Title: MASTER PRODUCTION SCHEDULING


1
MASTER PRODUCTION SCHEDULING
  • The Master Production Schedule
  • The Rough-cut Capacity Plan

2
CORE MRP II
MANUFACTURING RESOURCE PLANNING
3
AGGREGATE VERSUS DETAILED FORECASTS (Review)
  • Use aggregate forecasts for planning medium-range
    overall production levels.
  • High long-range forecast accuracy
  • Detail not needed for planning long-range
    resource use (labor, inventory, etc.)
  • Use detailed forecasts for initial detailed
    short-range Master Production Schedule (MPS)
  • Detailed forecasts reasonably accurate for this
    time frame
  • Need product-specific detail for MPS

4
FROM THE AGGREGATE PLAN TO THE MPS
  • Suppose that Export TVs, Inc. has the following
    production plan for the next six months
  • If they make three models, the MPS for January
    might look like

5
THE MASTER PRODUCTION SCHEDULE
  • An MPS starts with a forecast and a beginning
    inventory balance

6
THE MASTER PRODUCTION SCHEDULE
  • Inventory is projected forward until a shortage,
    or net requirement, occurs

7
THE MASTER PRODUCTION SCHEDULE
  • Production is scheduled to be completed (the MPS
    is a planned finish time) to cover the shortfall

8
THE MASTER PRODUCTION SCHEDULE
  • A planned start time the planned order
    release is determined based on lead time (here
    it is one period)

9
THE MASTER PRODUCTION SCHEDULE
  • The process continues until the product is
    scheduled

10
THE MASTER PRODUCTION SCHEDULE
  • The other product is scheduled the same way

11
THE MASTER PRODUCTION SCHEDULE
  • To check the feasibility of the MPS, we need to
    check the capacity requirements

12
ROUGH-CUT CAPACITY PLANNING A FIRST CHECK ON
THE MPS
  • Need to see if MPS is feasible
  • RCCP finds approximate capacity needs in each
    workcenter given the MPS
  • Quick-and-dirty reality check
  • If capacity overloads, redo MPS

13
THE "ROUGH-CUT" ROUTING
  • The Rough-cut" routing for a product lists
  • Where it is processed
  • Resources needed
  • Per batch or per setup
  • Per unit after workcenter is setup

14
THE ROUGH-CUT PLAN
  • The routing is applied to the planned order
    releases to obtain the capacity plan

15
THE ROUGH-CUT PLAN
  • The routing is applied to the planned order
    releases to obtain the capacity plan

16
THE ROUGH-CUT PLAN
  • The routing is applied to the planned order
    releases to obtain the capacity plan

17
THE ROUGH-CUT PLAN
  • The routing is applied to the planned order
    releases to obtain the capacity plan

18
THE ROUGH-CUT PLAN
  • The routing is applied to the planned order
    releases to obtain the capacity plan

19
THE ROUGH-CUT PLAN
  • The routing is applied to the planned order
    releases to obtain the capacity plan