P1246990946hCZwr - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

P1246990946hCZwr

Description:

Expand PM training resources to mature PM skills in the agencies ... Service Directors and Deputy Secretaries to establish Secretariat briefings to ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 19
Provided by: jennyh
Category:

less

Transcript and Presenter's Notes

Title: P1246990946hCZwr


1
ITIB Recommended Technology Investment Projects
(RTIP) Report for 2004 Lessons Learned
2
RTIP Lessons Learned Agenda
  • Data concerns and recommended actions
  • Process concerns and recommended actions
  • Report format and content suggested changes
  • Next Steps

3
Recap - 2004 Agency IT Strategic Planning Data
  • Agency Profile Strategic Direction
  • Agency Strategic Plan
  • Mission,
  • Core Business Activities,
  • Key Customers
  • Key Activities Outcomes
  • Critical Issues
  • IT Vision, Strategies and ITIM Practices
  • Major IT Projects
  • Description, Cost, Dates
  • Business Case Evaluation Questions
  • Funding
  • Related Procurements
  • Strategic Alignment
  • Major IT Procurements
  • Non-major IT Projects and Procurements

4
RTIP Project Data Concerns
  • Variances in Project Data
  • Completeness
  • Consistency
  • Accuracy
  • Currency
  • Feasibility
  • Information Affected
  • Scope definition
  • Business case
  • ROI calculations
  • Project schedules
  • Proposed technical solutions

5
RTIP Data Improvement Recommendations
  • Strengthen major IT project planning process
  • Develop and implement IT Strategic Planning and
    Portfolio Management Standard
  • Implement PM Standard
  • Acquire and implement project cost estimation
    tool
  • Expand PM training resources to mature PM skills
    in the agencies
  • Expand PMD staff to support project mentoring
    program

6
Recap - 2004 RTIP Report Selection Process
Code of Virginia Enterprise Architecture Strategic
Plan for Technology Best Practices
ITIB Evaluation Criteria
Agency IT Strategic Plans
Weighted Ranking
Secretariat CIO Prioritization
ITIB Approval
Evaluation Criteria Scoring
7
Recap - ITIB Approved Project Selection Ranking
Criteria
  • Strategic Alignment
  • COV Strategic Plan for technology initiatives
  • COV Enterprise Architecture (Enterprise) Business
    Strategies
  • Agency Strategic Direction (Key Activities
    Critical Issues)
  • Benefits to the Commonwealth
  • Benefits chronically underserved stakeholders
  • Increase public protection, health, education,
    environment, or safety, improve customer service,
    or increase citizen access
  • Positive return on investment
  • Support legal or regulatory requirements
  • Risk
  • Cost
  • Complexity
  • Risk Management
  • Funding Requirements
  • Cost reasonableness
  • Percent of the project funding from Non-state
    funds
  • Funding risk
  • Past Performance by Agency
  • Agency rating average and specific project
    rating on the Dashboard
  • Agency ITIM practices
  • Technical Feasibility
  • Stated Approach
  • Proposed approach based upon proven technology

8
ITIB Process Improvement Goal
  • Assist agencies of the Commonwealth of
    Virginia in the development of funding
    alternatives for project planning, with the goal
    of obtaining more accurate preliminary plans and
    cost estimates.

9
ITIBs Suggested Process Improvement
Recommendations
  • Funding for the project planning phase of major
    IT projects should be centralized and exist
    separately from funding for project development.
    Parallel Commonwealth Transportation Boards
    process for road construction projects.
  • Upon the recommendation of the CIO, the ITIB
    should consider awarding planning funds to
    proposed major IT projects meeting specified
    criteria. Agency and VITA staff would use
    awarded funds to conduct the detailed analyses
    necessary to produce appropriate scope and cost
    estimates, as per CIO/ITIB guidance.

10
ITIBs Suggested Process Improvement
Recommendations (Continued)
  • Use the current Virginia Technology
    Infrastructure Fund as the vehicle for awarding
    planning funds. Funds for this purpose would be
    refreshed annually via the Appropriation Act,
    with the ITIB reporting on its use and results as
    part of the annual September 1 report.
  • When a project is approved as a priority
    project, the Board recommends that the
    development funds for each major IT project be
    specifically set out in the Governors Executive
    Budget and the Appropriation Act.

