ILC Status, Progress and Plans

1 / 30
About This Presentation
Title:

ILC Status, Progress and Plans

Description:

ILC Status, Progress and Plans – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 31
Provided by: geral163

less

Transcript and Presenter's Notes

Title: ILC Status, Progress and Plans


1
ILC Status, Progress and Plans
  • Barry Barish
  • GDE / Caltech

2
Global Effort on Design / RD
Snowmass 49 GDE members
--------- Present GDE Membership
Americas 22 Europe 24 Asia
18 About 30 FTEs
EU
US
Asia
2003? 7?
Joint Design, Implementation, Operations,
Management Host Country Provides Conventional
Facilities
3
GDE RDR / RD Organization
FALC
ICFA
FALC Resource Board
ILCSC
GDE Directorate
GDE Executive Committee
GDE R D Board
GDE Change Control Board
GDE Design Cost Board
Global RD Program
RDR Design Matrix
ILC Design Effort
ILC RD Program
4
Designing a Linear Collider
Superconducting RF Main Linac
5
Luminosity Beam Size
  • frep nb tends to be low in a linear collider
  • The beam-beam tune shift limit is much looser in
    a linear collider than a storage rings ? achieve
    luminosity with spot size and bunch charge
  • Small spots mean small emittances and small
    betas sx sqrt (bx ex)

6
Achieving High Luminosity
  • Low emittance machine optics
  • Contain emittance growth
  • Squeeze the beam as small as possible

5 nm
Interaction Point (IP)
7
Parametric Approach
  • A working space - optimize machine for
    cost/performance

8
The Baseline Machine
31 km
20mr
ML 10km (G 31.5MV/m)
RTML 1.6km
BDS 5km
2mr
e undulator _at_ 150 GeV (1.2km)
R 955m E 5 GeV
x2
not to scale
9
Baseline to a RDR
2006
July
Dec
Jan
Bangalore
Frascati
Vancouver
Valencia
Freeze Configuration Organize for RDR
Review Design/Cost Methodology
Review Initial Design / Cost
Review Final Design / Cost RDR Document
Design and Costing
Preliminary RDR Released
10
Memos on Cost Confidentiality
  • ILC-GDE Cost Disclosure Rules
  • Guidelines for Area System, Technical and Global
    Group Leaders for discussing costs during
    parallel sessions at Vancouver
  • Distributed to GDE members prior to VLCW06 to
    serve as guidance for discussions at this meeting
    and general policy as costing evolves

11
Linear Collider Facility
Main Research Center
Particle Detector
30 km long tunnel
  • Two tunnels
  • accelerator units
  • other for services - RF power

12
Regional Differences
  • Tunnel Diameter
  • Both tunnels are 5 meter diameter (Fixed)
  • 5 meters in Asia 7.5 meters elsewhere between
    tunnels (for structural reasons)
  • 5 meters between tunnels required for shielding

13
Baseline Features Electron Source
  • Electron Source Conventional Source using a DC
    ----- Titanium-sapphire laser emits 2-ns pulses
    that knock out electrons electric field focuses
    each bunch into a 250-meter-long linear
    accelerator that accelerates up to 5 GeV

14
Baseline Features Positron Source
  • Positron Source Helical Undulator with
    Polarized beams 150 Gev electron beam goes
    through a 200m undulator making photons that hit
    a 0.5 rl titanium alloy target to produce
    positrons. The positrons are accelerated to
    5-GeV accelerator before injecting into positron
    damping ring.

15
6 Km Damping Ring
Requires Fast Kicker 5 nsec rise and 30 nsec fall
time
6km
The damping rings have more accelerator physics
than the rest of the collider
16
Damping Ring - Design Issues
Electron Cloud
  • Ecloud Threshold of electron cloud, 1.4x1011
    m-3.
  • Ion Feedback system can suppress for 650 MHz
    (3ns spacing),
  • Number of bunch in a train 45, and gap between
    trains 45ns.

