3Strategic Plan Review
- Process begun in late 2004 to create 3-5 year
plan to address future of pool - Evaluated various options
- Continue status quo (eventual closure)
- Merge with another local pool
- Renovate
- Surveys and meetings to gauge membership
indicated strong desire to keep pool open and to
improve physical plant - After careful consideration of alternatives, SPC
recommended developing renovation plan
4Physical Condition
- Pool was built in 1968 and is at a point where it
needs renovation to extend its service life - Repair damage to pools beam
- Replacement of metal drainage piping
- Pool deck has shifted causing drainage issues and
maintenance requirements - Tiles/coping stones replaced each season
- Drainage issues causing damage to decks and
compromises cleaning filters - At a minimum, Montgomery County is requiring a
new whitecoat (plastering) prior to opening in
2007. Minimum cost of about 40K (225 per
family)
5Renovation Process
- Board interviewed several pool architects to
explore rebuild/renovation options. - Opened line of credit with local bank, Harvest
Bank to pay for Phase I (architect study, new
tables and chairs, renovation of party
room/nursery school) of renovation plan - Renovation committee interview 5-6 potential
contractors - Renovation committee settled on company that
performed Country Glen and Lakewood CC
renovations, Catania Construction. Catania came
well recommended and was only company willing to
create a renovation plan with detailed and
itemized costs. - Harvest Bank willing to fund long-term renovation
plan with flexible terms
6Renovation Phases
- Phase I New chairs, tables and umbrellas plus
renovation of clubhouse/nursery school - complete - Phase II Renovation of pool shell, new deck,
revamped bathrooms, new baby pool, new entrance,
etc. Prior to opening of 2007 season - Phase III As membership increases, Sport court
surface to replace current basketball court, etc.
7Renovation Plan
- Phase II New pool infrastructure
- Repair the beam. Double amount of estimated cost
is included in budget - New pool deck
- New whitecoat
- New tiles and coping stones
- Replace feed and drain pipes
- New filter system better sized for pool
- New deck drains
- New guard chairs, ladders, skimmers
- New underwater lights
- Zero grade entry ramp
- Extend diving well to meet compliance
requirements
8Renovation Plan
- Phase II Attractive new baby pool
- Install new 30 x 30 zero grade entry baby pool
- Two water features (pool toys)
- New pool deck
- Terraced patio for better sightlines to main pool
- New 48 high fence
- Regrading of current playground with better
access for members
9Renovation Plan
- Phase II Bathrooms
- New seamless, solid color non-slip flooring in
both bathrooms - New toilet partitions in ladies room
- New shower partitions in ladies room
- New lighting and ventilation in both bathrooms
- New changing stall partitions in ladies room
- New vanity tops, sinks and fixtures
- Fresh paint
10Renovation Plan
- Phase II New and more welcoming entrance
- New entry gate
- New weatherproof guard station counter
- Outdoor phone jack, electric circuit, outlets and
ceiling fan - Weatherproof storage cabinet
11Renovation Plan
- Phase II Fun, asked-for features
- Pool slide to compliment our existing diving
boards - Concession stand
- Handsome grill area with refrigerator and sink
- Freshening of pergola area
12Renovation Plan
- Phase II Physical plant improvements
- New and attractive 6 high perimeter fence
- Improve parking lot drainage to prevent future
damage to pool and pool deck - New outdoor lighting
- Remove existing planters to give pool and more
open feel and improve space utilization - Repair retaining wall near current entrance
13Cost Estimate Phase II
- Pool infrastructure - 300K
- New baby pool, patio, fence and terraced
playground- 128K - New entrance - 28K
- Fun, asked-for features - 39K
- Physical plant improvements - 147K
- Contingency - 31K
- Total - 673K
14Capital Requirements Phase I II
- Phase I - 105K used in line of credit
- Renovations to party room/nursery school - 35K
- New pool furniture and umbrellas - 26K
- Architects study - 10K
- Safety modifications to wood deck, volleyball
court and basketball court - 20K - Additional maintenance expenses due to age of
pool - Phase II - 673K
- Total estimated capital requirement 775K
15Financing Phase I II
- Potential lenders have indicated a willingness to
structure our loan to keep dues increases at a
minimum. - Goal is to raise 100K initial payment through
assessment and fundraising - Maximum assessment of 750 per family member and
500 per empty nesters and singles
16Our Pool Neighbors
- Our neighbors, Country Glen, Potomac Woods and
Regency Estates are all approximately the same
age as MSC. - MSC is the only unrenovated pool amongst our
neighbors. - Potomac Woods and Country Glen renovated their
pool shell while Regency Estates put in a new
pool. - Potomac Woods is at capacity with some members
looking to move to a renovated MSC. - We are trying to keep our bond, assessment and
dues competitive with our neighbors
17Pool Comparison
18Why Renovate?
- Make the pool the center of the community again
- To attract new families as they move into our
neighborhoods and increase membership to the
point where we are self-sustaining again. - The pool will be as nice or nicer than other
surrounding pools - There is something for everyone in the renovation
- Make the pool a great place to bring family and
friends - Create an attractive environment for parties and
get-togethers - Help support the high real estate values of our
homes with a vibrant local pool - Continue the rich legacy of the Montgomery County
pool that has produced Olympic-caliber swimmers
19Ideas For Post-Renovation Marketing
- Placement of news articles in local papers such
at the Montgomery Weekly, Gazette, etc. - Attempt to get local news coverage
- Track renovation progress through our website,
build excitement - Pre-season open house for new members
- Kick-off party for members, friends and guests
- Walk-throughs with local real estate agents
- Mailings to new households
- Olympic celebration with our Olympic stars
- Propose end-of-school year parties at our local
schools - One week free trial memberships
- Membership incentives for neighbor referrals
- Other ideas?
20Vote for Renovation
Resolved That the Board of Directors of the
Montgomery Square Copenhaver Swim Club, Inc. (the
Club) is authorized 1) To proceed with a
renovation of the Clubs pool along the lines
recommended by the Board at the October 17, 2006
annual meeting of members of the Club with a
maximum expenditure of 700,000. 2) To impose
a special assessment on all members of the Club
of a maximum of 750 per family member and 500
per empty nester or single to help pay for such
renovation.
21Election of Board
- Tom Gebler President
- Sean McCarthy Secretary
- Rick Matta Treasurer
- Tom Gira Operations
- Laura Glynn Marketing
- Rebecca Cornelius Swim Team Rep
- Pat Burns Membership
- Rich Meyer At Large
- Trish Regan At Large
- Jim Baldwin At Large
- Mary Parker At Large
- Donald Klenk At Large
22Election of Board
- After many years as MSC Treasurer, Rick Matta is
leaving the board. Rick has agreed to stay on to
assist in a transition to a new treasurer. - The board needs a volunteer to replace Rick as
Treasurer
23Questions/Comments?