11
2004 RTIP Report Comments - Implemented
  • Add Commonwealth strategic imperatives and goals
    we are trying to achieve
  • Recommended Action Taken Verbiage was modified
    for final report
  • Status on Top 5
  • Recommended Action Taken Information was
    provided at the August 11th Board Meeting
  • Suggested wording changes on collaboration report
  • Recommended Action Taken Verbiage was modified
    for final report

12
2004 RTIP Report Comments Implemented(Continued
)
  • Remove the ROI from the reports
  • Recommended Action Taken Project Planning
    Approval
  • took place too early in the project life-cycle to
    provide valid
  • ROI Calculations. ROI was removed from the
    reports
  • Provide agency priorities in the report
  • Recommended Action Taken Agency priority was
    added to
  • the Secretariat Rank Report
  • Select Top 30 versus 20
  • Recommended Action Taken PTIP identified 27
    projects

13
2004 RTIP Report Comments Implemented(Continued
)
  • Only projects requesting funds should be listed
    on the report
  • Recommended Action Taken Highlighted projects
    needing
  • funding but included all projects
  • Remove PPEA Designation
  • Not Recommended Important to know PPEA
    opportunities in
  • light of lack of funding stated

14
RTIP ReportFormat and Content Recommendations
  • Include projects only if a Business Case has been
    submitted
  • Recommended Action Implement for next years
    report
  • Include projects that are being or have been
    terminated/suspended in a separate section (ex.
    EAGLES)
  • Recommended Action Implement for next years
    report
  • Identify long term debt funding (Treasury Loans
    or Bonds, etc.)
  • Recommended Action Adequate time and
    information not available for this years
    report. Recommend this be considered for future
    reports

15
RTIP ReportFormat and Content Recommendations
(Continued)
  • Align RTIP process with budget process
  • Recommended Action Show total funds needed
    and when over a six year period
  • Refocus RTIP Report for 2005
  • Recommended Action
  • Divide report into three parts
  • status quo or current state of major projects in
    the Commonwealth
  • project expenditures to date
  • projects approved and ready to move into
    development/implementation vs. projects approved
    for planning

16
RTIP ReportFormat and Content Recommendations
(Continued)
  • Refocus RTIP Report for 2005 (continued)
  • Recommended Action
  • Evaluate other options
  • Governors Initiatives
  • Council on Virginias Future
  • Commonwealth of Virginia Strategic Plan for
    Technology
  • PPEA Reengineering Initiatives
  • VITAs Business Plan
  • ITIB has not reviewed pre-ITIB active major
    projects approved prior to establishment of ITIB
  • Recommended Action Perform IVV audit on all
    active major IT
  • projects Target Completion date is 1/11/2005

17
Next Steps - Proposed Action Plan for ITPRC
Approval
  • PMD to proceed with implementation of data
    improvement recommendations
  • ITPRC to recommend Board approval for the budget
    request submitted by the ITIB Finance Committee
    for 7 million dollars for the Virginia Technology
    Infrastructure Fund to support project
    preliminary planning in the agencies
  • ITPRC to recommend Board assign ITIB Legal and
    Legislative Committee the responsibility for
    working with DPB and the General Assembly to
    obtain funding for this budget amendment
  • ITPRC to develop criteria for granting planning
    funding from the Virginia Technology
    Infrastructure Fund to agencies
  • ITPRC to identify 2005 RTIP reporting
    requirements
  • PMD to report Active Major IT Project IVV
    results to the ITPRC and Board
  • Enterprise Service Directors and Deputy
    Secretaries to establish Secretariat briefings to
    include active Major IT Projects in their
    enterprise project portfolio

18
RTIP Report Points of Contact
  • Judy Marchand
  • VITA Project Management Division
  • 804-786-4392
  • judy.marchand_at_vita.virginia.gov
  • or
  • Constance Scott
  • VITA Project Management Division
  • 804-371-5927
  • constance.scott_at_vita.virginia.gov
Write a Comment
User Comments (0)
About PowerShow.com