17
SRF Cavity Gradient
Cavity type Qualifiedgradient Operational gradient Length energy
MV/m MV/m Km GeV
initial TESLA 35 31.5 10.6 250
upgrade LL 40 36.0 9.3 500
Total length of one 500 GeV linac ? 20km
assuming 75 fill factor
18
Superconducting RF Cavities
Chemical Polish
Electro Polish
19
Beam Delivery System
Baseline
  • Requirements
  • Focus beams down to very small spot sizes
  • Collect out-going disrupted beam and transport to
    the dump
  • Collimate the incoming beams to limit beam halo
  • Provide diagnostics and optimize the system and
    determine the luminosity spectrum for the
    detector
  • Switch between IPs

20
Detectors for the ILC
  • Large Scale 4p detectors with solenoidal magnetic
    fields.
  • In order to take full advantage of the ILC
    ability to reconstruct, need to improve
    resolutions, tracking, etc by factor of two or
    three
  • New techniques in calorimetry, granularity of
    readout etc being developed

21
RDR Cost Estimating
  • 500 GeV BCD machine essentials for 1 TeV
  • Follow ITER Value CERN CORE model for
    International Projects
  • Provides basic agreed to costs common value
    in-house labor (man-hr)
  • RDR will provide information for translation into
    any countrys cost estimating metric, e.g. Basis
    of Estimate gt contingency estimate, in-house
    labor, GA, escalation, RD, pre-construction,
    commissioning, etc.
  • Assumes a 7 year construction phase

22
ILC Cost Estimate
  • Based on a call for world-wide tender
    lowest reasonable price
    for required quality
  • Classes of items in cost estimate
  • Site-Specific (separate estimates for each site)
  • Conventional global capability (single world
    est.)
  • High Tech cavities, cryomodules, regional
    estimates
  • Cost Engineers will determine how to combine and
    present multiple estimates
  • WBS WBS Dictionary Costing Guidelines are
    mature enough - cost estimating is underway

23
Cost Roll-ups
e- e damping RTML main
BDS source source rings
linac
Area Systems
Technical Systems  
Vacuum systems
Magnet systems
Cryomodule
Cavity Package
RF Power
Instrumentation
Dumps and Collimators
Accelerator Physics

Global Systems
Commissioning, Operations Reliability
Control System
Cryogenics
CFS
Installation
24

Vancouver Cost Data
25

Conventional Facilities
26
RF Unit Cost
27
Example of Problems to Work
  • Europe
  • scaled TESLA
  • Asia
  • industrial studies
  • Americas -
  • in-house engineering
  • big swing!

28

Civil Engineering Site Dependence
29
Whats Next on Costing?
  • Optimize cost/performance and continue to
    complete estimates based on current design
  • Validate the data we have
  • Pick cost drivers within systems study those
    costs, the requirements for those items, etc
  • Select a finite number of potential baseline
    changes that can save and analyze the
    cost/performance benefit.
  • We are making schedule of reviews and milestones
    for this process. EC-RDR Mgt will meet every
    month face-to face through Valencia. The work
    will be done through area, technical and global
    groups who will report at these meeting.
  • We plan to have internal costing and drafts of
    RDR Report ready for Valencia with the draft
    report ready for release early 2007.

30
Next Steps
  • Complete Reference Design by end of 2006
  • Complete concept documented in three volumes
  • Reference Design Report (RDR) 250 pages
  • Detector Concept Report (DCR) 250 pages
  • Companion Volume 25-50 pages
  • Costing (20 level ??)
  • Host Costs to Site Machine (regional costing)
  • Value Costing for shared components
  • Model for Work Packages divided Regionally
  • Next Year Engineering Design Phase
  • RD - demonstrations, optimize cost/performance,
    industrialize
  • Technical Design (2-3 years)
  • Siting Management
Write a Comment
User Comments (0)