with the Office of Conveyance - Document titles to those properties in which we
have ownership - Research all Section 16 lands owned by District
and royalty entitlements - Work with Real Estate in divesting of unnecessary
properties - Ensure all FEMA PW worksheets are complete for
properties owned - Work with Real Estate to declare certain
properties for Alternative use for FEMA per
direction of State and Board of Education - Vehicles
- Establish number of vehicles owned, vin numbers
and locations - Document ownership of vehicles
- Determine which vehicles are damaged and which
are salvageable - Find Titles and assign to inventory
- Make recommendation for divestiture of vehicles
- Identify those vehicles missing, file police
reports - Negotiate with Insurance Carriers for payment
- Ensure all FEMA PW worksheets are complete for
vehicles owned and damaged - Asset Inventory
- Perform assessment of each District property and
take detailed inventory of all assets
22 Dispute Analysis and Forensics (cont.)
- Key Deliverables to be Accomplished
- Contents FEMA claim
- Perform assessment of cost to repair/replace
contents of each District building. - File Documents for Project Worksheets for FEMA
- Fixed Assets
- Obtain and analyze a check register for the past
four years - Recreate asset list based on check register
- Reconcile with inventory
- File Documents for Project Worksheets for FEMA
- Temporary Classrooms
- Coordinate placement of classrooms
- Coordinate FFE for temp classrooms
- File Documents for Project Worksheets for FEMA
23 Dispute Analysis and Forensics (cont.)
- Key Deliverables to be Accomplished
- FEMA Documentation
- Manage all document request for FEMA and prepare
documentation for OIG audit - File, document and classify all FEMA Project
Worksheets and documentation - Utilize FTP site to streamline submission process
- Loss Payees
- Determine contractual obligations to loss payees
- Coordinate with Loss Payees to retrieve equipment
per contractual obligations - Negotiate and recommend settlements with Loss
Payees - Insurance Company Claims
- Prepare Proof of Loss for Insurance Companies
- Coordinate inspections for all insurance
adjusters and their representatives - Negotiate claim, manage claim efforts and
document all repair work in compliance with the
insurance claim - Expert witness testimony in the event litigation
becomes necessary - Cash Reconciliation and Overall Recordkeeping
- Prepare documentation to support inflows and
outflows of cash - Prepare reports for State and Board of Education
documenting uses of funds - Maintain data repository
24Appendix
25Schedule A Financial Management Accounting
26Schedule B Human Resources
27Schedule B Human Resources (cont.)
28Schedule B Human Resources (cont.)
29Schedule C Procurement
30Schedule D - Information Technology
31Schedule E - Facilities Maintenance
Deliverables